BLD-Final | 10/29/2019 | 10/30/2019 | 10/30/2019 | A | PASS |
Brandon Shaw
|
|
|
les Phone #: ###-####
|
DOC - Permit Finaled | 10/30/2019 | 10/30/2019 | 10/30/2019 | P | PASS |
Brandon Shaw
|
|
|
|
BLD-Blower Door Test Results | 10/30/2019 | 10/30/2019 | 10/30/2019 | A | DONE |
Brandon Shaw
|
|
|
ACH50- 1.71
|
PubWorks Occupancy Approval | 10/17/2019 | 10/17/2019 | 10/17/2019 | | DONE |
Melissa Jannusch
|
|
|
A letter from the applicant’s design professional indicating that the final grading and drainage is acceptable has been received by Public Works. Final occupancy may be approved by the building department. Melissa Jannusch ###-####.
|
BLD-Energy code compliance | 7/31/2019 | 8/1/2019 | 8/1/2019 | A | PASS |
Brandon Shaw
|
|
|
les Phone #: ###-####
|
BLD-Framing/Rough-in | 7/29/2019 | 7/30/2019 | 7/30/2019 | A | PASS |
Brandon Shaw
|
|
|
Les Phone #: ###-####
|
BLD-Ceiling Grid Inspection | 7/23/2019 | 7/24/2019 | 7/24/2019 | A | PASS |
Jim Storey
|
|
|
soffett // Les Phone #: ###-####
|
BLD-Wall Bracing | 6/25/2019 | 6/25/2019 | 6/25/2019 | A | FAIL |
Brandon Shaw
|
|
|
All exterior sheathing to be nailed to sill plates with approved fasteners... Renail all edge and field nailing...
|
BLD-Wall Bracing | 6/24/2019 | 6/25/2019 | 6/25/2019 | A | PASS |
Brandon Shaw
|
|
|
Corrections SAT...
|
BLD-Wall Bracing | 6/21/2019 | 6/21/2019 | 6/21/2019 | P | FAIL |
Jim Storey
|
|
|
Wes Phone #: ###-#### house wraped w/o insp.
|
BLD-Wall Bracing | 6/11/2019 | 6/11/2019 | 6/11/2019 | P | CANC |
Brandon Shaw
|
|
|
Wrong permit #...
|
BLD-Foundation | 6/4/2019 | 6/4/2019 | 6/4/2019 | P | PASS |
Jim Storey
|
|
|
Dion-foundation wall Phone #: ###-####
|
BLD-Footing | 6/3/2019 | 6/3/2019 | 6/3/2019 | P | PASS |
Jim Storey
|
|
|
Dion Phone #: ###-####
|
PubWorks Subgrade Approval | 6/3/2019 | 6/3/2019 | 6/3/2019 | | DONE |
Melissa Jannusch
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Melissa Jannusch ###-####.
|
OVERRIDE | | | 5/15/2019 | | |
|
|
|
|
Plan assigned to (RDP) | 4/18/2019 | 4/18/2019 | 5/15/2019 | | DONE |
Rob Patrick
|
|
|
05/03 sfd L2 ePlan...05-02 Failed
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/15/2019 | | DONE |
Rob Patrick
|
|
|
|
Permit Ready to Issue | | | 5/15/2019 | | DONE |
|
|
|
|
Telephone call | | | 5/15/2019 | | DONE |
|
|
|
Emailed Kyle to inform him that not all the fees for this project have been paid and once the remaining fees have been paid we can issue the permits.
|
Issue PAID IN FULL permit | | | 5/15/2019 | | DONE |
|
|
|
emailed bhhdrafting@boisehunterhomes.com the building permit to sign
|
Inspection Record Card- Bld | | | 5/15/2019 | | DONE |
|
|
|
|
Routing PW Grading-Hillside | 5/13/2019 | | 5/13/2019 | | PASS |
Melissa Jannusch
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Please e-mail the stamped inspection approval letter to mjannusch@cityofboise.org and allow 24 hours for subgrade approval processing. Call Melissa Jannusch at ###-#### with questions.
Prior to obtaining a final for the permit, the roof storm drainage system must be inspected by Public Works. Call Melissa Jannusch at ###-####.
The final inspection of the site grading and drainage work shall be done by the design engineer. Written approval shall be submitted to Boise Public Works prior to the issuance of the building final.
|
Routing - PLAN CHECK | 5/6/2019 | | 5/6/2019 | | PASS |
Rob Patrick
|
|
|
Pending Melissa's review
|
Routing - PLAN CHECK | 5/2/2019 | | 5/2/2019 | | FAIL |
Rob Patrick
|
|
|
Corrections Req'd
|
1st review completed | | | 5/2/2019 | | FAIL |
Rob Patrick
|
|
|
Corrections req'd
|
Routing - FIRE | 4/16/2019 | 4/16/2019 | 4/18/2019 | | PASS |
Lee G Meredith
|
|
|
04/29 6038 E Barber Dr. Residential Fire Review
|
Routing PW Grading-Hillside | 4/17/2019 | | 4/18/2019 | | FAIL |
Melissa Jannusch
|
|
|
See changemarks in ePlan
|
Route to Impact Fee Review | 4/16/2019 | 4/19/2019 | 4/17/2019 | | PASS |
Karina Myles
|
|
|
Initial residential review of new SFD permits requested for now.
|
Routing - MECHANICAL | 4/16/2019 | | 4/17/2019 | | PASS |
Troy James
|
|
|
|
Routing - PLANNING | 4/16/2019 | | 4/17/2019 | | PASS |
Sue Cummings
|
|
|
|
Routing - Addressing | 4/16/2019 | | 4/17/2019 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 4/16/2019 | | 4/17/2019 | | PASS |
Morgan Webb
|
|
|
|
Routing - Erosion and Sediment | 4/16/2019 | | 4/17/2019 | | PASS |
Michael Zawacki
|
|
|
Foothills lot, site prep inspection required.
|
Application received | | | 4/16/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Apr 16 2019 9:14AM
|
Plan assigned to (BJM) | 4/16/2019 | 4/16/2019 | 4/16/2019 | | DEFR |
Brian McGowan
|
|
|
05/03 sfd L2 ePlan
|
Plans ACCEPTED BY PLAN TECH | | | 4/16/2019 | | DONE |
|
|
|
|
Intake Approval | | | 4/16/2019 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 4/16/2019 | | DONE |
|
|
|
|