Information based on query as of Tuesday, July 23, 2024.
Permit Information
Permit NumberBLD19-01157
StatusFinaled
Name HHS CONSTRUCTION LLC
Site Address 2427 S TRAPPER PL
Project NameHarris North Lot 3 Block 1
Customer Number 
ePlanReviewYes
Description
**PRESCRIPTIVE ENERGY REQUIREMENTS** Permit for the construction of a new 2970 sq. ft., one story single family dwelling with 3 bedrooms, 2.5 bathrooms, approximately 375 sq. ft. of covered patio/porch and a 828 sq. ft. attached garage per the approved plans and any notations. SP-01 zoning and setbacks per planning. JJN NO SPRINKLERS REQUIRED. LGM
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Please e-mail the stamped inspection approval letter to mjannusch@cityofboise.org and allow 24 hours for subgrade approval processing. Call Melissa Jannusch at 208-608-7168 with questions.

Prior to obtaining a final for the permit, the roof storm drainage system must be inspected by Public Works. Call Melissa Jannusch at 208-608-7168.

The final inspection of the site grading and drainage work shall be done by the design engineer. Written approval shall be submitted to Boise Public Works prior to the issuance of the building final.
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final10/31/201910/31/201910/31/2019PPASS
DetailsBrandon Shaw
Les Phone #: ###-####
DOC - Permit Finaled10/31/201910/31/201910/31/2019PPASS
DetailsBrandon Shaw
BLD-Blower Door Test Results10/31/201910/31/201910/31/2019PDONE
DetailsBrandon Shaw
ACH50- 3.78
PubWorks Occupancy Approval10/31/201910/31/201910/31/2019 DONE
DetailsMelissa Jannusch
A letter from the applicant’s design professional indicating that the final grading and drainage is acceptable has been received by Public Works. Final occupancy may be approved by the building department. Melissa Jannusch ###-####.

BLD-Energy code compliance7/18/20197/18/20197/18/2019PPASS
DetailsBrandon Shaw
LES Phone #: ###-####
BLD-Framing/Rough-in7/3/20197/5/20197/5/2019APART
DetailsBrandon Shaw
Pending corrections- Straps at break in double top plates, drill and install hold downs per plans, point laod to bear down to foundation...
See red crayon...
BLD-Wall Bracing6/11/20196/11/20196/11/2019PPASS
DetailsBrandon Shaw
Work in progress...
Hold downs to be installed by framing rough-in...
BLD-Foundation5/16/20195/17/20195/17/2019ACANC
DetailsBrandon Shaw
Jerry Phone #: ###-####
BLD-Wall Bracing5/16/20195/16/20195/17/2019PPASS
DetailsBrandon Shaw
Foundation...
Work in progress...
BLD-Footing5/15/20195/15/20195/15/2019PPASS
DetailsBrandon Shaw
Work in progress...
PubWorks Subgrade Approval5/15/20195/15/20195/15/2019 DONE
DetailsMelissa Jannusch
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Melissa Jannusch ###-####.

Issue PAID IN FULL permit  5/3/2019 DONE
emailed permit to- kdavis@boisehunterhomes.com to signed permit
Inspection Record Card- Bld  5/3/2019 DONE
OVERRIDE  4/15/2019  
Route to Impact Fee Review4/12/20194/15/20194/15/2019 PASS
DetailsShannon Cade
Initial residential review of new SFD permits requested for now.
Plan assigned to (J_N)4/12/20194/12/20194/15/2019 DONE
Details
05/01 sfd L2 ePlan. 1st complete 4/15, waiting for hillside
Routing - PLAN CHECK4/12/2019 4/15/2019 PASS
DetailsJenny Nelson
Routing PW Grading-Hillside4/12/2019 4/15/2019 PASS
DetailsMelissa Jannusch

A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Please e-mail the stamped inspection approval letter to mjannusch@cityofboise.org and allow 24 hours for subgrade approval processing. Call Melissa Jannusch at ###-#### with questions.

Prior to obtaining a final for the permit, the roof storm drainage system must be inspected by Public Works. Call Melissa Jannusch at ###-####.

The final inspection of the site grading and drainage work shall be done by the design engineer. Written approval shall be submitted to Boise Public Works prior to the issuance of the building final.
1st review completed  4/15/2019 DONE
DetailsJenny Nelson
PLANS/APPL TAKEN TO FRONT DESK  4/15/2019 DONE
DetailsJenny Nelson
Permit Ready to Issue  4/15/2019 DONE
Routing - FIRE4/12/20194/12/20194/12/2019 PASS
DetailsLee G Meredith
04/25 2427 S Trapper Residential Hillside

No sprinklers required. LGM
Routing - Erosion and Sediment4/12/2019 4/12/2019 PASS
DetailsMichael Zawacki
Foothills lot.
Intake Approval  4/12/2019 PASS
Routing - MECHANICAL4/12/2019 4/12/2019 PASS
DetailsTroy James
Routing - PLANNING4/12/2019 4/12/2019 PASS
DetailsSue Cummings
Routing - Addressing4/12/2019 4/12/2019 PASS
DetailsDoug Chausow
Routing - PUBLIC WORKS4/12/2019 4/12/2019 PASS
DetailsMorgan Webb
Application received  4/11/2019 DONE
Application submitted via PDS Online on Apr 11 2019 8:30AM