BLD-Final | 6/17/2019 | 6/18/2019 | 6/18/2019 | A | PASS |
Brandon Shaw
|
|
|
Please call 30 min ahead so I can meet onsite for access Phone #: ###-#### Inspection requested via web by Mike Leonard
|
DOC - Permit Finaled | 6/18/2019 | 6/18/2019 | 6/18/2019 | P | PASS |
Brandon Shaw
|
|
|
|
Issue PAID IN FULL permit | | | 6/12/2019 | | DONE |
|
|
|
|
Plan assigned to (JAB) Josh | 4/17/2019 | 4/17/2019 | 5/28/2019 | | PASS |
Josh Bogle
|
|
|
4/23 PV, ePlan - 1st done
|
Routing - PLAN CHECK | 5/28/2019 | | 5/28/2019 | | PASS |
Josh Bogle
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/28/2019 | | DONE |
Josh Bogle
|
|
|
ESC no - Energy no
|
Permit Ready to Issue | | | 5/28/2019 | | DONE |
|
|
|
|
Routing - PLANNING | 5/26/2019 | | 5/26/2019 | | PASS |
Katelyn Menuge
|
|
|
DRH19-00179
|
1st review completed | | | 4/18/2019 | | FAIL |
Josh Bogle
|
|
|
|
Routing - PLAN CHECK | 4/17/2019 | | 4/18/2019 | | FAIL |
Josh Bogle
|
|
|
no Plan Review pending Planning approval
|
Routing - PLANNING | 4/17/2019 | | 4/17/2019 | | FAIL |
Katelyn Menuge
|
|
|
New panels require submittal of a new Certificate of Appropriateness application prior to building permit approval.
|
Intake Approval | | | 4/17/2019 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 4/17/2019 | | DONE |
|
|
|
no fees paid at intake
|
Application received | | | 4/16/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Apr 16 2019 3:32PM
|
Intake Approval | | | 4/16/2019 | | FAIL |
|
|
|
Please show location of new solar panels
|