First Notice | | 7/26/2020 | 8/11/2020 | | DONE |
|
|
|
MAILED 8-14-2020
|
Permanent Occupancy | | | 7/16/2020 | | DONE |
|
|
|
|
BLD-Final | 7/13/2020 | 7/14/2020 | 7/14/2020 | A | PASS |
Mike Jordan
|
|
|
SCREENED // Cecil Phone #: ###-####. . Ok for perm occ.
|
FIRE-Final Inspection | 6/29/2020 | 6/30/2020 | 6/30/2020 | A | PASS |
Troy Cobbley
|
|
|
Life safety, fire alarm and fire sprinkler passed.
screened // cecil Phone #: ###-####
|
FIRE-Final Inspection | 6/18/2020 | 6/19/2020 | 6/19/2020 | A | FAIL |
Troy Cobbley
|
|
|
Need project related fire alarm done prior to a life safety.
Screened- Cezal Phone #: ###-####
|
BLD-Ceiling Grid Inspection | 6/11/2020 | 6/12/2020 | 6/12/2020 | A | PASS |
Mike Jordan
|
|
|
Screened- Pezil Phone #: ###-####
|
BLD-Framing/Rough-in | 6/2/2020 | 6/2/2020 | 6/2/2020 | P | PASS |
Mike Jordan
|
|
|
screened // Cecil Phone #: ###-####
|
CHANGE STATUS TO (ISS) | | | 4/20/2020 | | DONE |
|
|
|
|
Plan assigned to (CJW) | 3/20/2020 | 3/20/2020 | 4/16/2020 | | PASS |
Carl Westfall
|
|
|
plan mod - St. Als - MOB #6 - exterior ducts (need to know time from KPFF)
|
Routing - PLAN CHECK | 4/15/2020 | | 4/16/2020 | | PASS |
Carl Westfall
|
|
|
|
Plan Reviewer's activity | | | 4/16/2020 | | PASS |
|
|
|
Plan mod review approved
|
Permit Ready to Issue | | | 4/16/2020 | | DONE |
|
|
|
PLAN MOD MET
|
Plan resubmittals received | | | 4/15/2020 | | DONE |
|
|
|
|
Plan resubmittals requested | | | 4/13/2020 | | DONE |
|
|
|
|
Routing Off Site - STRUCTURAL | 3/25/2020 | | 4/10/2020 | | PASS |
Carl Westfall
|
|
|
Cory Harelson (KPFF)
|
Routing - Design Review | 3/25/2020 | | 3/26/2020 | | PASS |
KayCee Babb
|
|
|
Per DRH20-00109
|
Routing - FIRE | 3/25/2020 | 3/25/2020 | 3/25/2020 | | PASS |
Mark Stumbaugh
|
|
|
No review needed Plan Mod for Mark Stumbaugh
|
Routing - PLANNING | 3/25/2020 | | 3/25/2020 | | PASS |
Jeff Lowe
|
|
|
this is reviewed under DRH20-00109
|
Routing - PLAN CHECK | 3/24/2020 | | 3/25/2020 | | PEND |
Carl Westfall
|
|
|
Routed drawings
|
Routing - MECHANICAL | 3/25/2020 | | 3/25/2020 | | PASS |
Troy James
|
|
|
|
Routing - PLAN CHECK | 3/20/2020 | | 3/23/2020 | | FAIL |
Carl Westfall
|
|
|
Plan intake review approved. IBC plan review failed. Approved roof sheathing required
|
Plan Modification Accepted | | | 3/20/2020 | | DONE |
|
|
|
Aurora with Lombard Conrad Arch. Opening up for plan modification. Plan Mod does not affect value of work being done.
See email in documents.
|
FIRE-Conference | 2/4/2020 | 2/4/2020 | 2/4/2020 | P | DONE |
Troy Cobbley
|
|
|
Life safety passed for Storage Room 309.
Cecil Phone #: ###-####
|
BLD-Framing/Rough-in | 11/14/2019 | 11/15/2019 | 11/15/2019 | A | PASS |
Mike Jordan
|
|
|
Cecil Phone #: ###-####
|
BLD-Framing/Rough-in | 10/1/2019 | 10/2/2019 | 10/2/2019 | A | PASS |
Mike Jordan
|
|
|
Cecel Phone #: ###-####. Pre rock on 2hr. fire wall at soffit.
|
Print Occupancy Form | | | 9/27/2019 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 9/27/2019 | | DONE |
|
|
|
|
Plan assigned to (CJW) | 7/30/2019 | 8/21/2019 | 9/25/2019 | | PASS |
Carl Westfall
|
|
|
(1st done) 08/14/19 (L-3 - 15 days) (eplan - 40 sheets) St Al's - EP Lab (waiting for fire)
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/25/2019 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 9/25/2019 | | DONE |
|
|
|
MET BBYINGTON@KREIZENBECK.COM
Need
GC Form
Revsied Cert of Value
|
Routing - FIRE | 9/17/2019 | 9/17/2019 | 9/24/2019 | | PASS |
Mark Stumbaugh
|
|
|
09/23 (resubmittal) SARMC EP Lab, ePlan
|
Routing Off Site - STRUCTURAL | 9/17/2019 | | 9/23/2019 | | PASS |
Carl Westfall
|
|
|
Cory Harelson (KPFF)
|
Routing - PLAN CHECK | 9/16/2019 | | 9/18/2019 | | PASS |
Carl Westfall
|
|
|
Passed pending structural. Received the Emailed drawings from the applicant and uploaded them. Started the routing to other agencies.
|
Telephone call | | | 9/17/2019 | | DONE |
|
|
|
Called the Applicant. Explained what needed to be seen on the drawings. Told her to Email the revised drawings to me and I would upload them.
|
Plan resubmittals received | | | 9/16/2019 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 9/3/2019 | | 9/4/2019 | | FAIL |
Carl Westfall
|
|
|
Failed the resubmittal plan intake review. Routed back to the applicant.
|
Route to Impact Fee Review | 8/23/2019 | 8/26/2019 | 8/26/2019 | | PASS |
Eric Bilimoria
|
|
|
Review requested for Commercial Permit
|
Routing - FIRE | 7/30/2019 | 7/30/2019 | 8/23/2019 | | FAIL |
Mark Scharfen
|
|
|
08/23-SARMC EP Lab 520 review complete. Uploade and emailed architect rev_fire 08.23.2019.pdf
|
1st review completed | | | 8/23/2019 | | DONE |
|
|
|
Time frame was not met because Fire did not get their review done in time.
|
Plan resubmittals requested | | | 8/23/2019 | | DONE |
|
|
|
|
Routing PW Environmental | 7/31/2019 | | 8/14/2019 | | PASS |
Rick Christenson
|
|
|
|
Routing - PLAN CHECK | 7/30/2019 | | 8/13/2019 | | FAIL |
Carl Westfall
|
|
|
|
Routing Off Site - STRUCTURAL | 7/30/2019 | | 8/12/2019 | | FAIL |
Carl Westfall
|
|
|
Cory Harelson (KPFF)
|
Routing - MECHANICAL | 7/30/2019 | | 8/5/2019 | | PASS |
Troy James
|
|
|
|
Routing - Addressing | 7/30/2019 | | 8/2/2019 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 7/30/2019 | | 7/31/2019 | | PASS |
Angela Hardy
|
|
|
|
Routing - PLUMBING | 7/30/2019 | | 7/31/2019 | | PASS |
Daryl Spivey
|
|
|
Per plan and ISPC and NFPA 99
|
Routing - PLANNING | 7/30/2019 | | 7/31/2019 | | PASS |
Stephanie Leonard
|
|
|
|
Intake Approval | | | 7/25/2019 | | PASS |
|
|
|
|
Application received | | | 4/3/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Apr 3 2019 4:16PM
|
Second Notice | | 8/21/2020 | | | |
|
|
|
|