Permanent Occupancy | | | 4/12/2019 | | DONE |
|
|
|
|
BLD-Final | 4/10/2019 | 4/11/2019 | 4/11/2019 | A | PASS |
Jim Sly
|
|
|
Beth Phone #: ###-#### OK for Perm Occ.
|
BLD-Final | 4/5/2019 | 4/8/2019 | 4/8/2019 | P | PART |
Jim Storey
|
|
|
Beth Phone #: ###-#### bag exit at power door/ change lockset office. tco ok
|
FIRE-Final Inspection | 4/8/2019 | 4/8/2019 | 4/8/2019 | P | PASS |
Jim Page
|
|
|
Previously noted items have been corrected, final life fire safety inspection complete.
|
FIRE-Final Inspection | 4/5/2019 | 4/8/2019 | 4/8/2019 | A | FAIL |
Jim Page
|
|
|
Provide annual inspection for fire extinguisher, add fire extinguisher in warehouse. Provide sticker on main entry reading "door to remain unloicked while building is occupied".
Beth Phone #: ###-####
|
Issue PAID IN FULL permit | | | 4/5/2019 | | DONE |
|
|
|
|
Routing - FIRE | 4/4/2019 | 4/4/2019 | 4/4/2019 | | FAIL |
Mark Scharfen
|
|
|
IFC 1st review 04.04.2019.pdf uploaded and emailed to applicant.
|
Routing - FIRE | 4/4/2019 | 4/4/2019 | 4/4/2019 | | PASS |
Mark Scharfen
|
|
|
IFC Final Review 04.04.2019.pdf uploaded. Approved.
|
Permit Ready to Issue | | | 4/4/2019 | | DONE |
|
|
|
met
|
Telephone call | | | 4/4/2019 | | DONE |
|
|
|
Spoke with Beth (Dan is out of the office) informing her the permit is ready after the second review.
|
Plan assigned to (CJW) | 4/1/2019 | 4/1/2019 | 4/3/2019 | | PASS |
Carl Westfall
|
|
|
Occupancy
|
Routing - PLAN CHECK | 4/1/2019 | | 4/3/2019 | | PASS |
Carl Westfall
|
|
|
Occupancy review completed and approved
|
1st review completed | | | 4/3/2019 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/3/2019 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 4/3/2019 | | DONE |
|
|
|
|
Print Occupancy Form | | | 4/3/2019 | | DONE |
|
|
|
|
Telephone call | | | 4/3/2019 | | DONE |
|
|
|
Spoke with Beth (dan was out of the office) informing her that this permit is ready to be picked up.
|
CHANGE STATUS TO (REV) | | | 4/3/2019 | | DONE |
|
|
|
per Carl M
|
Intake Approval | | | 4/1/2019 | | PASS |
Carl Westfall
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 4/1/2019 | | DONE |
|
|
|
|
First Notice | | 4/22/2019 | | | |
|
|
|
|
Application received | | 4/1/2019 | | | |
|
|
|
|