Second Notice | | 11/4/2019 | 11/4/2019 | | DONE |
|
|
|
This permit finaled on the web by Jackie Phelps
|
First Notice | 10/21/2019 | 10/21/2019 | 10/25/2019 | | DONE |
Mike Jordan
|
|
|
mailed 11-1-19
|
BLD-Final | 10/18/2019 | 10/21/2019 | 10/21/2019 | A | PASS |
Mike Jordan
|
|
|
Can we please final our life fire safety now that the FA permit FIR19-00585 is finaled (revised drawings approved). Thank you. Phone #: ###-#### Inspection requested via web by Jackie Phelps
|
DOC - Permit Finaled | 10/21/2019 | 10/21/2019 | 10/21/2019 | P | PASS |
Mike Jordan
|
|
|
|
FIRE-Final Inspection | 10/18/2019 | 10/21/2019 | 10/21/2019 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed. Thank you. Phone #: ###-#### Inspection requested via web by Jackie Phelps
|
FIRE-Final Inspection | 10/11/2019 | 10/15/2019 | 10/15/2019 | A | PART |
Troy Cobbley
|
|
|
A temp for life safety is being given until the as-builts/plan mods are approved.
Thank you. Phone #: ###-#### Inspection requested via web by Jackie Phelps
|
FIRE-Alarm Testing | 10/11/2019 | 10/15/2019 | 10/15/2019 | A | DONE |
Troy Cobbley
|
|
|
See the project related fire alarm permit for specifics for the fire alarm testing.
|
BLD-Final | 10/11/2019 | 10/15/2019 | 10/15/2019 | A | PART |
Mike Jordan
|
|
|
Fire Alarm / Final inspections scheduled for 7 am Tuesday. Please come afterward. Thank you. Phone #: ###-#### Inspection requested via web by Jackie Phelps. OK for temp occ. Will be ok for perm occ. once fire signs perm.
|
BLD-Final | 10/11/2019 | 10/16/2019 | 10/11/2019 | A | CANC |
Mike Jordan
|
|
|
Fire Alarm / Fire Final inspection scheduled for 7 AM Tuesday. Please come afterward. Thank you. Phone #: ###-#### >> Inspection requested via web by Jackie Phelps Inspection cancelled from web by: Jackie Phelps
|
FIRE-Final Inspection | 10/11/2019 | 10/16/2019 | 10/11/2019 | A | CANC |
Troy Cobbley
|
|
|
Please come first thing (7 am) so we can get done before school starts. We cant sound alarm when school in session. Thank you. Phone #: ###-#### >> Inspection requested via web by Jackie Phelps Inspection cancelled from web by: Jackie Phelps
|
FIRE-Alarm Testing | 10/11/2019 | 10/14/2019 | 10/11/2019 | A | CANC |
Troy Cobbley
|
|
|
Preferably before school opens if plan review is completed. Phone #: ###-#### >> Inspection requested via web by Jimmie Miller Inspection cancelled from web by: Jackie Phelps
|
BLD-Final | 10/11/2019 | 10/14/2019 | 10/11/2019 | P | CANC |
Mike Jordan
|
|
|
Preferably before school opens if plan review is completed. Phone #: ###-#### >> Inspection requested via web by Jimmie Miller Inspection cancelled from web by: Jackie Phelps
|
FIRE-Final Inspection | 10/11/2019 | 10/14/2019 | 10/11/2019 | A | CANC |
Troy Cobbley
|
|
|
Preferably before school opens if plan review is completed. Phone #: ###-#### >> Inspection requested via web by Jimmie Miller Inspection cancelled from web by: Jackie Phelps
|
BLD-Final | 10/10/2019 | 10/11/2019 | 10/11/2019 | P | CANC |
Brandon Shaw
|
|
|
Preferably right after final life safety. Phone #: ###-#### Inspection requested via web by Jimmie Miller
|
FIRE-Final Inspection | 10/10/2019 | 10/11/2019 | 10/11/2019 | A | NR |
Troy Cobbley
|
|
|
No ready for life safety due to fire alarm resubmittal. Phone #: ###-#### Inspection requested via web by Jimmie Miller
|
CHANGE STATUS TO (ISS) | | | 10/8/2019 | | DONE |
|
|
|
plan mod
|
Plan assigned to (JAR) | 9/16/2019 | 9/16/2019 | 10/7/2019 | | DONE |
Julie Romig
|
|
|
1st Rev Comp - Plan Mod Bishop Kelly HS Kitchen
|
Permit Ready to Issue | | | 10/7/2019 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 10/7/2019 | | 10/7/2019 | | PASS |
Julie Romig
|
|
|
Accessible upgrades will be completed under future permit. Upgrades will include remodel of the single user restroom in Phase II, to be completed by 10/20/2020. See attached letter. *JAR*
|
Routing - PLAN CHECK | 9/17/2019 | | 10/1/2019 | | FAIL |
Julie Romig
|
|
|
Need Accessibility upgrade information
|
Routing - MECHANICAL | 9/17/2019 | | 9/20/2019 | | PASS |
Troy James
|
|
|
|
Routing - PLUMBING | 9/17/2019 | | 9/19/2019 | | PASS |
Daryl Spivey
|
|
|
May require RPBP on steamer.
|
Routing - PUBLIC WORKS | 9/17/2019 | | 9/18/2019 | | PASS |
Morgan Webb
|
|
|
NO CHANGE TO FEES
|
Plan Modification Accepted | | | 9/16/2019 | | DONE |
|
|
|
Alternate #1 that was in the original permit set will no longer be a part of the project and has been removed fromthe drawings. This scope of work includes revising the dry storage area, remodeling the existing single user restroom, replacing the dishwasher and replacing the walk-in freezer and refridgerator. Sheets: A0.01, A2.01, A2.11, A2.21, A2.31, A2.41, A3.22, A6.11, M1.11, M1.12, M2.12, M3.11, P1.10, P1.11, P2.11, E2.0D, E2.0MP, E2.0P, E2.0R, E3.2
|
BLD-Framing/Rough-in | 9/10/2019 | 9/11/2019 | 9/11/2019 | A | PASS |
Tell Riley
|
|
|
jimmie//SSC clips installed per RFI 027 for connection of box header//correction made per Mikes notes//
|
BLD-Framing/Rough-in | 9/5/2019 | 9/6/2019 | 9/6/2019 | A | PART |
Mike Jordan
|
|
|
Early as possible please. Phone #: ###-#### Inspection requested via web by Jimmie Miller. Steel stud framing and box headers for new openings. Needs to install SSC clips from bottom track to each stud. Contractor to fllow up with RFI approving the angle clips in leiu of HUC hangars for box header to jamb conections.
|
BLD-Framing/Rough-in | 9/5/2019 | 9/5/2019 | 9/5/2019 | P | NR |
Jim Storey
|
|
|
Jimmy Phone #: ###-#### no one on site.
|
BLD-Wall cover | 8/22/2019 | 8/22/2019 | 8/22/2019 | P | CANC |
Mike Jordan
|
|
|
Ross is on site contact through 8/27. ###-####. We are scheduled to sheetrock the ceiling tomorrow, insulation has been removed and replaced with new. RFI mentioned in early inspection comment has been sent. Please confirm If we need a re-inspection prior to cover. Thank you! Jackie Phelps ###-#### Phone #: ###-#### >> Inspection requested via web by Jackie Phelps Inspection cancelled from web by: Jackie Phelps
|
BLD-Framing/Rough-in | 8/16/2019 | 8/16/2019 | 8/16/2019 | P | PASS |
Mike Jordan
|
|
|
Jimmy Phone #: ###-####. Interior steel stud furred walls for equipment chases. Also reviewed RFI for use of A35's.
|
BLD-Framing/Rough-in | 8/5/2019 | 8/5/2019 | 8/5/2019 | P | PART |
Mike Jordan
|
|
|
Jimmie Phone #: ###-####. Additional 2x12 joist sistering to support new mech. equpment in kitchen. Need RFI for alternate attacment of A35 in lieu of the 2 inch bearing.
|
(F) Reprint permit | | | 6/7/2019 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 6/7/2019 | | DONE |
|
|
|
|
Telephone call | | | 6/6/2019 | | DONE |
|
|
|
Emailed permit to signed to GC, davidm@cmcompany.com
|
Issue PAID IN FULL permit | | | 6/6/2019 | | DONE |
|
|
|
Emailed permit to signed
|
Inspection Record Card- Bld | | | 6/6/2019 | | DONE |
|
|
|
|
Plan assigned to (JAR) | 4/29/2019 | 4/29/2019 | 6/3/2019 | | DONE |
Julie Romig
|
|
|
06/04 - 2nd Rev - 1st Rev Comp - L3 Bishop Kelly Kitchen Remodel
|
Routing - PLAN CHECK | 5/28/2019 | | 6/3/2019 | | PASS |
Julie Romig
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/3/2019 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 6/3/2019 | | DONE |
|
|
|
MET (KKULM@ERSTADARCHITECTS.COM)
NOT PART OF BOISE SCHOOL DISTRICT; NO "CREDIT"
Need GC
Need rev cert of val
|
Route to Impact Fee Review | 5/23/2019 | 5/26/2019 | 5/23/2019 | | PASS |
Shannon Cade
|
|
|
Review requested for Commercial Permit
|
1st review completed | | | 5/23/2019 | | DONE |
Julie Romig
|
|
|
|
Routing - FIRE | 4/29/2019 | 4/29/2019 | 5/22/2019 | | PASS |
Mark Scharfen
|
|
|
Completed review and uploaded rev_fire 05.22.2019.pdf. Passed review.
|
Routing - PLAN CHECK | 4/29/2019 | | 5/22/2019 | | FAIL |
Julie Romig
|
|
|
Refer to ePlanReview for required corrections
|
Routing PW Environmental | 4/29/2019 | | 5/16/2019 | | PASS |
Rick Christenson
|
|
|
|
Routing - MECHANICAL | 4/29/2019 | | 5/6/2019 | | PASS |
Troy James
|
|
|
|
Routing - PLUMBING | 4/29/2019 | | 4/30/2019 | | PASS |
Daryl Spivey
|
|
|
Per plan and ISPC.
|
Routing Off Site - STRUCTURAL | 4/29/2019 | | 4/30/2019 | | PASS |
Julie Romig
|
|
|
|
Routing - PUBLIC WORKS | 4/29/2019 | | 4/30/2019 | | PASS |
Morgan Webb
|
|
|
WEST BOISE SEWER DISTRICT
|
Plan assigned to (JHB) | 4/29/2019 | 4/29/2019 | 4/29/2019 | | DEFR |
Joe Bruce
|
|
|
05/22 - Bishop Kelly Cafeteria L-3
|
Routing - Addressing | 4/29/2019 | | 4/29/2019 | | PASS |
Laura Hunter
|
|
|
|
Intake Approval | | | 4/25/2019 | | FAIL |
Julie Romig
|
|
|
Need: 1. Architectural sheets are missing architect's stamp/signature. Please upload stamped/signed sheets.
2. The lower right corner of all drawings are to have a blank 4"x2" space located 3" off the right sheet edge for the city's stamp. Please upload all electrical sheets with this area left blank.
3. Mechanical COMcheck and heating & cooling load calcs are indicated on checklist, but were not found. Please upload Mechanical COMcheck and heating & cooling load calcs.
|
Plan Reviewer's activity | | | 4/25/2019 | | DONE |
Julie Romig
|
|
|
School Prescreen approved 4/25/19
|
Intake Approval | | | 4/25/2019 | | PASS |
|
|
|
|
Application received | | | 4/17/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Apr 17 2019 9:29AM
|
Agreement of Future work | 10/7/2019 | 10/2/2020 | | | |
|
|
|
(BISHOP KELLEY HS) 20% Accessible Upgrade will be completed under future permit (Phase II). Upgrades will be to remodel the single user restroom for full accessibility. Work to be completed by 10/2/2020. See attached letter.
|