First Notice | | 8/17/2019 | 9/18/2019 | | DONE |
|
|
|
mailed 9-19-19
|
BLD-Final | 8/6/2019 | 8/7/2019 | 8/7/2019 | A | PASS |
Jim Storey
|
|
|
Call ahead 45 minutes - he's in Nampa // Dennis Phone #: ###-#### , restroom door configuration is existing with no changes.
|
Permanent Occupancy | | | 8/7/2019 | | DONE |
|
|
|
|
FIRE-Final Inspection | 8/2/2019 | 8/2/2019 | 8/2/2019 | P | PASS |
Jim Page
|
|
|
No fire alarms, no fire sprinklers, hood suppression system inspection complete, fire exitnguishers are placed with current inspection tags, restroom door configuration is existing with no changes. Final life fire safety inspection for area of work complete.
|
BLD-Ceiling Grid Inspection | 7/30/2019 | 7/31/2019 | 7/31/2019 | P | PASS |
Jim Storey
|
|
|
Mike Phone #: ###-####
|
BLD-Framing/Rough-in | 7/2/2019 | 7/3/2019 | 7/3/2019 | P | PART |
Jim Storey
|
|
|
Mike Phone #: ###-#### walls ok need screws removed ceilling track to top plate.
|
Print Occupancy Form | | | 7/2/2019 | | DONE |
|
|
|
|
Print Occupancy Form | | | 4/26/2019 | | DONE |
|
|
|
|
Print Occupancy Form | | | 4/26/2019 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 4/26/2019 | | DONE |
|
|
|
|
Plan assigned to (JG) | 3/29/2019 | 3/29/2019 | 4/16/2019 | | PASS |
Javier Guzman
|
|
|
2nd rev, 04/09 L2 Happy Teriyaki ePlan
|
Routing - PLAN CHECK | 4/11/2019 | | 4/16/2019 | | PASS |
Javier Guzman
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/16/2019 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 4/16/2019 | | DONE |
|
|
|
all met: hcd_inc@msn.com
NEED
GC FORM
REVISED VALUE
|
Routing - FIRE | 3/29/2019 | 3/29/2019 | 4/10/2019 | | PASS |
Mark Scharfen
|
|
|
04.10.2019 completed IFC review. No comments needed. Approved.
|
1st review completed | | | 4/9/2019 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 3/29/2019 | | 4/9/2019 | | FAIL |
Javier Guzman
|
|
|
|
Routing Off Site - C.D.H | 3/29/2019 | | 4/5/2019 | | PASS |
Javier Guzman
|
|
|
Signed off in ePlan by Central District Health Department Scott Paradis
|
Routing - Design Review | 3/29/2019 | | 4/4/2019 | | PASS |
Andrea Tuning
|
|
|
|
Routing PW Environmental | 3/29/2019 | | 4/1/2019 | | PASS |
Rick Christenson
|
|
|
Per connection to GW-Line
|
Routing - MECHANICAL | 3/29/2019 | | 4/1/2019 | | PASS |
Troy James
|
|
|
|
Routing - PLUMBING | 3/29/2019 | | 4/1/2019 | | PASS |
Daryl Spivey
|
|
|
Per plan and ISPC.
|
Routing - Addressing | 3/29/2019 | | 3/29/2019 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 3/29/2019 | | 3/29/2019 | | PASS |
Morgan Webb
|
|
|
|
Intake Approval | | | 3/29/2019 | | PASS |
Michael Hanson
|
|
|
Prescreen approved by Michael Hanson.
|
Plan Reviewer's activity | | | 3/27/2019 | | DONE |
Michael Hanson
|
|
|
Checked with Javier and he indicated 518 would be okay.
|
Intake Approval | | | 3/25/2019 | | FAIL |
Michael Hanson
|
|
|
Provide updated coversheet with current Boise city codes and CDHD approval stamped and signed.
|
Application received | | | 3/22/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Mar 22 2019 10:32AM
|