Third Notice | | 11/3/2019 | 11/26/2019 | | DONE |
|
|
|
mailed 12-2-19
|
Second Notice | | 9/28/2019 | 10/29/2019 | | DONE |
|
|
|
mailed 11-1
|
First Notice | | 9/2/2019 | 9/18/2019 | | DONE |
|
|
|
mailed 9-19-19
|
Permanent Occupancy | | | 8/23/2019 | | DONE |
|
|
|
|
BLD-Final | 6/28/2019 | 7/1/2019 | 7/1/2019 | A | PASS |
Mike Jordan
|
|
|
John- please call for access Phone #: ###-####. All issues resolved. Ok for perm occ.
|
Plan Reviewer's activity | | | 6/28/2019 | | DONE |
Brian McGowan
|
|
|
Occupancy sensors not required as per Daryl DeGrange.
|
BLD-Final | 6/24/2019 | 6/25/2019 | 6/25/2019 | A | PART |
Mike Jordan
|
|
|
Joe Phone #: ###-####. Ok for temp occ. only. Needs to provide occupancy sensors and ADA compliant pos.
|
FIRE-Final Inspection | 6/25/2019 | 6/25/2019 | 6/25/2019 | A | PASS |
Jim Page
|
|
|
Fire sprinkler inspection is complete, no fire alarm modifications, fire extinguisher is placed with a current inspection tag. Final life fire safety inspection for area of work complete.
|
FIRE-Final Inspection | 6/18/2019 | 6/18/2019 | 6/18/2019 | P | FAIL |
Troy Cobbley
|
|
|
Provide sprinkler coverage for the massage room missing a head, repair the emergency light in the corridor and provide verification of annual inspection of the sprinkler system.
Call for access // John Phone #: ###-####
|
BLD-Final | 6/17/2019 | 6/18/2019 | 6/18/2019 | A | NR |
Mike Jordan
|
|
|
John-please call for access Phone #: ###-####. Needs fire/life/safety final first.
|
BLD-Conference | 5/31/2019 | 5/31/2019 | 5/31/2019 | P | DONE |
Brandon Shaw
|
|
|
Call half hour before // Joe Phone #: ###-####
|
BLD-Framing/Rough-in | 5/21/2019 | 5/22/2019 | 5/22/2019 | A | PASS |
Mike Jordan
|
|
|
Call when on the way // Joe Phone #: ###-####. Interior steel stud framed walls ok.
|
BLD-Framing/Rough-in | 5/16/2019 | 5/17/2019 | 5/17/2019 | A | NR |
Mike Jordan
|
|
|
Call ahead // Joe Phone #: ###-####. Needs lectrical rough in inspection first.
|
BLD-Conference | 5/14/2019 | 5/14/2019 | 5/14/2019 | P | DONE |
Mike Jordan
|
|
|
Call when on the way // Joe Phone #: ###-####
|
Issue PAID IN FULL permit | | | 5/1/2019 | | DONE |
|
|
|
|
Print Occupancy Form | | | 5/1/2019 | | DONE |
|
|
|
|
Plan assigned to (BJM) | 3/26/2019 | 3/26/2019 | 4/15/2019 | | DONE |
Brian McGowan
|
|
|
04/15 - 1st Review Complete - 04/03 - L2 Queen Massage Spa
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/15/2019 | | DONE |
Brian McGowan
|
|
|
|
Permit Ready to Issue | | | 4/15/2019 | | DONE |
|
|
|
ALL MET
Need GC
Need Rev Val
|
Routing - PLAN CHECK | 4/10/2019 | | 4/12/2019 | | PASS |
Brian McGowan
|
|
|
|
Routing - PLUMBING | 4/10/2019 | | 4/10/2019 | | PASS |
Daryl Spivey
|
|
|
Per plan and ISPC.
|
Route to Impact Fee Review | 3/28/2019 | 3/31/2019 | 3/28/2019 | | PASS |
Shannon Cade
|
|
|
Review requested for Commercial Permit
|
1st review completed | | | 3/28/2019 | | FAIL |
Brian McGowan
|
|
|
|
Routing - PLAN CHECK | 3/22/2019 | | 3/28/2019 | | FAIL |
Brian McGowan
|
|
|
See Plumbing Requirements
|
Plan assigned to (JAR) | 3/22/2019 | 3/22/2019 | 3/26/2019 | | DEFR |
Julie Romig
|
|
|
04/03 - L2 Queen Massage Spa
|
Routing - PLUMBING | 3/22/2019 | | 3/25/2019 | | FAIL |
Daryl Spivey
|
|
|
Provide stamped State of Idaho engineered set of plumbing plans
|
Routing - Addressing | 3/22/2019 | | 3/22/2019 | | PASS |
Doug Chausow
|
|
|
Ste 150
|
Routing - PUBLIC WORKS | 3/22/2019 | | 3/22/2019 | | PASS |
Angela Hardy
|
|
|
|
Intake Approval | | | 3/21/2019 | | PASS |
Brian McGowan
|
|
|
Prescreen approved by Brian McGowan.
|
Application received | | | 3/19/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Mar 19 2019 5:00PM
|