BLD-Energy code compliance | 7/19/2019 | 7/19/2019 | 7/19/2019 | P | PASS |
Tell Riley
|
|
|
Mike Phone #: ###-####
|
BLD-Framing/Rough-in | 7/16/2019 | 7/16/2019 | 7/16/2019 | P | PASS |
Tell Riley
|
|
|
Mike Phone #: ###-####//corrections made//ok to insulate only
|
BLD-Wall Bracing | 7/16/2019 | 7/16/2019 | 7/16/2019 | A | PASS |
Tell Riley
|
|
|
corrections made//
|
BLD-Framing/Rough-in | 7/15/2019 | 7/16/2019 | 7/16/2019 | A | PART |
Tell Riley
|
|
|
mIKE Phone #: ###-####//add stud at west wall next to cut stud// add straps to portal frame per engineering//ok to insulate//
|
BLD-Wall Bracing | 7/8/2019 | 7/9/2019 | 7/9/2019 | P | FAIL |
Tell Riley
|
|
|
Mike Phone #: ###-####//correction notice//add staples per plans//add hardware per plans//add anchor bolt at plate end//add nuts to hold downs//call for re-inspection//
|
BLD-Footing | 4/23/2019 | 4/24/2019 | 4/24/2019 | A | PASS |
Jim Sly
|
|
|
John Phone #: ###-####
|
OVERRIDE | | | 4/16/2019 | | |
|
|
|
|
OVERRIDE | | | 4/16/2019 | | |
|
|
|
|
Routing Walk-In (Zoning) | 4/16/2019 | 4/16/2019 | 4/16/2019 | P | PASS |
Ethan Mansfield
|
|
|
|
Routing Walk-In (BLD) | 4/16/2019 | 4/16/2019 | 4/16/2019 | P | DONE |
Gemma Flores
|
|
|
|
Routing Walk-In (BLD) | 4/16/2019 | 4/16/2019 | 4/16/2019 | P | DONE |
Josh Bogle
|
|
|
|
Routing - PLAN CHECK | 4/16/2019 | | 4/16/2019 | | PASS |
Josh Bogle
|
|
|
|
1st review completed | | | 4/16/2019 | | DONE |
Josh Bogle
|
|
|
|
Inspection Record Card- Bld | | | 4/16/2019 | | DONE |
Josh Bogle
|
|
|
|
Case Summary (BLD) | | | 4/16/2019 | | DONE |
Josh Bogle
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/16/2019 | | DONE |
Josh Bogle
|
|
|
|
Permit Ready to Issue | | | 4/16/2019 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 4/16/2019 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 4/16/2019 | | DONE |
|
|
|
|
Application received | | 4/16/2019 | | | |
|
|
|
|