Second Notice | | 7/20/2019 | 8/5/2019 | | DONE |
|
|
|
mailed 8/5/19
|
First Notice | | 6/9/2019 | 7/10/2019 | | DONE |
|
|
|
mailed 7-11
|
BLD-Final | 5/30/2019 | 5/30/2019 | 5/30/2019 | P | PASS |
Mike Jordan
|
|
|
Mark Phone #: ###-####. Ok for perm occ.
|
FIRE-Final Inspection | 5/29/2019 | 5/30/2019 | 5/30/2019 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed. Contractor is going to knock out arrows on the exit signs prior to the building inspection.
Mark Phone #: ###-####
|
BLD-Wall cover | 5/28/2019 | 5/30/2019 | 5/30/2019 | P | CANC |
Mike Jordan
|
|
|
Mark Phone #: ###-####
|
Permanent Occupancy | | | 5/30/2019 | | DONE |
|
|
|
|
BLD-Ceiling Grid Inspection | 5/16/2019 | 5/16/2019 | 5/16/2019 | P | PASS |
Mike Jordan
|
|
|
Mark Phone #: ###-####
|
BLD-Framing/Rough-in | 5/15/2019 | 5/15/2019 | 5/15/2019 | A | PASS |
Jim Storey
|
|
|
framing ok to cover
|
BLD-Ceiling Grid Inspection | 5/14/2019 | 5/15/2019 | 5/15/2019 | A | FAIL |
Jim Storey
|
|
|
Mark Phone #: ###-#### wire supports with in 8 inches of perimtior/ missing clips .
|
Issue PAID IN FULL permit | | | 5/14/2019 | | DONE |
|
|
|
|
Print Occupancy Form | | | 5/14/2019 | | DONE |
|
|
|
|
Print Occupancy Form | | | 5/14/2019 | | DONE |
|
|
|
|
Plan assigned to (BJM) | 5/2/2019 | 5/2/2019 | 5/13/2019 | | DONE |
Brian McGowan
|
|
|
04/23 (518 - L2) CVS Services, ePlan
|
Routing - PLAN CHECK | 5/2/2019 | | 5/13/2019 | | PASS |
Brian McGowan
|
|
|
|
1st review completed | | | 5/13/2019 | | DONE |
Brian McGowan
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/13/2019 | | DONE |
Brian McGowan
|
|
|
|
Permit Ready to Issue | | | 5/13/2019 | | DONE |
|
|
|
all met
need GC
need rev cert of val
|
Routing - FIRE | 5/2/2019 | 5/2/2019 | 5/9/2019 | | PASS |
Mark Scharfen
|
|
|
05.09.2019-Completed IFC review. Noted extinguishers to be field verified on plans. Passed fire review.
|
Intake Approval | | | 5/2/2019 | | PASS |
Javier Guzman
|
|
|
|
Intake Approval | | | 4/30/2019 | | FAIL |
Javier Guzman
|
|
|
Provide and upload the following:
• The revised cover sheet “CS” came back with no architect’s stamp, revise and have an Idaho licensed architect stamped, date and sign plan sheet CS
• Previous request not addressed: Plan sheet A3.1 not responding and will not open to view it seems when this happens in the past the file size is too large and needs to be flattened, flatten and re-upload file
• The new checklist showed a plan sheet A1.0 for the interior demolition work but none was uploaded, upload sheet A1.0. Per our records under BLD14-00140 there are wall being demoed in the open office area #101, per checklist revise and provide a plan sheet to show interior walls to be removed.
|
Intake Approval | | | 4/22/2019 | | FAIL |
Javier Guzman
|
|
|
Provide and upload the following:
• Per checklist provide Code Analysis/Building Data on front cover sheet of plans which includes: code year, occupancy group(s), land use zone, construction type, tenant area, fire suppression system (specify NFPA code applicable)
• Plan sheet A3.1 not responding and will not open to view it seems when this happens in the past the file size is too large and needs to be flattened, flatten and re-upload file
• Per our records under BLD14-00140 there are wall being demoed in the open office area #101, per checklist revise and show interior walls to be removed.
|
Application received | | | 4/9/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Apr 9 2019 8:33AM
|