(BALANCE RECOVERY – COUNSELING SERVICES – OCCUPANCY) This building does not have a fire sprinkler system. Application for inspection to determine the requirements for the issuance of a Certificate of Occupancy for a new counseling services office tenant within an existing 1,255 square foot tenant space located within an existing 4,450 square foot building that has a total of 3 office tenant spaces and a common toilet room core with its own means of egress to the outside. No new work is authorized under this permit except for minor work that may be needed to correct noncompliant conditions that may exist. Painting, carpeting, counter tops, and similar finish work are not required to have a building permit. Compliance is required with the items listed in the plan review report under Referenced Code Sections because noncompliance with these items is believed to constitute a distinct hazard to life and safety or to discriminate against the disabled. **CJW**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final4/12/20194/15/20194/15/2019APASS
DetailsJim Storey
Dennis Phone #: ###-####
BLD-Final4/12/20194/12/20194/12/2019PPASS
DetailsJim Storey
FIRE-Final Inspection4/12/20194/12/20194/12/2019PPASS
DetailsJim Page
No fire sprinklers, no fire alarms, fire extinguishers are placed with current inspection tags. Final life fire safety inspection for area of work complete.

Steve-please call to meet Phone #: ###-####
Telephone call  4/12/2019 DONE
Spoke with Jim Storey. He did the final inspection and passed it on this permit.However the inspection was scheduled on a permit from 2015. I called him and he said they passed and to go ahead and issue the Certificate of Occupancy. I have scheduled the inspection for Monday AM, and Jim said he will go in when he gets a chance and pass it. GF 4-12-2019
Permanent Occupancy  4/12/2019 DONE
Issue PAID IN FULL permit  4/3/2019 DONE
Plan assigned to (CJW)3/22/20193/22/20194/2/2019 PASS
DetailsCarl Westfall
Occupancy
Routing - PLAN CHECK3/22/2019 4/2/2019 PASS
DetailsCarl Westfall
This permit was submitted just before the Plans Examiner left for a week long vacation. The review was done when he got back.
1st review completed  4/2/2019 DONE
PLANS/APPL TAKEN TO FRONT DESK  4/2/2019 DONE
Permit Ready to Issue  4/2/2019 DONE
Print Occupancy Form  4/2/2019 DONE
Telephone call  4/2/2019 DONE
called Steve to let know permit is ready
Routing - Addressing3/22/2019 3/22/2019 PASS
DetailsDoug Chausow
Routing - PUBLIC WORKS  3/22/2019 PASS
Intake Approval  3/22/2019 PASS
DetailsCarl Westfall
Recd Pcfee & Taken To Pln CK  3/22/2019 DONE
First Notice 4/22/2019   