BLD-Final | 5/9/2019 | 5/10/2019 | 5/10/2019 | P | PASS |
Brandon Shaw
|
|
|
Please call two hours ahead to Nick ###-#### if you can Phone #: ###-#### Inspection requested via web by BRS Permitting
|
DOC - Permit Finaled | 5/10/2019 | 5/10/2019 | 5/10/2019 | P | PASS |
Brandon Shaw
|
|
|
|
BLD-Framing/Rough-in | 5/7/2019 | 5/9/2019 | 5/9/2019 | A | CANC |
Brandon Shaw
|
|
|
If possible, please call the number above before heading to the jobsite. Thank you! Phone #: ###-#### Inspection requested via web by BRS Permitting
|
Place hold on job | 4/29/2019 | | 4/29/2019 | | DONE |
Judith Amador
|
|
|
MET-need- signed permit
|
Permit Ready to Issue | | | 4/26/2019 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 4/26/2019 | | DONE |
|
|
|
emailed to -permitting.department@blueravensolar.com
|
Inspection Record Card- Bld | | | 4/26/2019 | | DONE |
|
|
|
|
Plan assigned to (JAB) Josh | 4/12/2019 | 4/12/2019 | 4/25/2019 | | PASS |
Josh Bogle
|
|
|
4/18 PV, ePlan - 1st done
|
Routing - PLAN CHECK | 4/25/2019 | | 4/25/2019 | | PASS |
Josh Bogle
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/25/2019 | | DONE |
Josh Bogle
|
|
|
ESC no - Energy no
|
Routing - PLANNING | 4/12/2019 | | 4/23/2019 | | PASS |
Sue Cummings
|
|
|
Needs approval from HOA. HOA approval submitted. O.K. now
|
1st review completed | | | 4/18/2019 | | FAIL |
Josh Bogle
|
|
|
|
Routing - PLAN CHECK | 4/12/2019 | | 4/18/2019 | | FAIL |
Josh Bogle
|
|
|
no Plan Review pending Planning approval
|
Plans ACCEPTED BY PLAN TECH | | | 4/12/2019 | | DONE |
|
|
|
|
Intake Approval | | | 4/12/2019 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 4/12/2019 | | DONE |
|
|
|
|
Application received | | | 4/11/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Apr 11 2019 1:41PM
|