Permit Information
Permit NumberBLD19-00915
StatusIssued
Name BARBARA FARBER
Site Address 2300 W FAIRVIEW AVE Unit: 110
Project NameOFFICE Suite 110
Customer NumberBLD19-00915, 01334 - 01336
ePlanReviewYes
Description
(VANILLA TI – SUITE #110) THERE ARE (4) PERMITS UNDER THIS EPLAN CASE BLD19-00915. (4) Vanilla TI Suites are being developed in an existing 6,374 square foot building. (See BLD19-01334, 01335, 01336) Suite #110 TI, “A” as per plans, is to be an 1,496 square foot Tenant Space. Approval is contingent upon adhering to the approved plans on file. Work to include: DEMOLISHING existing non-wall bearing interior walls, existing bathrooms, existing HVAC and electrical as needed, removing CMU Blocks installed to infill a previous opening in the exterior wall in 1988; ADDING a non-bearing interior wall, ADA compliant Bathroom, replacing an existing exterior wall between CMU wall opening with a new front door, glass and exterior wall, HVAC and electrical as per plans, interior finishes in compliance with Ch. 8 of the 2015 IBC. This building was previously occupied by Ennis Furnishings. This building is not sprinklered. ***BJM***
Contact Information
See Activities list for contact information
Color Key
Current location of plans being reviewed:  
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Telephone call  5/28/2020 DONE
Updating valuation to reflect only one suite's electrical work. Was originally valued for all 4 suites
BLD-Framing/Rough-in5/27/20205/27/20205/27/2020PPASS
DetailsMike Jordan
Tara Phone #: ###-####
BLD-Framing/Rough-in5/15/20205/18/20205/18/2020ANR
DetailsBrandon Shaw
Ele permits to be asigned to proper addresses...
BLD-Framing/Rough-in5/15/20205/15/20205/15/2020PNR
DetailsTell Riley
kara Phone #: ###-####/add backing for grab bars//need ELE permits fixed//need mechanical permits//seal penetrations at top plates//
Issue PAID IN FULL permit  8/1/2019 DONE
Inspection Record Card- Bld  8/1/2019 DONE
(F) Reprint permit  8/1/2019 DONE
Plan assigned to (BJM)5/3/20195/3/20197/30/2019 DONE
DetailsBrian McGowan
6th Review Complete-05/24 - 4 Office suite #110 L-3
Routing - PLAN CHECK7/23/2019 7/30/2019 PASS
DetailsBrian McGowan
Routing - PUBLIC WORKS7/23/2019 7/30/2019 PASS
DetailsMorgan Webb
Please remember that this is one of (4) Pemits attached to this ePlan. Tidemark sign offs are needed on all.
BLD19- 00915, 01334, 01335, 01336
Needs Streetlight Review
Routing PW Street Lights7/30/2019 7/30/2019 PASS
DetailsTom Marshall
PLANS/APPL TAKEN TO FRONT DESK  7/30/2019 DONE
DetailsBrian McGowan
Permit Ready to Issue  7/30/2019 DONE
BLD19-00915, 01334 - 01336
NEED
GC FORM
REVISED VALUE
Routing PW Street Lights7/25/2019 7/25/2019 FAIL
DetailsTom Marshall
Routing - FIRE7/17/20197/17/20197/23/2019 PASS
DetailsMark Scharfen
Completed fire review. Uploaded rev_fire 07.23.2019.pdf
Plan Reviewer's activity  7/19/2019  
DetailsBrian McGowan
I deleted Sheet DWG A0.0-Cover Sheett, Site & Landscape Plan-revision.pdf uploaded on 6/12/19 since it was redundant and not going to be used. (it should have been named to version over the previous submittal).
I also deleted the Engineering calculations uploaded into the drawing folder on 7/16/19 since it was the same exact packet as in the Documents.
Routing - PLAN CHECK7/18/2019 7/19/2019 FAIL
DetailsBrian McGowan
1. Special Inspections for welding are required. Provide a completed Form #310.
2. Sheet A4.1 has Engineered Designs. It must be stamped and signed by the Engineer.
Routing PW Street Lights7/18/2019 7/18/2019 PASS
DetailsTom Marshall
Routing - PLAN CHECK7/16/2019 7/16/2019 FAIL
DetailsBrian McGowan
Electrical Layout for the revised Floor Plan must be updated to match.
Routing PW Street Lights7/15/2019 7/15/2019 FAIL
Details
Routing - PLAN CHECK7/1/2019 7/10/2019 FAIL
DetailsBrian McGowan
Routing PW Street Lights7/2/2019 7/2/2019 FAIL
DetailsTom Marshall
Routing - PLAN CHECK6/13/2019 7/1/2019 FAIL
DetailsBrian McGowan
Routing PW Street Lights6/24/2019 6/24/2019 FAIL
DetailsTom Marshall
Routing - Design Review6/13/2019 6/14/2019 PASS
DetailsKayCee Babb
Per DRH19-00186 modification, to comply with all conditions of approval including any RTU shall be fully screened by either the existing parapet or additional screening as approved through Design Review.
Routing PW Street Lights6/14/2019 6/14/2019 FAIL
DetailsTom Marshall
Need a street light plan for the 3 required lights to be installed.
Routing - PLAN CHECK6/6/2019 6/6/2019 FAIL
DetailsBrian McGowan
Routing - MECHANICAL5/31/2019 6/3/2019 PASS
DetailsTroy James
Routing - Design Review5/31/2019 5/31/2019 FAIL
DetailsKayCee Babb
Plans do not match those approved through DRH18-00376. Application DRH19-00186 has not yet been processed/reviewed.
Route to Impact Fee Review5/29/20196/1/20195/30/2019 PASS
DetailsShannon Cade
Review requested for Commercial Permit
Routing - FIRE5/3/20195/3/20195/29/2019 PASS
DetailsMark Scharfen
05.29.2019-Completed IFC review. Uploaded rev_fire 05.29.2019.pdf.
1st review completed  5/29/2019 FAIL
DetailsBrian McGowan
Routing - PLAN CHECK5/3/2019 5/29/2019 FAIL
DetailsBrian McGowan
Modifying floor plan
Routing - PLUMBING5/3/2019 5/9/2019 PASS
DetailsDan Ediger
Per Plans and ISPC
Routing - PLANNING5/3/2019 5/7/2019 PASS
DetailsNicolette Womack
Need DR Review.
Routing - MECHANICAL5/3/2019 5/7/2019 PASS
DetailsTroy James
Need to address mechanical ventilation at occupancy.
Routing - Design Review5/3/2019 5/6/2019 FAIL
DetailsKayCee Babb
Per DRH18-00376. Plans do not match approved elevations and a Class II tree is required in the northern terminal planter.
Routing - Addressing5/3/2019 5/6/2019 PASS
DetailsDoug Chausow
Suite 110
Routing - PUBLIC WORKS5/3/2019 5/6/2019 PASS
DetailsAngela Hardy
Intake Approval  5/1/2019 PASS
Intake Approval  4/24/2019 FAIL
DetailsJavier Guzman
Provide and upload the following:
• Previous request below not submitted: I need a 520 application for the new suite B, a 520 application for new suite C, and a 520 application for new suite D.
Four suites are being created in an existing building and requires four applications to be uploaded one for each suite, provide and upload three more completed applications for the remaining new suites. 520 Application can be found at our website at https://pds.cityofboise.org/home/documents/apps/500/
Intake Approval  4/22/2019 FAIL
DetailsJavier Guzman
Provide and upload the following:
• Provide a completed 304 form
• Four suites are being created in an existing building and requires four applications to be uploaded one for each suite, provide and upload three more completed applications for the remaining new suites. 520 Application can be found at our website at https://pds.cityofboise.org/home/documents/apps/500/
Application received  3/22/2019 DONE
Application submitted via PDS Online on Mar 22 2019 10:41AM
Routing - PUBLIC WORKS6/14/2019    
DetailsMorgan Webb
Routing - PUBLIC WORKS7/1/2019    
DetailsMorgan Webb
Routing - PUBLIC WORKS7/18/2019   FAIL
DetailsMorgan Webb
Needs Street light review