BLD-Final | 3/26/2020 | 3/27/2020 | 3/27/2020 | P | PASS |
Jim Storey
|
|
|
Please call 30 minutes before hand for access to fire riser room. Phone #: ###-#### Inspection requested via web by Stephen Griswold
|
DOC - Permit Finaled | 3/27/2020 | 3/27/2020 | 3/27/2020 | P | PASS |
Jim Storey
|
|
|
|
FIRE-Final Inspection | 3/25/2020 | 3/26/2020 | 3/26/2020 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed. Call for access/site meeting. Phone #: ###-#### Inspection requested via web by Stephen Griswold
|
FIRE-Final Inspection | 3/25/2020 | 3/25/2020 | 3/25/2020 | P | FAIL |
Troy Cobbley
|
|
|
Need city approved plans an dsmall documents, need smoke alarms placed and tested as discussed, need fire extinguisher placed as discussed. Need address as discussed.
NEED FINAL LIFE SAFETY COMPLETED; WAS NOT DONE DURING INITIAL FIRE FINAL INSPECTION Phone #: ###-#### Inspection requested via web by Stephen Griswold
|
BLD-Final | 3/24/2020 | 3/24/2020 | 3/24/2020 | P | CANC |
Jim Storey
|
|
|
Please call prior to inspection to coordinate access. Phone #: ###-#### >> Inspection requested via web by Stephen Griswold Inspection cancelled from web by: Stephen Griswold
|
BLD-Final | 1/3/2020 | 1/3/2020 | 1/3/2020 | P | FAIL |
Jim Storey
|
|
|
Phone #: ###-#### Inspection requested via web by Stephen Griswold need fire and hvac finals
|
FIRE-Final Inspection | 1/3/2020 | 1/3/2020 | 1/3/2020 | P | CANC |
Troy Cobbley
|
|
|
Need fire alarm and sprinkler permits addressed as per discussion before life safety inspection can be completed.
Phone #: ###-#### Inspection requested via web by Stephen Griswold
|
BLD-Framing/Rough-in | 9/30/2019 | 9/30/2019 | 9/30/2019 | P | PART |
Jim Storey
|
|
|
Phone #: ###-#### Inspection requested via web by Stephen Griswold INSP-Sprinkler Rough-in 9/26/2019 9/27/2019 9/27/2019 P PART
DetailsTroy Cobbley Tenting failed for all areas. No piping to be covered. Rough-in passed for the single level area of work but again no piping can be covered. Also prior to a final inspection R38 insulation value will need to be provided. framing ok to cover upon passing fire insp.
|
BLD-Framing/Rough-in | 9/5/2019 | 9/5/2019 | 9/5/2019 | P | FAIL |
Jim Storey
|
|
|
need fire chakl per plan/ need hvac permit and insp./ fire spk insp// group all permits to bld.
|
BLD-Framing/Rough-in | 9/4/2019 | 9/4/2019 | 9/4/2019 | P | NR |
Jim Storey
|
|
|
Phone #: ###-#### Inspection requested via web by Stephen Griswold
|
BLD-Framing/Rough-in | 8/6/2019 | 8/6/2019 | 8/6/2019 | P | FAIL |
Jim Storey
|
|
|
Phone #: ###-#### Inspection requested via web by Stephen Griswold c/n arch to address conf with builder.
|
Issue PAID IN FULL permit | | | 7/19/2019 | | DONE |
|
|
|
|
Print Occupancy Form | | | 7/19/2019 | | DONE |
|
|
|
|
Telephone call | | | 7/19/2019 | | DONE |
|
|
|
Email permit and inspection card to- andrewc@brightstarps.com & info@brightstarps.com
|
Route to Impact Fee Review | 5/24/2019 | 5/27/2019 | 5/28/2019 | | PASS |
Karina Myles
|
|
|
Review requested for Commercial Permit
|
Permit Ready to Issue | | | 5/28/2019 | | DONE |
|
|
|
MET STEPHENG@BRIGHTSTARPS.COM
NEED
GC FORM
REVISED VALUE
|
Plan assigned to (CJW) | 5/2/2019 | 5/2/2019 | 5/24/2019 | | PASS |
Carl Westfall
|
|
|
(1st done) 05/17/19 (L-3 - 15 days) (eplan - 7 sheets) Sierra Vista condos (waiting for fire)
|
1st review completed | | | 5/24/2019 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/24/2019 | | DONE |
|
|
|
|
Routing - FIRE | 5/2/2019 | 5/2/2019 | 5/23/2019 | | PASS |
Mark Scharfen
|
|
|
Completed fire review and uploade rev_fire 05.23.2019.pdf. Passed review.
|
Routing - PLAN CHECK | 5/2/2019 | | 5/17/2019 | | PASS |
Carl Westfall
|
|
|
1st IBC plan review approved with conditions
|
Routing - PLANNING | 5/2/2019 | | 5/6/2019 | | PASS |
Celine Acord
|
|
|
|
Routing - MECHANICAL | 5/2/2019 | | 5/3/2019 | | PASS |
Chad Schwendiman
|
|
|
|
Routing - PUBLIC WORKS | 5/2/2019 | | 5/3/2019 | | PASS |
Morgan Webb
|
|
|
NO NEW FEES. CREDIT FOR EXISTING FIXTURES
|
Routing - PLUMBING | 5/2/2019 | | 5/2/2019 | | PASS |
Dan Ediger
|
|
|
Per plans and ISPC
|
Routing - Addressing | 5/2/2019 | | 5/2/2019 | | PASS |
Doug Chausow
|
|
|
|
Routing - Design Review | 5/2/2019 | | 5/2/2019 | | PASS |
Josh Wilson
|
|
|
|
Intake Approval | | | 4/29/2019 | | PASS |
|
|
|
|
Plan Reviewer's activity | | | 4/26/2019 | | DONE |
Michael Hanson
|
|
|
This project was approved by CJW last year, permit expired, assign to CJW for quick review
|
Intake Approval | | | 4/25/2019 | | FAIL |
Michael Hanson
|
|
|
4-25-19 UPDATES IN ALL CAPS
1. Provide Form #304 - Registered Design Professional. COMPLETED
2. Site Specific fire flow letter from SUEZ. COMPLETED
3. Site Plan does not indicate Fire Hydrant locations. COMPLETED
4. One exterior elevation has not been provided. Please provide all (4) exterior elevations. COMPLETED
5. Finish schedule not provided. PLEASE PROVIDE
6. No structural calculations provided as indicated by Submittal Checklist. COMPLETED
7. No lighting or mechanical COMchecks provided. CANNOT BE DEFERRED PLEASE PROVIDE
8. No fixture schedule provided. CANNOT BE DEFERRED PLEASE PROVIDE
9. No Plumbing Plan provided or Letter from the Chief Plumbing Inspector not requiring stamped plans from an Engineer provided. CANNOT BE DEFERRED PLEASE PROVIDE
10. No Electrical Plan provided or Letter from the Chief Electrical Inspector not requiring stamped plans from an Engineer provided. CANNOT BE DEFERRED PLEASE PROVIDE
11. Accessible upgrade work not specified on plans. PLEASE PROVIDE
|
Intake Approval | | | 4/16/2019 | | FAIL |
Brian McGowan
|
|
|
4-16-19
1. Provide Form #304 - Registered Design Professional.
2. Site Specific fire flow letter from SUEZ.
3. Site Plan does not indicate Fire Hydrant locations.
4. One exterior elevation has not been provided. Please provide all (4) exterior elevations.
5. Finish schedule not provided.
6. No structural calculations provided as indicated by Submittal Checklist.
7. No lighting or mechanical COMchecks provided.
8. No fixture schedule provided.
9. No Plumbing Plan provided or Letter from the Chief Plumbing Inspector not requiring stamped plans from an Engineer provided.
10. No Electrical Plan provided or Letter from the Chief Electrical Inspector not requiring stamped plans from an Engineer provided.
11. Accessible upgrade work not specified on plans.
|
Intake Approval | | | 4/11/2019 | | FAIL |
Brian McGowan
|
|
|
Application #520 – Major Tenant Improvement Submittal Checklist must be provided with all required information and documents. This Form must be completely filled out before your Prescreen can begin to be processed.
|
Application received | | | 4/9/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Apr 9 2019 12:17PM
|
First Notice | 3/27/2020 | 3/27/2020 | | | |
Jim Storey
|
|
|
|