Permit Information
Permit NumberBLD19-00925
StatusFinaled
Name Lindy Riebe
Site Address 1409 N 13TH ST
Project Name1409 N 13th St
Customer Number 
ePlanReviewYes
Description
(NORTH END REAL ESTATE) This building is NOT fire sprinklered. To convert an existing house to a 597-square foot office building. The 2015 International Existing Building Code (IEBC) shall be used to regulate this conversion. Work is to include demolition of existing millwork/appliances in kitchen, demolition of existing bathtub, a new accessible ramp, a new van accessible parking space, remodeled restroom, office, and breakroom area. New finished are required to comply with Chapter 8 of the 2015 IBC. DRH18-00557 CUP18-00085 **JHB**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Permanent Occupancy  7/30/2020 DONE
BLD-Final7/27/20207/27/20207/27/2020PPASS
DetailsTony Young
call ahead for access - screened // Lindy Phone #: ###-####
Zoning Approval2/19/20202/19/20202/19/2020 PASS
DetailsKevin Holmes
Meets approval criteria of CUP19-00080
BLD-Aging Inspection12/5/201912/5/201912/6/2019 PEND
DetailsTony Young
FIRE-Final Inspection7/22/20197/23/20197/23/2019APASS
DetailsJim Page
Previously noted items have been corrected. No fire sprinklers, no fire alarms, fire extinguisher is placed with a current inspection tag. Final life fire safety inspection complete.

Lindy Phone #: ###-####
FIRE-Final Inspection7/18/20197/18/20197/18/2019PFAIL
DetailsJim Page
Provide code compliant address numbering as discussed. Provide annual inspection for fire extinguisher and mount extinguisher as discussed.

Lindy Phone #: ###-####
Print Occupancy Form  5/30/2019 DONE
Print Occupancy Form  5/30/2019 DONE
Issue PAID IN FULL permit  5/30/2019 DONE
Plan assigned to (JHB)4/2/20194/2/20195/28/2019 PASS
DetailsJoe Bruce
05/29 (3rd Rev) 04/29 (L3) North 13th Business Conversion, ePlan (Planning, Bldg)
Routing - PLAN CHECK5/22/2019 5/28/2019 PASS
DetailsJoe Bruce
Routing - PLANNING5/22/2019 5/28/2019 PASS
DetailsDavid Moser
PLANS/APPL TAKEN TO FRONT DESK  5/28/2019 DONE
Permit Ready to Issue  5/28/2019 DONE
NEED
ACHD
GC FORM
REVISED VALUE
Plan resubmittals received  5/22/2019 FAIL
DetailsJoe Bruce
Resubmittal sent back to Architect due to detail notes that are partially missing from the details. **JHB**
Plan resubmittals received  5/22/2019 DONE
DetailsJoe Bruce
Plan resubmittals requested  5/13/2019 DONE
DetailsJoe Bruce
Need more information for Building and Planning Review.
Routing - PLANNING5/7/2019 5/10/2019 FAIL
DetailsDavid Moser
I need more information on the bike parking space
Routing - PLAN CHECK5/7/2019 5/9/2019 FAIL
DetailsJoe Bruce
Plan resubmittals received  5/7/2019 DONE
DetailsJoe Bruce
Route to Impact Fee Review4/29/20195/2/20194/29/2019 PASS
DetailsKarina Myles
Review requested for Commercial Permit
Routing - FIRE4/2/20194/2/20194/29/2019 PASS
DetailsMark Scharfen
04/29 1409 N 13th Conversion-Commercial.
1st review completed  4/29/2019 FAIL
DetailsJoe Bruce
Plan resubmittals requested  4/29/2019 DONE
DetailsJoe Bruce
Plan Reviewer's activity  4/29/2019 DONE
DetailsJoe Bruce
Received letter from owner (Lindy Riebe) to change name on application to "North End Real Estate"
Routing - PLAN CHECK4/2/2019 4/25/2019 FAIL
DetailsJoe Bruce
Routing - PUBLIC WORKS4/2/2019 4/4/2019 PASS
DetailsMorgan Webb
Routing - Erosion and Sediment4/2/2019 4/2/2019 PASS
DetailsMichael Zawacki
No ESC required, convert SFH to commercial office.
Routing - PLANNING4/2/2019 4/2/2019 FAIL
DetailsDavid Moser
Need to show one bike parking space on the site plan. This was a condition of approval of CUP18-00085
Routing - Addressing4/2/2019 4/2/2019 PASS
DetailsDoug Chausow
Routing - Design Review4/2/2019 4/2/2019 PASS
DetailsTed Vanegas
Intake Approval  4/2/2019 PASS
Intake Approval  3/27/2019 FAIL
DetailsJoe Bruce
(3-27-19) Please provide the following to complete your prescreen:
1) Site specific flow at hydrants letter from Suez Water.
Application received  3/22/2019 DONE
Application submitted via PDS Online on Mar 22 2019 1:48PM
Intake Approval  3/22/2019 FAIL
(3-22-19) Upload a 520 Plan Intake Checklist. Make sure you fill it out first. Upload each drawing as a separate file. No more than one sheet per file name. A plan intake review has not been done. CJW