BLD-Final | 4/20/2020 | 4/20/2020 | 4/20/2020 | P | PASS |
Brandon Shaw
|
|
|
HVAC is now completed and signed off Phone #: ###-#### Inspection requested via web by Larry Kincaid
|
DOC - Permit Finaled | 4/20/2020 | 4/20/2020 | 4/20/2020 | P | PASS |
Brandon Shaw
|
|
|
|
PubWorks Occupancy Approval | 4/6/2020 | 4/6/2020 | 4/6/2020 | | DONE |
Melissa Jannusch
|
|
|
A bond for the sites final grading and re-vegetation has been received by Public Works. Occupancy may be approved by the building department. Melissa Jannusch ###-####.
|
BLD-Final | 4/1/2020 | 4/2/2020 | 4/2/2020 | P | PART |
Brandon Shaw
|
|
|
Temp C of O ia approved for 30 days ending 4Mar20... Needs MEC19-04186 final, no other issues...
|
BLD-Final | 4/1/2020 | 4/2/2020 | 4/2/2020 | A | CANC |
Brandon Shaw
|
|
|
I did a pre-conference walk through with Tell Riley for this project and we are now ready for the final. He might be best to do the final since we already went through all the items. Please call prior to coming to the site so I can make sure and be their. Thanks, Phone #: ###-#### Inspection requested via web by Larry Kincaid
|
Telephone call | | | 3/30/2020 | | DONE |
|
|
|
Emailed Larry Kincaid the Bond Agreement per Melissa for notarized signature.
|
BLD-Conference | 3/24/2020 | 3/24/2020 | 3/24/2020 | P | DONE |
Tell Riley
|
|
|
I would like to schedule a conference or job site meeting to discuss all items we will need to get the project final inspection Phone #: ###-#### Inspection requested via web by Larry Kincaid
|
BLD-Foundation | 1/13/2020 | 1/13/2020 | 1/13/2020 | P | PASS |
Brandon Shaw
|
|
|
Work in progress... Frost protection is reqired...
|
BLD-Footing | 1/8/2020 | 1/9/2020 | 1/9/2020 | A | PASS |
Brandon Shaw
|
|
|
Need rebar inspection for retaining wall footers Thanks, Inspection requested via web by Larry Kincaid
|
BLD-Foundation | 12/23/2019 | 12/26/2019 | 12/26/2019 | P | PASS |
Brandon Shaw
|
|
|
Work in progress...
|
BLD-Footing | 12/18/2019 | 12/19/2019 | 12/19/2019 | A | PASS |
Brandon Shaw
|
|
|
need footing rebar inspection at retaining wall Inspection requested via web by Larry Kincaid
|
BLD-Energy code compliance | 11/22/2019 | 11/22/2019 | 11/22/2019 | P | PASS |
Brandon Shaw
|
|
|
OK to cover...
|
BLD-Wall cover | 11/22/2019 | 11/22/2019 | 11/22/2019 | P | CANC |
Brandon Shaw
|
|
|
Inspection requested via web by Larry Kincaid
|
BLD-Framing/Rough-in | 11/18/2019 | 11/19/2019 | 11/19/2019 | A | PASS |
Brandon Shaw
|
|
|
Inspection requested via web by Larry Kincaid
|
BLD-Energy code compliance | 11/18/2019 | 11/19/2019 | 11/19/2019 | A | PART |
Brandon Shaw
|
|
|
Air/foam seal...
|
BLD-Foundation | 11/18/2019 | 11/18/2019 | 11/18/2019 | P | PART |
Brandon Shaw
|
|
|
Work in progress...
|
BLD-Framing/Rough-in | 11/18/2019 | 11/18/2019 | 11/18/2019 | P | CANC |
Brandon Shaw
|
|
|
>> Inspection requested via web by Larry Kincaid Inspection cancelled from web by: Larry Kincaid
|
BLD-Footing | 11/12/2019 | 11/13/2019 | 11/13/2019 | A | PASS |
Brandon Shaw
|
|
|
rebar inspection for retaining wall footer
Thanks, Inspection requested via web by Larry Kincaid
|
CHANGE STATUS TO (ISS) | | | 11/6/2019 | | DONE |
|
|
|
|
OVERRIDE | | | 11/4/2019 | | |
|
|
|
|
Plan assigned to (J_N) | 10/21/2019 | 10/21/2019 | 11/4/2019 | | DONE |
Jenny Nelson
|
|
|
plan mod - grading, waiting for hillside to review, no structural changes so no building review required
|
Routing PW Grading-Hillside | 10/25/2019 | | 11/4/2019 | | PASS |
Melissa Jannusch
|
|
|
PLAN MOD:
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Please e-mail the stamped inspection approval letter to mjannusch@cityofboise.org and allow 24 hours for subgrade approval processing. Call Melissa Jannusch at ###-#### with questions.
Prior to obtaining a final for the permit, the roof storm drainage system must be inspected by Public Works. Call Melissa Jannusch at ###-####.
The final inspection of the site grading and drainage work shall be done by the design engineer. Written approval shall be submitted to Boise Public Works prior to the issuance of the building final.
|
Permit Ready to Issue | | | 11/4/2019 | | DONE |
|
|
|
plan mod approved
|
Routing - PLAN CHECK | 10/25/2019 | | 10/25/2019 | | PASS |
Jenny Nelson
|
|
|
1 hour fee - no structural changes
|
BLD-Concrete | 10/24/2019 | 10/24/2019 | 10/24/2019 | P | PASS |
Brandon Shaw
|
|
|
Work in progress... West wall...
|
Plan Modification Accepted | | | 10/21/2019 | | DONE |
|
|
|
Plan mod requested per Cathy Sewell, Architect for update requested by Melissa to grading plan. Sheet G1.0.
|
BLD-Framing/Rough-in | 10/7/2019 | 10/8/2019 | 10/8/2019 | A | PART |
Brandon Shaw
|
|
|
Need to schedule an inspection for the roof underside so we can do a spray foam insulation before we install fire sprinkler lines.
|
BLD-Footing | 9/26/2019 | 9/27/2019 | 9/27/2019 | A | PASS |
Brandon Shaw
|
|
|
Work in progress...
|
BLD-Wall Bracing | 9/20/2019 | 9/23/2019 | 9/23/2019 | A | PART |
Brandon Shaw
|
|
|
Exterior only... Interior shear and hold downs to be completed before framing rough-in...
|
BLD-Foundation | 7/23/2019 | 7/24/2019 | 7/24/2019 | A | PASS |
Dave Hannah
|
|
|
Inspection requested via web by Larry Kincaid
|
BLD-Footing | 7/17/2019 | 7/18/2019 | 7/18/2019 | A | PASS |
Brandon Shaw
|
|
|
need rebar inspection for footings. Concrete pump and concrete delivery is scheduled for 11:00am. Thursday thanks Phone #: ###-#### Inspection requested via web by Larry Kincaid
|
PubWorks Subgrade Approval | 7/18/2019 | 7/18/2019 | 7/18/2019 | | DONE |
Melissa Jannusch
|
|
|
Perimeter footings A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Melissa Jannusch ###-####.
|
BLD-Foundation | 6/26/2019 | 6/26/2019 | 6/26/2019 | P | PART |
Tony Young
|
|
|
rebar inspection for basement walls Phone #: ###-#### Inspection requested via web by Larry Kincaid// work in progress on the basement walls,, ok
|
BLD-Footing | 6/14/2019 | 6/14/2019 | 6/14/2019 | P | PART |
Tony Young
|
|
|
Jerry Phone #: ###-####,, basement footing ok
|
BLD-Footing | 6/13/2019 | 6/14/2019 | 6/14/2019 | A | PART |
Tony Young
|
|
|
Jerry Phone #: ###-####,, basement footing
|
PubWorks Subgrade Approval | 6/14/2019 | 6/14/2019 | 6/14/2019 | | DONE |
Melissa Jannusch
|
|
|
BASEMENT FOOTINGS A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Melissa Jannusch ###-####.
|
Issue PAID IN FULL permit | | | 5/17/2019 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 5/17/2019 | | DONE |
|
|
|
|
OVERRIDE | | | 5/14/2019 | | |
|
|
|
|
Plan assigned to (J_N) | 4/24/2019 | 4/24/2019 | 5/14/2019 | | DONE |
|
|
|
05/13 sfd L2 ePlan. 1st complete, waiting for hillside.
|
1st review completed | | | 5/14/2019 | | DONE |
Jenny Nelson
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/14/2019 | | DONE |
Jenny Nelson
|
|
|
|
Permit Ready to Issue | | | 5/14/2019 | | DONE |
|
|
|
met- emailed permits to larry@kincaidc.com
|
Routing PW Grading-Hillside | 4/24/2019 | | 5/9/2019 | | PASS |
Melissa Jannusch
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Please e-mail the stamped inspection approval letter to mjannusch@cityofboise.org and allow 24 hours for subgrade approval processing. Call Melissa Jannusch at ###-#### with questions.
Prior to obtaining a final for the permit, the roof storm drainage system must be inspected by Public Works. Call Melissa Jannusch at ###-####.
The final inspection of the site grading and drainage work shall be done by the design engineer. Written approval shall be submitted to Boise Public Works prior to the issuance of the building final.
An erosion and sediment control site preparation inspection is required for this site. The site preparation inspection takes place after all required erosion and sediment control best management practices have been installed and BEFORE any earthwork takes place. Call ###-#### to schedule an inspection.
All disturbed slopes included in the construction of this project must be stabilized and approved by Public Works before a Final Occupancy Permit is granted. If weather conditions prohibit revegetation and stabilization activities, the contractor shall provide a bond/surety agreement or an irrevocable letter of credit in the amount of 110% of the cost estimated by the project engineer to enable stabilization of the site. Call ###-#### for an inspection.
|
Routing - PLAN CHECK | 4/24/2019 | | 4/30/2019 | | PASS |
Jenny Nelson
|
|
|
|
Routing - FIRE | 4/24/2019 | 4/24/2019 | 4/26/2019 | | PASS |
Lee G Meredith
|
|
|
05/06 1840 N Mockbee Pl 402 Residential Fire Review
Fire sprinklers are being provided, as noted on the Cover Sheet / Site Plan drawing.
|
Routing - PLANNING | 4/24/2019 | | 4/26/2019 | | PASS |
Jeff Lowe
|
|
|
do not issue until PW signs off
|
Route to Impact Fee Review | 4/24/2019 | 4/27/2019 | 4/25/2019 | | PASS |
Shannon Cade
|
|
|
Initial residential review of new SFD permits requested for now.
|
Routing - MECHANICAL | 4/24/2019 | | 4/25/2019 | | PASS |
Troy James
|
|
|
|
Routing - Addressing | 4/24/2019 | | 4/24/2019 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 4/24/2019 | | 4/24/2019 | | PASS |
Angela Hardy
|
|
|
|
Routing - Erosion and Sediment | 4/24/2019 | | 4/24/2019 | | PASS |
Michael Zawacki
|
|
|
Site prep inspection required.
|
Intake Approval | | | 4/24/2019 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 4/24/2019 | | DONE |
|
|
|
|
Intake Approval | | | 4/22/2019 | | FAIL |
|
|
|
Please upload the geotechnical addendum dated 3-29-2019 prior to acceptance of the building permit for review. --MMJ ###-####
|
Application received | | | 4/19/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Apr 19 2019 12:52PM
|