Information based on query as of Tuesday, July 23, 2024.
Permit Information
Permit NumberBLD19-01282
StatusFinaled
Name KINCAID CONSTRUCTION LLC
Site Address 1840 N MOCKBEE PL
Project NameMockbee House - 1840 N. Mockbe
Customer Number 
ePlanReviewYes
Description
**PLAN MODIFICATION - changes to site drainage per hillside requirements JJN 11/4/19** **HILLSIDE** **WUI FOOTHILLS ZONE A** **PRESCRIPTIVE ENERGY REQUIREMENTS** Permit for the construction of a new 3588 sq. ft., two story (first story 1856 sq. ft., second story 1300 sq. ft., basement 432 sq. ft.) single family dwelling with 3 bedrooms, 3.5 bathrooms, approximately and a 590 sq. ft. attached garage per the approved plans and any notations. R-1B zoning and setbacks per planning. JJN SPRINKLERS ARE REQUIRED AND BEING PROVIDED, AS NOTED ON THE COVER SHEET / SITE PLAN. LGMA letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Please e-mail the stamped inspection approval letter to mjannusch@cityofboise.org and allow 24 hours for subgrade approval processing. Call Melissa Jannusch at 208-608-7168 with questions.

Prior to obtaining a final for the permit, the roof storm drainage system must be inspected by Public Works. Call Melissa Jannusch at 208-608-7168.

The final inspection of the site grading and drainage work shall be done by the design engineer. Written approval shall be submitted to Boise Public Works prior to the issuance of the building final.

An erosion and sediment control site preparation inspection is required for this site. The site preparation inspection takes place after all required erosion and sediment control best management practices have been installed and BEFORE any earthwork takes place. Call 208-608-7070 to schedule an inspection.



All disturbed slopes included in the construction of this project must be stabilized and approved by Public Works before a Final Occupancy Permit is granted. If weather conditions prohibit revegetation and stabilization activities, the contractor shall provide a bond/surety agreement or an irrevocable letter of credit in the amount of 110% of the cost estimated by the project engineer to enable stabilization of the site. Call 208-608-7168 for an inspection.

Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final4/20/20204/20/20204/20/2020PPASS
DetailsBrandon Shaw
HVAC is now completed and signed off Phone #: ###-#### Inspection requested via web by Larry Kincaid
DOC - Permit Finaled4/20/20204/20/20204/20/2020PPASS
DetailsBrandon Shaw
PubWorks Occupancy Approval4/6/20204/6/20204/6/2020 DONE
DetailsMelissa Jannusch
A bond for the sites final grading and re-vegetation has been received by Public Works. Occupancy may be approved by the building department. Melissa Jannusch ###-####.

BLD-Final4/1/20204/2/20204/2/2020PPART
DetailsBrandon Shaw
Temp C of O ia approved for 30 days ending 4Mar20...
Needs MEC19-04186 final, no other issues...
BLD-Final4/1/20204/2/20204/2/2020ACANC
DetailsBrandon Shaw
I did a pre-conference walk through with Tell Riley for this project and we are now ready for the final. He might be best to do the final since we already went through all the items. Please call prior to coming to the site so I can make sure and be their. Thanks, Phone #: ###-#### Inspection requested via web by Larry Kincaid
Telephone call  3/30/2020 DONE
Emailed Larry Kincaid the Bond Agreement per Melissa for notarized signature.
BLD-Conference3/24/20203/24/20203/24/2020PDONE
DetailsTell Riley
I would like to schedule a conference or job site meeting to discuss all items we will need to get the project final inspection Phone #: ###-#### Inspection requested via web by Larry Kincaid
BLD-Foundation1/13/20201/13/20201/13/2020PPASS
DetailsBrandon Shaw
Work in progress...
Frost protection is reqired...
BLD-Footing1/8/20201/9/20201/9/2020APASS
DetailsBrandon Shaw
Need rebar inspection for retaining wall footers
Thanks, Inspection requested via web by Larry Kincaid
BLD-Foundation12/23/201912/26/201912/26/2019PPASS
DetailsBrandon Shaw
Work in progress...
BLD-Footing12/18/201912/19/201912/19/2019APASS
DetailsBrandon Shaw
need footing rebar inspection at retaining wall Inspection requested via web by Larry Kincaid
BLD-Energy code compliance11/22/201911/22/201911/22/2019PPASS
DetailsBrandon Shaw
OK to cover...
BLD-Wall cover11/22/201911/22/201911/22/2019PCANC
DetailsBrandon Shaw
Inspection requested via web by Larry Kincaid
BLD-Framing/Rough-in11/18/201911/19/201911/19/2019APASS
DetailsBrandon Shaw
Inspection requested via web by Larry Kincaid
BLD-Energy code compliance11/18/201911/19/201911/19/2019APART
DetailsBrandon Shaw
Air/foam seal...
BLD-Foundation11/18/201911/18/201911/18/2019PPART
DetailsBrandon Shaw
Work in progress...
BLD-Framing/Rough-in11/18/201911/18/201911/18/2019PCANC
DetailsBrandon Shaw
>> Inspection requested via web by Larry Kincaid Inspection cancelled from web by: Larry Kincaid
BLD-Footing11/12/201911/13/201911/13/2019APASS
DetailsBrandon Shaw
rebar inspection for retaining wall footer

Thanks, Inspection requested via web by Larry Kincaid
CHANGE STATUS TO (ISS)  11/6/2019 DONE
OVERRIDE  11/4/2019  
Plan assigned to (J_N)10/21/201910/21/201911/4/2019 DONE
DetailsJenny Nelson
plan mod - grading, waiting for hillside to review, no structural changes so no building review required
Routing PW Grading-Hillside10/25/2019 11/4/2019 PASS
DetailsMelissa Jannusch
PLAN MOD:
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Please e-mail the stamped inspection approval letter to mjannusch@cityofboise.org and allow 24 hours for subgrade approval processing. Call Melissa Jannusch at ###-#### with questions.

Prior to obtaining a final for the permit, the roof storm drainage system must be inspected by Public Works. Call Melissa Jannusch at ###-####.

The final inspection of the site grading and drainage work shall be done by the design engineer. Written approval shall be submitted to Boise Public Works prior to the issuance of the building final.

Permit Ready to Issue  11/4/2019 DONE
plan mod approved
Routing - PLAN CHECK10/25/2019 10/25/2019 PASS
DetailsJenny Nelson
1 hour fee - no structural changes
BLD-Concrete10/24/201910/24/201910/24/2019PPASS
DetailsBrandon Shaw
Work in progress...
West wall...
Plan Modification Accepted  10/21/2019 DONE
Plan mod requested per Cathy Sewell, Architect for update requested by Melissa to grading plan. Sheet G1.0.
BLD-Framing/Rough-in10/7/201910/8/201910/8/2019APART
DetailsBrandon Shaw
Need to schedule an inspection for the roof underside so we can do a spray foam insulation before we install fire sprinkler lines.
BLD-Footing9/26/20199/27/20199/27/2019APASS
DetailsBrandon Shaw
Work in progress...
BLD-Wall Bracing9/20/20199/23/20199/23/2019APART
DetailsBrandon Shaw
Exterior only...
Interior shear and hold downs to be completed before framing rough-in...
BLD-Foundation7/23/20197/24/20197/24/2019APASS
DetailsDave Hannah
Inspection requested via web by Larry Kincaid
BLD-Footing7/17/20197/18/20197/18/2019APASS
DetailsBrandon Shaw
need rebar inspection for footings. Concrete pump and concrete delivery is scheduled for 11:00am. Thursday thanks
Phone #: ###-#### Inspection requested via web by Larry Kincaid
PubWorks Subgrade Approval7/18/20197/18/20197/18/2019 DONE
DetailsMelissa Jannusch
Perimeter footings A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Melissa Jannusch ###-####.

BLD-Foundation6/26/20196/26/20196/26/2019PPART
DetailsTony Young
rebar inspection for basement walls Phone #: ###-#### Inspection requested via web by Larry Kincaid// work in progress on the basement walls,, ok
BLD-Footing6/14/20196/14/20196/14/2019PPART
DetailsTony Young
Jerry Phone #: ###-####,, basement footing ok
BLD-Footing6/13/20196/14/20196/14/2019APART
DetailsTony Young
Jerry Phone #: ###-####,, basement footing
PubWorks Subgrade Approval6/14/20196/14/20196/14/2019 DONE
DetailsMelissa Jannusch
BASEMENT FOOTINGS A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Melissa Jannusch ###-####.
Issue PAID IN FULL permit  5/17/2019 DONE
Inspection Record Card- Bld  5/17/2019 DONE
OVERRIDE  5/14/2019  
Plan assigned to (J_N)4/24/20194/24/20195/14/2019 DONE
Details
05/13 sfd L2 ePlan. 1st complete, waiting for hillside.
1st review completed  5/14/2019 DONE
DetailsJenny Nelson
PLANS/APPL TAKEN TO FRONT DESK  5/14/2019 DONE
DetailsJenny Nelson
Permit Ready to Issue  5/14/2019 DONE
met- emailed permits to larry@kincaidc.com
Routing PW Grading-Hillside4/24/2019 5/9/2019 PASS
DetailsMelissa Jannusch
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Please e-mail the stamped inspection approval letter to mjannusch@cityofboise.org and allow 24 hours for subgrade approval processing. Call Melissa Jannusch at ###-#### with questions.

Prior to obtaining a final for the permit, the roof storm drainage system must be inspected by Public Works. Call Melissa Jannusch at ###-####.

The final inspection of the site grading and drainage work shall be done by the design engineer. Written approval shall be submitted to Boise Public Works prior to the issuance of the building final.

An erosion and sediment control site preparation inspection is required for this site. The site preparation inspection takes place after all required erosion and sediment control best management practices have been installed and BEFORE any earthwork takes place. Call ###-#### to schedule an inspection.



All disturbed slopes included in the construction of this project must be stabilized and approved by Public Works before a Final Occupancy Permit is granted. If weather conditions prohibit revegetation and stabilization activities, the contractor shall provide a bond/surety agreement or an irrevocable letter of credit in the amount of 110% of the cost estimated by the project engineer to enable stabilization of the site. Call ###-#### for an inspection.

Routing - PLAN CHECK4/24/2019 4/30/2019 PASS
DetailsJenny Nelson
Routing - FIRE4/24/20194/24/20194/26/2019 PASS
DetailsLee G Meredith
05/06 1840 N Mockbee Pl 402 Residential Fire Review

Fire sprinklers are being provided, as noted on the Cover Sheet / Site Plan drawing.
Routing - PLANNING4/24/2019 4/26/2019 PASS
DetailsJeff Lowe
do not issue until PW signs off
Route to Impact Fee Review4/24/20194/27/20194/25/2019 PASS
DetailsShannon Cade
Initial residential review of new SFD permits requested for now.
Routing - MECHANICAL4/24/2019 4/25/2019 PASS
DetailsTroy James
Routing - Addressing4/24/2019 4/24/2019 PASS
DetailsDoug Chausow
Routing - PUBLIC WORKS4/24/2019 4/24/2019 PASS
DetailsAngela Hardy
Routing - Erosion and Sediment4/24/2019 4/24/2019 PASS
DetailsMichael Zawacki
Site prep inspection required.
Intake Approval  4/24/2019 PASS
Recd Pcfee & Taken To Pln CK  4/24/2019 DONE
Intake Approval  4/22/2019 FAIL
Please upload the geotechnical addendum dated 3-29-2019 prior to acceptance of the building permit for review. --MMJ ###-####
Application received  4/19/2019 DONE
Application submitted via PDS Online on Apr 19 2019 12:52PM