First Notice | | 9/28/2019 | 9/19/2019 | | DONE |
|
|
|
This permit finaled on the web by Brian McCoy
|
DOC - Permit Finaled | | | 9/18/2019 | | DONE |
|
|
|
passed final inspection 9-17-19
|
Letter of compliance/Occupancy | | | 9/18/2019 | | DONE |
|
|
|
|
BLD-Final | 9/16/2019 | 9/17/2019 | 9/17/2019 | P | PASS |
Tell Riley
|
|
|
Please call 30 mins ahead of time so I can meet you there. Phone #: ###-#### Inspection requested via web by Gerome Fries//final complete per plans//
|
FIRE-Final Inspection | 9/16/2019 | 9/17/2019 | 9/17/2019 | A | PASS |
Troy Cobbley
|
|
|
life safety passed. Card signed.
Please call 30 mins ahead of time so I can meet you there. Phone #: ###-#### Inspection requested via web by Gerome Fries
|
FIRE-Final Inspection | 9/16/2019 | 9/16/2019 | 9/16/2019 | P | CANC |
Troy Cobbley
|
|
|
Please call 30 mins ahead of time so I can meet you there. Phone #: ###-#### >> Inspection requested via web by Gerome Fries Inspection cancelled from web by: Gerome Fries
|
FIRE-Final Inspection | 9/14/2019 | 9/16/2019 | 9/16/2019 | A | PART |
Mike Jordan
|
|
|
Please call 30 mins ahead so I can meet you there. Phone #: ###-#### Inspection requested via web by Gerome Fries. Fire/life safety will be ok for perm. as soon as the project related fire sprinkler permit has been finaled.
|
BLD-Final | 9/14/2019 | 9/16/2019 | 9/16/2019 | P | CANC |
Tell Riley
|
|
|
Please call 30 mins ahead of time so I can meet you there. Phone #: ###-#### >> Inspection requested via web by Gerome Fries Inspection cancelled from web by: Gerome Fries
|
BLD-Final | 9/13/2019 | 9/16/2019 | 9/14/2019 | A | CANC |
Tell Riley
|
|
|
Please call 3 mins head of time so I can meet you there. Phone #: ###-#### >> Inspection requested via web by Gerome Fries Inspection cancelled from web by: Gerome Fries
|
BLD-Ceiling Grid Inspection | 8/29/2019 | 8/30/2019 | 8/30/2019 | P | PASS |
Mike Jordan
|
|
|
Please call 30 mins ahead of arrival. Phone #: ###-#### Inspection requested via web by Gerome Fries
|
BLD-Framing/Rough-in | 8/16/2019 | 8/19/2019 | 8/19/2019 | P | PASS |
Tell Riley
|
|
|
Please call 30 min in ahead of time so I can meet you there. Phone #: ###-#### Inspection requested via web by Gerome Fries//wall cover for partitions in office area//ok to cover walls only//call for grid inspection//
|
BLD-Final | 7/18/2019 | 7/18/2019 | 7/18/2019 | P | PART |
Tell Riley
|
|
|
Please call 30 minutes ahead Phone #: ###-#### Inspection requested via web by Gerome Fries//temp occupancy approved for phase 1 minor remodel//life safety and electrical have passed in this area//no temp occupancy signature area on card//
|
FIRE-Final Inspection | 7/17/2019 | 7/17/2019 | 7/18/2019 | P | PART |
Troy Cobbley
|
|
|
Life safety passed for the south side tennt space of the remodel work.
Phone #: ###-#### Inspection requested via web by Gerome Fries
|
BLD-Final | 7/12/2019 | 7/17/2019 | 7/17/2019 | A | NR |
Mike Jordan
|
|
|
Please call 30 mins ahead of time Phone #: ###-#### Inspection requested via web by Gerome Fries. Fire final has failed.
|
FIRE-Final Inspection | 7/12/2019 | 7/16/2019 | 7/16/2019 | P | FAIL |
Troy Cobbley
|
|
|
Inspection was just for the south half of the second floor at this time. Basically all exit signs need repaired and emergency lighting provided in the remodeled tenant space and in the paths of egress down both stair wells and out of the building. All other items for this phase of the work appear ok.
Please call 30 mins ahead of time Phone #: ###-#### Inspection requested via web by Gerome Fries
|
BLD-Ceiling Grid Inspection | 6/26/2019 | 6/26/2019 | 6/26/2019 | A | PART |
Tell Riley
|
|
|
Please call 30 mins ahead of time so I can meet you there. Phone #: ###-#### Inspection requested via web by Gerome Fries//grid ok//need to get mechanical completed and inspected//do not cover until HVAC is passed//divider wall framing ok per engineering.//
|
BLD-Framing/Rough-in | 5/31/2019 | 6/3/2019 | 6/3/2019 | P | PASS |
Mike Jordan
|
|
|
Please call 30 mins ahead of time so I can meet you there. Phone #: ###-#### Inspection requested via web by Gerome Fries. Interior steel stud framed walls only for phase 1. Will need inspection and engineering for folding wall system when installed.
|
Permit Ready to Issue | | | 4/29/2019 | | DONE |
|
|
|
ALL MET
need
GC FORM
REVISED VALUE
|
Issue PAID IN FULL permit | | | 4/29/2019 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 4/29/2019 | | DONE |
|
|
|
|
Plan assigned to (JG) | 4/9/2019 | 4/9/2019 | 4/27/2019 | | PASS |
Javier Guzman
|
|
|
2nd rev, 04/19 L2 Carollo Engineers 2nd floor ePlan
|
Routing - PLAN CHECK | 4/25/2019 | | 4/27/2019 | | PASS |
Javier Guzman
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/27/2019 | | DONE |
|
|
|
|
Route to Impact Fee Review | 4/12/2019 | 4/15/2019 | 4/12/2019 | | PASS |
Eric Bilimoria
|
|
|
Review requested for Commercial Permit
|
Routing - PLAN CHECK | 4/9/2019 | | 4/12/2019 | | FAIL |
Javier Guzman
|
|
|
|
1st review completed | | | 4/12/2019 | | FAIL |
Javier Guzman
|
|
|
|
Routing - Addressing | 4/9/2019 | | 4/10/2019 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 4/9/2019 | | 4/9/2019 | | PASS |
Angela Hardy
|
|
|
|
Intake Approval | | | 4/8/2019 | | PASS |
Javier Guzman
|
|
|
|
Application received | | | 4/4/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Apr 4 2019 1:34PM
|