BLD-Aging Inspection | 9/4/2019 | 9/4/2019 | 9/6/2019 | | PEND |
Tony Young
|
|
|
|
PubWorks Subgrade Approval | 7/18/2019 | 7/18/2019 | 7/18/2019 | | DONE |
Melissa Jannusch
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Melissa Jannusch ###-####.
|
Override - Parcel Holds | | | 7/18/2019 | | |
|
|
|
|
BLD-Final | 7/10/2019 | 7/11/2019 | 7/11/2019 | A | NR |
Tony Young
|
|
|
Rod Phone #: ###-####,, no answer,, needs hillside pass on subgrade 1st
|
BLD-Footing | 4/23/2019 | 4/23/2019 | 4/23/2019 | P | PASS |
Jim Sly
|
|
|
rebar for pool // Rod Phone #: ###-####
|
BLD-Foundation | 4/22/2019 | 4/23/2019 | 4/23/2019 | A | NR |
Tony Young
|
|
|
rebar for pool // Rod Phone #: ###-####,, needs soils 1st
|
Issue PAID IN FULL permit | | | 4/2/2019 | | DONE |
|
|
|
|
Plan assigned to (M_H) | 3/20/2019 | | 4/1/2019 | | DONE |
Michael Hanson
|
|
|
1st review completed 03/26 #426 L2 Paper
|
Routing PW Grading-Hillside | 4/1/2019 | | 4/1/2019 | | PASS |
Melissa Jannusch
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the pool subgrade is acceptable must be approved by Public Works prior to scheduling inspections. Please allow 24 hours for subgrade approval processing. If you have any questions call Melissa Jannusch ###-####.
|
Routing - PLAN CHECK | 4/1/2019 | | 4/1/2019 | | PASS |
Michael Hanson
|
|
|
|
Case Summary (BLD) | | | 4/1/2019 | | DONE |
Michael Hanson
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/1/2019 | | DONE |
Michael Hanson
|
|
|
|
Routing - Erosion and Sediment | 4/1/2019 | | 4/1/2019 | | PASS |
Andy J. Long
|
|
|
Will use existing SFH ESC permit with permission from builder
|
Routing - PUBLIC WORKS | 4/1/2019 | | 4/1/2019 | | PASS |
Angela Hardy
|
|
|
|
Inspection Record Card- Bld | | | 4/1/2019 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 4/1/2019 | | DONE |
|
|
|
Need- met
GC Form
|
Telephone call | | | 4/1/2019 | | DONE |
|
|
|
Spoke with Joel to inform him the permit is ready, that we need a GC form filled out and what fees are due.
|
Routing - PLANNING | 3/29/2019 | | 3/29/2019 | | PASS |
Sue Cummings
|
|
|
relocated pool outside the easements, but the pool apron needs to be 3 ft. from property line per code.
|
Routing - Erosion and Sediment | 3/26/2019 | | 3/26/2019 | | FAIL |
Andy J. Long
|
|
|
No ESC site plan with narrative or ESC plan waiver request submitted. Check with homebuilder on existing ESC plan.
|
1st review completed | | | 3/26/2019 | | DONE |
Michael Hanson
|
|
|
|
Plan resubmittals received | | | 3/26/2019 | | DONE |
|
|
|
Two copies of each GeO Tech report and whole new set of plans
|
Routing - PLANNING | 3/26/2019 | | 3/26/2019 | | FAIL |
Sue Cummings
|
|
|
5 ft. easement on sine, 10 ft. easement on rear.
|
Routing - PLAN CHECK | 3/20/2019 | | 3/26/2019 | | FAIL |
Michael Hanson
|
|
|
Emailed corrections to applicant.
|
Routing - PUBLIC WORKS | 3/20/2019 | | 3/25/2019 | | FAIL |
Angela Hardy
|
|
|
|
Routing PW Grading-Hillside | 3/22/2019 | | 3/25/2019 | | FAIL |
Melissa Jannusch
|
|
|
Scope requires Grading and Drainage plans and possibly CFH application.
Geotechnical report required with application
|
Routing - Addressing | 3/22/2019 | | 3/22/2019 | | PASS |
Doug Chausow
|
|
|
|
Routing Walk-In (BLD) | 3/20/2019 | 3/20/2019 | 3/20/2019 | P | FAIL |
Michael Hanson
|
|
|
Never saw this applicant.
|
Plans ACCEPTED BY PLAN TECH | | | 3/20/2019 | | DONE |
|
|
|
|
Intake Approval | | | 3/20/2019 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 3/20/2019 | | DONE |
|
|
|
|
Application received | | 3/20/2019 | | | |
|
|
|
|
Routing - PLANNING | 3/20/2019 | | | | FAIL |
|
|
|
Five foot side easement 3/19/19 SAC
|
Routing - PUBLIC WORKS | 3/27/2019 | | | | FAIL |
|
|
|
|