BLD-Final | 6/6/2019 | 6/6/2019 | 6/6/2019 | A | PASS |
Jim Storey
|
|
|
|
BLD-Final | 6/5/2019 | 6/6/2019 | 6/6/2019 | A | PASS |
Jim Storey
|
|
|
Inspection requested via web by Candyce Moss
|
DOC - Permit Finaled | 6/6/2019 | 6/6/2019 | 6/6/2019 | P | PASS |
Jim Storey
|
|
|
|
BLD-Footing | 5/30/2019 | 5/31/2019 | 5/31/2019 | A | PASS |
Tony Young
|
|
|
Inspection requested via web by Candyce Moss..3 patio footings ok,, per plan
|
Issue PAID IN FULL permit | | | 5/14/2019 | | DONE |
|
|
|
|
Plan assigned to (JAB) Josh | 4/2/2019 | 4/2/2019 | 5/13/2019 | | PASS |
Josh Bogle
|
|
|
4/8 patio cover, ePlan - 1st done
|
Plan Reviewer's activity | | | 5/13/2019 | | DONE |
Josh Bogle
|
|
|
sent this for another round to satisfy Planning
|
Routing - PLANNING | 5/13/2019 | | 5/13/2019 | | PASS |
KayCee Babb
|
|
|
Per DRH19-00153, to comply with all Conditions of Approval.
|
Routing - PLAN CHECK | 5/13/2019 | | 5/13/2019 | | PASS |
Josh Bogle
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/13/2019 | | DONE |
Josh Bogle
|
|
|
ESC no - Energy no
|
Permit Ready to Issue | | | 5/13/2019 | | DONE |
|
|
|
|
Routing - PLANNING | 5/1/2019 | | 5/1/2019 | | FAIL |
KayCee Babb
|
|
|
Historic approval was issued through DRH19-00153 on April 30, 2019. A 10-day appeal period from the date of issuance must pass prior to passage of Building permits. Appeal period expires at 5pm on May 10th.
|
1st review completed | | | 4/4/2019 | | FAIL |
Josh Bogle
|
|
|
|
Routing - PLAN CHECK | 4/2/2019 | | 4/4/2019 | | FAIL |
Josh Bogle
|
|
|
no review pending Planning approval
|
Routing - PLANNING | 4/2/2019 | | 4/2/2019 | | FAIL |
Sue Cummings
|
|
|
Requires Design Review for a Substandard lot approval prior to obtaining a BLD
|
Intake Approval | | | 4/2/2019 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 4/2/2019 | | DONE |
|
|
|
no fees paid at intake
|
Application received | | | 4/1/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Apr 1 2019 4:44PM
|