BLD-Final | 11/12/2019 | 11/14/2019 | 11/14/2019 | A | PASS |
Brandon Shaw
|
|
|
Phone #: ###-#### Inspection requested via web by Clint Wall
|
DOC - Permit Finaled | 11/14/2019 | 11/14/2019 | 11/14/2019 | P | PASS |
Brandon Shaw
|
|
|
|
BLD-Blower Door Test Results | 11/12/2019 | 11/14/2019 | 11/14/2019 | A | DONE |
Brandon Shaw
|
|
|
ACH50- 4.3
|
BLD-Energy code compliance | 9/11/2019 | 9/12/2019 | 9/12/2019 | A | PASS |
Brandon Shaw
|
|
|
Phone #: ###-#### Inspection requested via web by Clint Wall
|
BLD-Framing/Rough-in | 9/3/2019 | 9/10/2019 | 9/10/2019 | A | PASS |
Brandon Shaw
|
|
|
Phone #: ###-#### Inspection requested via web by Clint Wall
|
BLD-Other | 8/23/2019 | 8/23/2019 | 8/23/2019 | P | PASS |
Dave Hannah
|
|
|
soffits sheetrock
|
BLD-Wall Bracing | 8/22/2019 | 8/23/2019 | 8/23/2019 | A | PART |
Dave Hannah
|
|
|
Eber Phone #: ###-#### ex ok but needs to add two hold downs by window front bed room
|
BLD-Foundation | 6/24/2019 | 6/24/2019 | 6/24/2019 | P | PASS |
Dave Hannah
|
|
|
Many- would like to pour around 2 oclock Phone #: ###-####
|
BLD-Footing | 6/20/2019 | 6/21/2019 | 6/21/2019 | A | PASS |
Dave Hannah
|
|
|
pouring at 11 // Manny Phone #: ###-####
|
PubWorks Subgrade Approval | 6/20/2019 | 6/20/2019 | 6/20/2019 | | DONE |
Melissa Jannusch
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Melissa Jannusch ###-####.
|
Issue PAID IN FULL permit | | | 6/11/2019 | | DONE |
|
|
|
emailed joshb@blackrockhomes.com to sign permit and send back
|
Inspection Record Card- Bld | | | 6/11/2019 | | DONE |
|
|
|
|
OVERRIDE | | | 4/3/2019 | | |
|
|
|
|
Plan assigned to (J_N) | 3/28/2019 | 3/28/2019 | 4/3/2019 | | DONE |
Jenny Nelson
|
|
|
1st complete 3/29, wall bracing calculations, braced line offsets
|
Routing - PLAN CHECK | 4/3/2019 | | 4/3/2019 | | PASS |
Jenny Nelson
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/3/2019 | | DONE |
Jenny Nelson
|
|
|
|
Permit Ready to Issue | | | 4/3/2019 | | DONE |
|
|
|
met
|
1st review completed | | | 3/29/2019 | | FAIL |
Jenny Nelson
|
|
|
|
Routing - PLAN CHECK | 3/21/2019 | | 3/29/2019 | | FAIL |
Jenny Nelson
|
|
|
|
Plan assigned to (M_H) | 3/21/2019 | | 3/28/2019 | | DEFR |
Michael Hanson
|
|
|
04/03 #402 L1 ePlan
|
Routing - MECHANICAL | 3/21/2019 | | 3/25/2019 | | PASS |
Chad Schwendiman
|
|
|
|
Route to Impact Fee Review | 3/21/2019 | 3/24/2019 | 3/22/2019 | | PASS |
Eric Bilimoria
|
|
|
Initial residential review of new SFD permits requested for now.
|
Routing - FIRE | 3/21/2019 | 3/21/2019 | 3/22/2019 | | PASS |
Lee G Meredith
|
|
|
04/03 Gemini A Residential
Sprinklers are not required.
|
Routing - PLANNING | 3/21/2019 | | 3/21/2019 | | PASS |
Colleen T Carroll
|
|
|
|
Routing - Addressing | 3/21/2019 | | 3/21/2019 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 3/21/2019 | | 3/21/2019 | | PASS |
Morgan Webb
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 3/21/2019 | | DONE |
|
|
|
|
Override - Parcel Holds | | | 3/21/2019 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 3/21/2019 | | DONE |
|
|
|
|
Intake Approval | | | 3/21/2019 | | PASS |
|
|
|
|
Application received | | | 3/20/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Mar 20 2019 2:44PM
|