First Notice | 5/14/2019 | 5/14/2019 | 6/7/2019 | | DONE |
Jim Storey
|
|
|
mailed 6-10
|
BLD-Final | 5/10/2019 | 5/14/2019 | 5/14/2019 | P | PASS |
Jim Storey
|
|
|
John Phone #: ###-####
|
DOC - Permit Finaled | 5/14/2019 | 5/14/2019 | 5/14/2019 | P | PASS |
Jim Storey
|
|
|
|
FIRE-Final Inspection | 5/13/2019 | 5/14/2019 | 5/14/2019 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed.
John Phone #: ###-####
|
FIRE-Final Inspection | 5/10/2019 | 5/13/2019 | 5/13/2019 | P | CANC |
Troy Cobbley
|
|
|
Electrician is not done yet. To be rescheduled per John Phone #: ###-####
|
BLD-Final | 5/9/2019 | 5/10/2019 | 5/10/2019 | A | NR |
Jim Storey
|
|
|
John Phone #: ###-#### fire c/n
|
FIRE-Final Inspection | 5/9/2019 | 5/10/2019 | 5/10/2019 | A | FAIL |
Troy Cobbley
|
|
|
Provide annual inspection for the fire extinguisher and provide exit sign/emergency light/exit discharge as per the approved plans.
John Phone #: ###-####
|
Issue PAID IN FULL permit | | | 4/23/2019 | | DONE |
|
|
|
|
Routing - FIRE | 4/8/2019 | 4/8/2019 | 4/8/2019 | | PASS |
Mark Scharfen
|
|
|
IFC Final Review 04.08.2019.pdf uploaded.
|
Plan assigned to (JHB) | 3/28/2019 | 3/28/2019 | 4/8/2019 | | PASS |
Joe Bruce
|
|
|
04/12 (2nd Rev) 04/04 (L2) - Peterbuilt Racking, ePlan (Fire)
|
Plan resubmittals received | | | 4/8/2019 | | DONE |
Joe Bruce
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/8/2019 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 4/8/2019 | | DONE |
|
|
|
MET (JALDERSON@JGPETE.COM)
NEED
GC FORM
REVISED VALUE
|
Routing - FIRE | 3/28/2019 | 3/28/2019 | 4/4/2019 | | FAIL |
Mark Scharfen
|
|
|
IFC 1st Review 04.04.2019.pdf uploaded and emailed to applicant.
|
1st review completed | | | 4/4/2019 | | FAIL |
Joe Bruce
|
|
|
|
Plan resubmittals requested | | | 4/4/2019 | | DONE |
Joe Bruce
|
|
|
|
Routing - PLAN CHECK | 3/28/2019 | | 4/4/2019 | | PASS |
Joe Bruce
|
|
|
|
Intake Approval | | | 3/22/2019 | | PASS |
|
|
|
|
Intake Approval | | | 3/20/2019 | | FAIL |
Joe Bruce
|
|
|
Please provide the following to complete your prescreen.
1. Identify the location of the structure on a site/keyplan to determine the room in which these racks will be installed.
|
Application received | | | 3/19/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Mar 19 2019 11:20AM
|