BLD-Conference | 7/30/2019 | 7/31/2019 | 7/31/2019 | P | DONE |
Troy Cobbley
|
|
|
The stage and the sound booth floors have both been filled with non-combustible insulation. They are ok for cover. We also spoke about the need for a fire alarm permit for the modifications.
as late as possible - fire conference // Matt Phone #: ###-####
|
BLD-Framing/Rough-in | 7/30/2019 | 7/31/2019 | 7/31/2019 | A | PASS |
Tell Riley
|
|
|
Matt Phone #: ###-####//framing ok per plans//electrical rough ok//insulate per plan change and have fire inspection prior to cover//
|
Plan Reviewer's activity | | | 7/30/2019 | | DONE |
|
|
|
A plan mod will soon be submitted to allow an approved method of dealing with concealed combustible spaces per NFPA 13 other than installing fire sprinklers within the space. Any approved method per NFPA 13 is acceptable. CJW
|
BLD-Framing/Rough-in | 7/26/2019 | 7/29/2019 | 7/29/2019 | A | NR |
Tell Riley
|
|
|
robin Phone #: ###-####//talked with contact at Discovery//they still need fire sprinklers or alternate//need a plan change if alternate is requuested//not ready for inspection//
|
BLD-Framing/Rough-in | 7/17/2019 | 7/18/2019 | 7/18/2019 | A | NR |
Tell Riley
|
|
|
Robin Phone #: ###-####//need verification on blocking at I joists//need fire sprinkler and alarm permits and inspections prior to any cover on project//call for re-inspection after fire inspection//
|
Issue PAID IN FULL permit | | | 6/7/2019 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 6/7/2019 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 6/6/2019 | | DONE |
|
|
|
MET RMEACHAM@DCBOISE.ORG
Need GC
Need Rev Val
|
Plan assigned to (CJW) | 3/28/2019 | 3/28/2019 | 6/5/2019 | | PASS |
Carl Westfall
|
|
|
(1st done) 04/15/19 (L-3 - 15 days) (eplan - 5 sheets) Discovery Church (back to applicant)
|
Routing - PLAN CHECK | 6/4/2019 | | 6/5/2019 | | PASS |
Carl Westfall
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/5/2019 | | DONE |
|
|
|
|
Plan resubmittals received | | | 6/4/2019 | | DONE |
|
|
|
|
Route to Impact Fee Review | 4/24/2019 | 4/27/2019 | 4/25/2019 | | PASS |
Shannon Cade
|
|
|
Review requested for Commercial Permit
|
Plan resubmittals requested | | | 4/24/2019 | | DONE |
|
|
|
|
Routing - FIRE | 3/28/2019 | 3/28/2019 | 4/23/2019 | | PASS |
Mark Scharfen
|
|
|
IFC Review 04.23.2019.pdf uploaded.
|
1st review completed | | | 4/23/2019 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 3/28/2019 | | 4/23/2019 | | FAIL |
Carl Westfall
|
|
|
|
Routing - Addressing | 3/28/2019 | | 3/29/2019 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 3/28/2019 | | 3/28/2019 | | PASS |
Morgan Webb
|
|
|
|
Intake Approval | | | 3/26/2019 | | PASS |
|
|
|
|
Application received | | | 3/22/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Mar 22 2019 9:38AM
|
Plan Reviewer's activity | | | 3/22/2019 | | PASS |
|
|
|
Plan intake review approved
|