BLD-Final | 9/13/2019 | 9/13/2019 | 9/13/2019 | P | PASS |
Tell Riley
|
|
|
Mike Phone #: ###-####//hand rail fixed//
|
DOC - Permit Finaled | 9/13/2019 | 9/13/2019 | 9/13/2019 | P | PASS |
Tell Riley
|
|
|
|
BLD-Final | 8/30/2019 | 9/3/2019 | 9/3/2019 | A | PART |
Tell Riley
|
|
|
Mike Phone #: ###-####//need to change handrail at steps to meet code requirements//discussed with contractor on phone//all other areas complete//
|
BLD-Framing/Rough-in | 8/8/2019 | 8/9/2019 | 8/9/2019 | A | PASS |
Tell Riley
|
|
|
Mike Phone #: ###-####//deck framing ok to cover//call for final when project is complete//
|
Routing Walk-In (BLD) | 8/8/2019 | 8/8/2019 | 8/8/2019 | A | PASS |
Josh Bogle
|
|
|
asked Techs to return to Issued status
|
Plan assigned to (JAB) Josh | 8/6/2019 | 8/6/2019 | 8/8/2019 | | DONE |
Josh Bogle
|
|
|
plan mod not needed
|
Permit Ready to Issue | | | 8/8/2019 | | DONE |
|
|
|
Per JAB put back in issued status
|
CHANGE STATUS TO (ISS) | | | 8/8/2019 | | DONE |
|
|
|
|
Routing Walk-In (BLD) | 8/6/2019 | 8/6/2019 | 8/6/2019 | P | FAIL |
Jenny Nelson
|
|
|
Plan for JAB, took in for JAB to review
|
Routing Walk-In (Zoning) | 8/6/2019 | 8/6/2019 | 8/6/2019 | P | PASS |
Jeff Lowe
|
|
|
plan mod. since it is uncovered stair then no sub-standard ordinance reveiw required.
|
Plan Modification Accepted | | | 8/6/2019 | | DONE |
|
|
|
changining roof over head
|
BLD-Framing/Rough-in | 5/7/2019 | 5/8/2019 | 5/8/2019 | A | PART |
Jim Sly
|
|
|
Mike Phone #: ###-#### Addition framing OK (no Deck yet). Wall bracing and energy code OK too.
|
BLD-Foundation | 4/15/2019 | 4/16/2019 | 4/17/2019 | P | PASS |
Dave Hannah
|
|
|
Mike-manothic pour Phone #: ###-#### ftg and foundation
|
Routing Walk-In (BLD) | 4/12/2019 | 4/12/2019 | 4/12/2019 | A | DONE |
Josh Bogle
|
|
|
|
Routing - PLAN CHECK | 4/12/2019 | | 4/12/2019 | | PASS |
Josh Bogle
|
|
|
|
1st review completed | | | 4/12/2019 | | DONE |
Josh Bogle
|
|
|
|
Inspection Record Card- Bld | | | 4/12/2019 | | DONE |
Josh Bogle
|
|
|
|
Case Summary (BLD) | | | 4/12/2019 | | DONE |
Josh Bogle
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/12/2019 | | DONE |
Josh Bogle
|
|
|
|
Permit Ready to Issue | | | 4/12/2019 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 4/12/2019 | | DONE |
|
|
|
|
Routing Walk-In (Zoning) | 4/11/2019 | 4/11/2019 | 4/11/2019 | A | PASS |
Ethan Mansfield
|
|
|
|
Routing Walk-In (BLD) | 4/11/2019 | 4/11/2019 | 4/11/2019 | A | FAIL |
Rob Patrick
|
|
|
Needs to provide better drawings
|
Application received | | 4/11/2019 | | | |
|
|
|
|