BLD-Final | 1/3/2020 | 1/7/2020 | 1/7/2020 | A | DONE |
Tony Young
|
|
|
Garage Code: 0713 Phone #: ###-#### Inspection requested via web by Steve Hanson
|
DOC - Permit Finaled | 1/7/2020 | 1/7/2020 | 1/7/2020 | P | PASS |
Tony Young
|
|
|
c of o issued
|
BLD-Final | 1/6/2020 | 1/6/2020 | 1/6/2020 | P | PASS |
Tony Young
|
|
|
Need a final inspection, should just need foothills approval letter from Melissa. Garage code: 0713 Thanks! Phone #: ###-#### Inspection requested via web by Steve Hanson
|
PubWorks Occupancy Approval | 1/6/2020 | 1/6/2020 | 1/6/2020 | | DONE |
Melissa Jannusch
|
|
|
A letter from the applicant’s design professional indicating that the final grading and drainage is acceptable has been received by Public Works. Final occupancy may be approved by the building department. Melissa Jannusch ###-####.
|
BLD-Final | 1/3/2020 | 1/3/2020 | 1/3/2020 | P | PEND |
Tony Young
|
|
|
Garage Code: 0713 Phone #: ###-#### Inspection requested via web by Steve Hanson
|
BLD-Final | 1/2/2020 | 1/3/2020 | 1/3/2020 | A | NR |
Tony Young
|
|
|
Garage Code: 0713 Phone #: ###-#### Inspection requested via web by Steve Hanson
|
BLD-Blower Door Test Results | 1/2/2020 | 1/3/2020 | 1/3/2020 | A | DONE |
Tony Young
|
|
|
Garage Code: 0713 Phone #: ###-#### Inspection requested via web by Steve Hanson.. 4.2
|
BLD-Final | 12/31/2019 | 1/2/2020 | 1/2/2020 | A | NR |
Tony Young
|
|
|
Garage Code: 0713 Phone #: ###-#### Inspection requested via web by Steve Hanson// needs hillside public works final 1st
|
BLD-Wall cover | 9/5/2019 | 9/6/2019 | 9/6/2019 | A | PASS |
Tony Young
|
|
|
Need a sheetrock sheer inspection please.
Thank you Phone #: ###-#### Inspection requested via web by Steve Hanson
|
BLD-Other | 9/3/2019 | 9/4/2019 | 9/4/2019 | P | PASS |
Tony Young
|
|
|
Need soffit inspection for WUI code compliance.
Thank you! Phone #: ###-#### Inspection requested via web by Steve Hanson
|
BLD-Other | 8/29/2019 | 8/30/2019 | 8/30/2019 | A | PART |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by Steve Hanson,, need to look at truss engineering// add bracing per engineering,, soffit work in progress,, fire block ceiling line under stairs at fur down,, ok to cover after
|
BLD-Energy code compliance | 8/28/2019 | 8/29/2019 | 8/29/2019 | P | PASS |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by Steve Hanson
|
BLD-Framing/Rough-in | 8/27/2019 | 8/29/2019 | 8/29/2019 | P | PASS |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by Steve Hanson
|
BLD-Framing/Rough-in | 8/23/2019 | 8/27/2019 | 8/27/2019 | A | PART |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by Steve Hanson,, need truss engineering,, ok to insulate
|
BLD-Wall Bracing | 8/13/2019 | 8/13/2019 | 8/13/2019 | P | PART |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by Steve Hanson,,, exterior ok
|
BLD-Foundation | 6/26/2019 | 6/26/2019 | 6/26/2019 | P | PART |
Tony Young
|
|
|
Phone #: 2088708888 >> Inspection requested via mobile web by Wes,, retaining and basement and main walls ok,, work in progress
|
BLD-Footing | 6/20/2019 | 6/21/2019 | 6/21/2019 | P | PASS |
Tony Young
|
|
|
As early as possible Phone #: 2088708888 >> Inspection requested via mobile web by Wes
|
PubWorks Subgrade Approval | 6/13/2019 | 6/13/2019 | 6/13/2019 | | DONE |
Melissa Jannusch
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Melissa Jannusch ###-####.
|
Issue PAID IN FULL permit | | | 6/3/2019 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 5/29/2019 | | DONE |
|
|
|
|
Telephone call | | | 5/29/2019 | | DONE |
|
|
|
left a message for kim informing her that this permit is ready and the fee amount due for issuance
|
OVERRIDE | | | 5/28/2019 | | |
|
|
|
|
Plan assigned to (RDP) | 4/3/2019 | 4/3/2019 | 5/28/2019 | | DONE |
Rob Patrick
|
|
|
04/08 sfd L2 Paper...04/04 Failed. 04/22...Failed; Fire Flow, Grading/Drainage.
|
Routing - PLAN CHECK | 5/28/2019 | | 5/28/2019 | | PASS |
Rob Patrick
|
|
|
|
Case Summary (BLD) | | | 5/28/2019 | | DONE |
Rob Patrick
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/28/2019 | | DONE |
Rob Patrick
|
|
|
|
Permit Ready to Issue | | | 5/28/2019 | | DONE |
|
|
|
met
|
Routing - PLANNING | 5/22/2019 | | 5/23/2019 | | PASS |
Karla Nelson
|
|
|
Revised plans submitted on 5-3-19 are ok.
|
Routing PW Grading-Hillside | 5/22/2019 | | 5/22/2019 | | PASS |
Melissa Jannusch
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Please e-mail the stamped inspection approval letter to mjannusch@cityofboise.org and allow 24 hours for subgrade approval processing. Call Melissa Jannusch at ###-#### with questions.
Prior to obtaining a final for the permit, the roof storm drainage system must be inspected by Public Works. Call Melissa Jannusch at ###-####.
The final inspection of the site grading and drainage work shall be done by the design engineer. Written approval shall be submitted to Boise Public Works prior to the issuance of the building final.
|
Routing - PUBLIC WORKS | 5/22/2019 | | 5/22/2019 | | PASS |
Angela Hardy
|
|
|
|
Plan Reviewer's activity | | | 5/6/2019 | | |
|
|
|
Delivered resubmittal to Melissa for review
|
Plan resubmittals received | | | 5/3/2019 | | DONE |
|
|
|
three copies of sheets L-1.1 taken to Rob
|
Routing - FIRE | 4/22/2019 | 4/22/2019 | 5/2/2019 | | PASS |
Lee G Meredith
|
|
|
05/06-Syringa Highland View Home LM Resubmittal
Revised SUEZ document indicates adequate fire flow.
|
Telephone call | | | 5/2/2019 | | DONE |
|
|
|
left a message for steve informing him i can not give the plan sheet turned in on 4-30 until we have the second copy
|
Telephone call | | | 5/2/2019 | | DONE |
|
|
|
left a message for kim (steve no longer with the company) informing we need a second copy for resubmittal
|
Telephone call | | | 4/30/2019 | | DONE |
|
|
|
Left a message for Steve in forming when need a second copy for the plan. asked the person who was here and they stated yes. should have looked before they left
|
Routing - PLAN CHECK | 4/22/2019 | | 4/22/2019 | | FAIL |
Rob Patrick
|
|
|
04/22...Failed; Fire Flow, Grading/Drainage, H.E.R.S. rating.
|
Routing PW Grading-Hillside | 4/18/2019 | | 4/18/2019 | | FAIL |
Melissa Jannusch
|
|
|
see e-mail
|
Plan Reviewer's activity | | | 4/11/2019 | | |
|
|
|
Set entire package on Melissa's desk for her review.
|
Plan resubmittals received | | | 4/10/2019 | | DONE |
|
|
|
Resubmittal. page. Every sheet has new title block. Resubmitted Sheets 4, 7, 9 and 10.
|
Routing - PLAN CHECK | 4/3/2019 | | 4/4/2019 | | FAIL |
Rob Patrick
|
|
|
Corrections Rreq'd
|
1st review completed | | | 4/4/2019 | | FAIL |
Rob Patrick
|
|
|
|
Plan assigned to (BJM) | 3/20/2019 | 3/20/2019 | 4/3/2019 | | DEFR |
Brian McGowan
|
|
|
04/08 (L2 sfd) ePlan
|
Routing - FIRE | 4/2/2019 | | 4/3/2019 | | FAIL |
Lee G Meredith
|
|
|
04/10 Syringa Highland View Home 402
4-3-19 Hydrant fire flow is inadequate for fire area. Emailed applicant comments and details.
|
Routing - Erosion and Sediment | 3/28/2019 | | 4/1/2019 | | PASS |
Andy J. Long
|
|
|
ESC plan approved. Certified stormwater team. ESC site preparation inspection is required.
|
Routing - MECHANICAL | | | 3/28/2019 | | PASS |
Troy James
|
|
|
|
Routing - PLANNING | | | 3/27/2019 | | FAIL |
|
|
|
The driveway can be no more than 33' in the front setback. Rock walls can be no more than 3' in the front setback and no more than 6' in other setback areas.
|
Routing - PUBLIC WORKS | | | 3/27/2019 | | FAIL |
|
|
|
|
Plan resubmittals received | | | 3/27/2019 | | DONE |
|
|
|
Resubmittal received 3 sets of materials testing & insp and 3 sets of sheet grading plan-took to Brian McGowan
|
Plan Reviewer's activity | | | 3/27/2019 | | |
Brian McGowan
|
|
|
Took (3) copies of Sheet L-1.1 to Melissa's office
|
Routing PW Grading-Hillside | 3/22/2019 | | 3/26/2019 | | FAIL |
Melissa Jannusch
|
|
|
Needs updated grading plans and conclusion letter
|
Routing - Addressing | 3/20/2019 | | 3/22/2019 | | PASS |
Doug Chausow
|
|
|
|
Route to Impact Fee Review | 3/20/2019 | 3/23/2019 | 3/21/2019 | | PASS |
Shannon Cade
|
|
|
Initial residential review of new SFD permits requested for now.
|
Plans ACCEPTED BY PLAN TECH | | | 3/20/2019 | | DONE |
|
|
|
|
Intake Approval | | | 3/20/2019 | | PASS |
|
|
|
|
Override - Parcel Holds | | | 3/20/2019 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 3/20/2019 | | DONE |
|
|
|
|
Application received | | 3/20/2019 | | | |
|
|
|
|