Information based on query as of Wednesday, July 24, 2024.
Permit Information
Permit NumberBLD19-01275
StatusFinaled
Name PHOENIX COMMERCIAL CONSTRUCTION LLC
Site Address 2273 S VISTA AVE Unit: STE 110
Project NameIdaho Perio Vista TI
Customer Number 
ePlanReviewYes
Description
(IDAHO PERIO) **PLAN MODIFICATION 1-14-19**, Reconfigured routing of gas line from the original design route to the updated routing design in the field. (1 - sheet, P1.1) Fire sprinklers used for building are increase and for fire area. Permit for tenant improvements to an existing 2,297 sq. ft. tenant space. Work is to include 2 restrooms accessible to the disabled, interior nonbearing walls, interior doors, electrical work, plumbing work, mechanical work, and interior finishes in compliance with Ch. 8 of the current IBC. The work is required to comply with the approved drawings, with the plan review report, and with all applicable codes and ordinances. The fire sprinkler system is required to comply with NFPA 13 as regulated by the Fire Department. **JHB** Tenant will be utilizing a med gas cart with 1 E size tank of N2O and 1 stored for medical procedures. Amount of gas under permitted use, so med gas room is not needed. MS
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Second Notice 3/15/20203/16/2020 DONE
This permit finaled on the web by Roy Moore
First Notice 2/8/20203/5/2020 DONE
mailed 3-6-20
BLD-Final1/27/20201/29/20201/29/2020APASS
DetailsJim Storey
Call prior to arrival, needing to conduct with Fire Final Phone #: ###-#### Inspection requested via web by Roy Moore final ok no card on site.
FIRE-Final Inspection1/27/20201/29/20201/29/2020APASS
DetailsTroy Cobbley
Life safety passed. Contractor to remove the non-functional door mags at the main exit as discussed.

Call prior to arrival, needing to conduct with Fire Final Phone #: ###-#### Inspection requested via web by Roy Moore
Print Occupancy Form  1/29/2020 DONE
Permanent Occupancy  1/29/2020 DONE
CHANGE STATUS TO (ISS)  1/15/2020 DONE
plan mod back to ISS
Plan assigned to (Joe)1/3/20201/3/20201/14/2020 PASS
DetailsJoe Bruce
(plan mod)
Permit Ready to Issue  1/14/2020 DONE
Plan mod Approved
Routing - PLUMBING1/8/2020 1/13/2020 PASS
DetailsDan Ediger
Per plans and ISPC
Routing - MECHANICAL1/8/2020 1/10/2020 PASS
DetailsTroy James
Plan Modification Accepted  1/3/2020 DONE
reconfigured routing of gas line from the originally design route to the updated routing design
Print Occupancy Form  12/31/2019 DONE
emailed to tenant at idahoperio@gmail.com per their request
BLD-Ceiling Grid Inspection11/18/201911/18/201911/18/2019PPASS
DetailsJim Storey
Jim please re-inspect this afternoon. Inspection requested via web by Roy Moore
BLD-Ceiling Grid Inspection11/18/201911/18/201911/18/2019AFAIL
DetailsJim Storey
Please call prior to arrival to ensure access. Roy.
thank you
Phone #: ###-#### Inspection requested via web by Roy Moore need wire max 8 inches end of mains
BLD-Framing/Rough-in10/2/201910/3/201910/3/2019APASS
DetailsJim Storey
Please call prior to arrival. If possible to have inspection before 10am. Please ask inspector to call to confirm time for access. Phone #: ###-#### Inspection requested via web by Roy Moore
Issue PAID IN FULL permit  7/31/2019 DONE
Print Occupancy Form  7/31/2019 DONE
Plan assigned to (JHB)4/29/20194/29/20197/1/2019 PASS
DetailsJoe Bruce
07/01 (2nd Rev) 05/23 (L3) Idaho Perio Center, ePlan
Routing - PLAN CHECK6/26/2019 7/1/2019 PASS
DetailsJoe Bruce
PLANS/APPL TAKEN TO FRONT DESK  7/1/2019 DONE
Permit Ready to Issue  7/1/2019 DONE
Need GC
Need Rev Val
Routing - MECHANICAL6/26/2019 6/26/2019 PASS
DetailsTroy James
Plan resubmittals received  6/26/2019 DONE
DetailsJoe Bruce
Route to Impact Fee Review5/23/20195/26/20195/23/2019 PASS
DetailsShannon Cade
Review requested for Commercial Permit
1st review completed  5/23/2019 FAIL
DetailsJoe Bruce
Plan resubmittals requested  5/23/2019 DONE
DetailsJoe Bruce
emailed plan review report to architect.
Routing - PLAN CHECK4/29/2019 5/23/2019 FAIL
DetailsJoe Bruce
Routing - FIRE5/22/20195/22/20195/22/2019 PASS
DetailsMark Scharfen
Completed fire review. Uploaded rev_fire 05.22.2019.pdf. Passed.
Routing - PLANNING5/2/2019 5/2/2019 PASS
DetailsNicolette Womack
Exterior Modifications require DR.
Routing - MECHANICAL4/29/2019 4/30/2019 FAIL
DetailsTroy James
See eplan
Routing - PLUMBING4/29/2019 4/30/2019 PASS
DetailsDaryl Spivey
Per plan and ISPC
Routing - Addressing4/29/2019 4/30/2019 PASS
DetailsDoug Chausow
Ste 110
Routing PW Environmental4/30/2019 4/30/2019 PASS
DetailsTerry Alber
Installation of City approved amalgam separator meeting ISO11143 certification is required at all dental care facilities where any amalgam is placed or removed. All dental care facilities subject to pretreatment program best management practice requirements for proper management of generated wastes. Please call ###-#### for list of approved separators, Dental BMPs and an application for coverage under the City Dental BMP program.
Routing - PUBLIC WORKS4/30/2019 4/30/2019 PASS
DetailsMorgan Webb
Intake Approval  4/26/2019 PASS
Intake Approval  4/22/2019 FAIL
DetailsJavier Guzman
Provide and upload the following:
• Per ePlan submittal standards provide on the bottom right corner for City electronic stamps a blank 4” x 2” space located 3” off the right sheet edge to allow for the title block on all electrical plan sheets
Application received  4/19/2019 DONE
Application submitted via PDS Online on Apr 19 2019 9:07AM