BLD-Final | 10/9/2019 | 10/10/2019 | 10/10/2019 | P | PASS |
Dave Hannah
|
|
|
Rob Phone #: ###-####
|
DOC - Permit Finaled | 10/10/2019 | 10/10/2019 | 10/10/2019 | P | PASS |
Dave Hannah
|
|
|
|
BLD-Blower Door Test Results | 10/10/2019 | 10/10/2019 | 10/10/2019 | P | PASS |
Dave Hannah
|
|
|
4.3
|
BLD-Energy code compliance | 7/29/2019 | 7/30/2019 | 7/30/2019 | P | PASS |
Tell Riley
|
|
|
Robert Phone #: ###-####//corrections made//
|
BLD-Energy code compliance | 7/26/2019 | 7/29/2019 | 7/29/2019 | A | NR |
Tony Young
|
|
|
Rob Phone #: ###-####,, needs fire sprinkler passes 1st
|
BLD-Framing/Rough-in | 7/25/2019 | 7/26/2019 | 7/26/2019 | A | PASS |
Tony Young
|
|
|
Rob Phone #: ###-####
|
BLD-Framing/Rough-in | 7/23/2019 | 7/23/2019 | 7/24/2019 | P | DONE |
Dave Hannah
|
|
|
Rob Phone #: ###-####
|
BLD-Framing/Rough-in | 7/24/2019 | 7/24/2019 | 7/24/2019 | A | PASS |
Dave Hannah
|
|
|
Rob Phone #: ###-#### c/n on site ok to insulate
|
BLD-Wall Bracing | 7/1/2019 | 7/1/2019 | 7/1/2019 | P | PART |
Tell Riley
|
|
|
Rob Phone #: ###-####//add nuts to 5/8 bolts//check a framing//
|
BLD-Foundation | 6/5/2019 | 6/6/2019 | 6/6/2019 | A | PASS |
Tony Young
|
|
|
Nick Phone #: ###-####
|
BLD-Footing | 6/4/2019 | 6/4/2019 | 6/4/2019 | P | PART |
Tony Young
|
|
|
Nick Phone #: ###-####,, ok after point load footing adjustments
|
Issue PAID IN FULL permit | | | 5/23/2019 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 5/8/2019 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 5/8/2019 | | DONE |
|
|
|
|
Telephone call | | | 5/8/2019 | | DONE |
|
|
|
left a message for robert informing him that this permit is ready and the fee amount due
|
OVERRIDE | | | 5/7/2019 | | |
|
|
|
|
Plan assigned to (J_N) | 4/8/2019 | 4/8/2019 | 5/7/2019 | | DONE |
Jenny Nelson
|
|
|
04/19 sfd L1 Paper. 1st complete 4/12, failed planning and fire
|
Case Summary (BLD) | | | 5/7/2019 | | DONE |
Jenny Nelson
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/7/2019 | | DONE |
Jenny Nelson
|
|
|
|
Override - Parcel Holds | | | 5/7/2019 | | |
|
|
|
|
Permit Ready to Issue | | | 5/7/2019 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 5/7/2019 | | DONE |
|
|
|
|
Routing - FIRE | 5/3/2019 | 5/3/2019 | 5/3/2019 | | PASS |
Lee G Meredith
|
|
|
05/10 Lander St LM Resubmittal 402
Items noted on first review have not been addressed in this resubmittal.
5/7/19 Owner submitted documentation of NFPA 13d sprinkler system being installed to meet minimum fire requirements.
|
Routing - PLANNING | 5/2/2019 | | 5/2/2019 | | PASS |
Sue Cummings
|
|
|
|
Plan resubmittals received | | | 5/2/2019 | | DONE |
|
|
|
Two copies each of small site plan and whole new set of plans because the floorplan changed. Stamped and taken to Jenny
|
1st review completed | | | 4/12/2019 | | DONE |
Jenny Nelson
|
|
|
Failed planning and fire
|
Routing - PLAN CHECK | | | 4/12/2019 | | PASS |
Jenny Nelson
|
|
|
|
Routing - FIRE | 4/11/2019 | | 4/12/2019 | | FAIL |
Lee G Meredith
|
|
|
04/22 913 Lander St. Residential Fire Review.
4-12-19 resubmittal required with corrections addressed. Driveway exceeds limits as is. No SUEZ fire flow provided.
|
Routing - MECHANICAL | 4/9/2019 | | 4/11/2019 | | PASS |
Troy James
|
|
|
|
Route to Impact Fee Review | 4/8/2019 | 4/11/2019 | 4/9/2019 | | PASS |
Karina Myles
|
|
|
Initial residential review of new SFD permits requested for now.
|
Routing - PLANNING | 4/9/2019 | | 4/9/2019 | | FAIL |
|
|
|
The site plan does not match the GIS map nor ROS 11123
|
Routing - Addressing | 4/8/2019 | | 4/9/2019 | | PASS |
Laura Hunter
|
|
|
|
Routing - PUBLIC WORKS | | | 4/9/2019 | | PASS |
|
|
|
|
Plan assigned to (RDP) | 4/8/2019 | 4/8/2019 | 4/8/2019 | | DEFR |
Rob Patrick
|
|
|
04/19 sfd L1 ePlan
|
Intake Approval | | | 4/8/2019 | | PASS |
|
|
|
|
Override - Parcel Holds | | | 4/8/2019 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 4/5/2019 | | DONE |
|
|
|
|
Application received | | 4/5/2019 | | | |
|
|
|
|