BLD-Framing/Rough-in | 5/3/2019 | 5/6/2019 | 5/6/2019 | P | PASS |
Dave Hannah
|
|
|
Phone #: ###-#### Inspection requested via web by Justin Cruise
|
Issue PAID IN FULL permit | | | 5/3/2019 | | DONE |
|
|
|
|
Print Occupancy Form | | | 5/3/2019 | | DONE |
|
|
|
|
Route to Impact Fee Review | 4/30/2019 | 5/3/2019 | 5/1/2019 | | PASS |
Karina Myles
|
|
|
Review requested for Commercial Permit
|
Permit Ready to Issue | | | 5/1/2019 | | DONE |
|
|
|
NEED
GC form
Certificate of Value
|
Plan assigned to (JHB) | 4/27/2019 | 4/27/2019 | 4/30/2019 | | PASS |
Joe Bruce
|
|
|
05/01 L1 Highland Rare Coin ePlan
|
Routing - PLAN CHECK | 4/27/2019 | | 4/30/2019 | | PASS |
Joe Bruce
|
|
|
|
1st review completed | | | 4/30/2019 | | DONE |
Joe Bruce
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/30/2019 | | DONE |
|
|
|
|
Routing - Addressing | 4/27/2019 | | 4/29/2019 | | PASS |
Laura Hunter
|
|
|
Corrected address to 217 N 10th St
|
Routing - PUBLIC WORKS | 4/27/2019 | | 4/29/2019 | | PASS |
Morgan Webb
|
|
|
NO NEW PLUMBING
|
Intake Approval | | | 4/25/2019 | | PASS |
Javier Guzman
|
|
|
|
Intake Approval | | | 4/23/2019 | | FAIL |
Joe Bruce
|
|
|
1) Show portable fire extinguisher locations on the floor plan. This is a requirements of the 2015 IBC.
2) Sheet G1.1 references the wrong mechanical code used for this design. The City of Boise has adopted the 2012 IMC. Revise drawings to show correct code.
|
Application received | | | 4/19/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Apr 19 2019 4:02PM
|