Meeting | | | 1/21/2020 | | DONE |
|
|
|
third notice for final values came in 1/21/20
|
Third Notice | | 11/30/2019 | 12/30/2019 | | DONE |
|
|
|
mailed 1-1-20
|
Second Notice | | 11/4/2019 | 11/25/2019 | | DONE |
|
|
|
mailed 12-2-19
|
First Notice | 10/16/2019 | 10/16/2019 | 10/25/2019 | | DONE |
Brandon Shaw
|
|
|
mailed 11-1-19
|
BLD-Final | 10/15/2019 | 10/16/2019 | 10/16/2019 | A | PASS |
Brandon Shaw
|
|
|
tOBY- PLEASWE CALL, LOCK BOX Phone #: ###-####
|
DOC - Permit Finaled | 10/16/2019 | 10/16/2019 | 10/16/2019 | P | PASS |
Brandon Shaw
|
|
|
|
FIRE-Final Inspection | 10/15/2019 | 10/15/2019 | 10/15/2019 | P | PASS |
Jim Page
|
|
|
Fire sprinkler inspection is complete, no fire alarm modifications, fire exitnguisher is placed with a current inspection tag. Final life fire safety inspection for area of work is complete, signatures provided on signature card.
tOBY- PLEASWE CALL, LOCK BOX Phone #: ###-####
|
BLD-Final | 10/14/2019 | 10/14/2019 | 10/14/2019 | P | NR |
Brandon Shaw
|
|
|
Need Fire/life safety...
|
Print Occupancy Form | | | 10/9/2019 | | DONE |
|
|
|
|
CHANGE STATUS TO (ISS) | | | 10/9/2019 | | DONE |
|
|
|
|
Telephone call | | | 10/8/2019 | | DONE |
|
|
|
emailed GC tobycarpentersson@gmail.com, need revised cert of value per plan mod application value is effected. Per Brian McGowan although description of plan mod on application, addition of sink was not included in modification.
|
Permit Ready to Issue | | | 10/4/2019 | | DONE |
|
|
|
Need
Revised Value (plan mod app states value is being affected)
|
Plan assigned to (BJM) | 9/16/2019 | 9/16/2019 | 10/3/2019 | | DONE |
Brian McGowan
|
|
|
09/24- Plan Mod- adding door
|
Routing - PLAN CHECK | 9/20/2019 | | 10/3/2019 | | PASS |
Brian McGowan
|
|
|
|
Plan Reviewer's activity | | | 10/3/2019 | | DONE |
Brian McGowan
|
|
|
Uploaded Plan Review Fee Sheet to Documents. (1) hour
|
Route to Impact Fee Review | 9/16/2019 | 9/19/2019 | 9/17/2019 | | PASS |
Shannon Cade
|
|
|
Review requested for Commercial Permit
|
Plan Modification Accepted | | | 9/16/2019 | | DONE |
|
|
|
plan mod in e plan-enclosing mech area and adding a sink-sheets A-2.0, A-3.0, A-3.01 & A-4.0-cert of val will be required-assigned to Brian McGowan
|
BLD-Framing/Rough-in | 8/19/2019 | 8/19/2019 | 8/19/2019 | P | FAIL |
Brandon Shaw
|
|
|
Need revised plans- One, new addition breakroom doorway has been ommited, and plans call for 2x lumber, 2x steel studs used. Plans and permit should reflect "As Built"...
|
Print Occupancy Form | | | 7/18/2019 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 4/30/2019 | | DONE |
|
|
|
|
Plan assigned to (BJM) | 4/4/2019 | 4/4/2019 | 4/17/2019 | | DONE |
Brian McGowan
|
|
|
04/15 L2 - Tolsma USA TI, ePlan
|
Routing - PLAN CHECK | 4/4/2019 | | 4/17/2019 | | PASS |
Brian McGowan
|
|
|
|
Routing - PUBLIC WORKS | 4/4/2019 | | 4/17/2019 | | PASS |
Morgan Webb
|
|
|
|
1st review completed | | | 4/17/2019 | | DONE |
Brian McGowan
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/17/2019 | | DONE |
Brian McGowan
|
|
|
|
Permit Ready to Issue | | | 4/17/2019 | | DONE |
|
|
|
ALL MET: tobycarpentersson@gmail.com
Need
GC Form
met Revised Value
|
Routing - FIRE | 4/4/2019 | 4/4/2019 | 4/10/2019 | | PASS |
Mark Scharfen
|
|
|
04.10.2019 IFC review complete. No report needed.
|
Routing - Addressing | 4/4/2019 | | 4/4/2019 | | PASS |
Doug Chausow
|
|
|
|
Intake Approval | | | 4/2/2019 | | PASS |
Brian McGowan
|
|
|
Prescreen approved by BJM.
|
Intake Approval | | | 3/28/2019 | | FAIL |
Brian McGowan
|
|
|
In order to approve your Prescreen please provide the following information;
1. The square footage for Building Area on A-3.0 indicates there is an additional 208 sq. ft. being added to the existing sq. ft. in the Building Total. Please verify.
2. Please indicate the direction the 9-1/2" ceiling joists are to be installed, (are you proposing the ceiling as storage) provide headers and additional supports as/if needed. If using as storage please provide for the FIRE Review with proposed materials/items to be stored.
3. Door Schedule notes Hardware Group #1 to be used, only Hardware Group #2 is listed. Please verify.
4. Interior wall details do not match from A-4.0 to A-5.0.
|
Application received | | | 3/26/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Mar 26 2019 9:36AM
|
Place hold on job | 1/22/2020 | | | | |
|
|
|
make sure plumbing permit is pulled and completed before printing off occupancy
|