Information based on query as of Tuesday, July 23, 2024.
Permit Information
Permit NumberBLD19-01168
StatusFinaled
Name BLUE RAVEN SOLAR LLC
Site Address 3003 S BROOKRIDGE WAY
Project NameNick Canrinus PV
Customer Number 
ePlanReviewYes
Description
Permit for 630sq' of roof-mounted, grid-tied Photo-voltaic panels with micro-inverters; 36 panels in 4 arrays. No work needed to the existing roof structure per engineer’s roof evaluation. All racking, modules, and other listed equipment must be installed by a certified installer. All work per plans, engineering, manufacturer’s specs, & local code. Separate electrical permit required. **JAB**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final5/9/20195/10/20195/10/2019PPASS
DetailsBrandon Shaw
Please call two hours ahead to Nick ###-#### if you can Phone #: ###-#### Inspection requested via web by BRS Permitting
DOC - Permit Finaled5/10/20195/10/20195/10/2019PPASS
DetailsBrandon Shaw
BLD-Framing/Rough-in5/7/20195/9/20195/9/2019ACANC
DetailsBrandon Shaw
If possible, please call the number above before heading to the jobsite. Thank you! Phone #: ###-#### Inspection requested via web by BRS Permitting
Place hold on job4/29/2019 4/29/2019 DONE
DetailsJudith Amador
MET-need- signed permit
Permit Ready to Issue  4/26/2019 DONE
Issue PAID IN FULL permit  4/26/2019 DONE
emailed to -permitting.department@blueravensolar.com
Inspection Record Card- Bld  4/26/2019 DONE
Plan assigned to (JAB) Josh4/12/20194/12/20194/25/2019 PASS
DetailsJosh Bogle
4/18 PV, ePlan - 1st done
Routing - PLAN CHECK4/25/2019 4/25/2019 PASS
DetailsJosh Bogle
PLANS/APPL TAKEN TO FRONT DESK  4/25/2019 DONE
DetailsJosh Bogle
ESC no - Energy no
Routing - PLANNING4/12/2019 4/23/2019 PASS
DetailsSue Cummings
Needs approval from HOA. HOA approval submitted. O.K. now
1st review completed  4/18/2019 FAIL
DetailsJosh Bogle
Routing - PLAN CHECK4/12/2019 4/18/2019 FAIL
DetailsJosh Bogle
no Plan Review pending Planning approval
Plans ACCEPTED BY PLAN TECH  4/12/2019 DONE
Intake Approval  4/12/2019 PASS
Recd Pcfee & Taken To Pln CK  4/12/2019 DONE
Application received  4/11/2019 DONE
Application submitted via PDS Online on Apr 11 2019 1:41PM