BLD-Aging Inspection | 8/5/2020 | 8/5/2020 | 8/6/2020 | | PEND |
Tell Riley
|
|
|
no final inspections requested//
|
BLD-Aging Inspection | 8/4/2020 | 8/4/2020 | 8/5/2020 | | PEND |
Tell Riley
|
|
|
|
PubWorks Occupancy Approval | 7/30/2020 | 7/30/2020 | 7/30/2020 | | DONE |
Jason C. Taylor
|
|
|
A letter from the applicant’s civil engineer/landscape architect indicating that the final grading and drainage is acceptable has been received by Public Works. Final occupancy may be approved by the building department Jason Taylor ###-####.
|
BLD-Framing/Rough-in | 3/23/2020 | 3/23/2020 | 3/23/2020 | P | PASS |
Tell Riley
|
|
|
Framing Inspection. Please contact us 20 minutes prior to have someone on site. Thank you! Phone #: ###-#### Inspection requested via web by Oleksiy Yanchuk//email from engineer recieved//corrections made//
|
BLD-Framing/Rough-in | 3/9/2020 | 3/10/2020 | 3/10/2020 | A | FAIL |
Tell Riley
|
|
|
Correction List: Nailed all green plate with hand dipped galvanized nails. Removed 3 small panels of shear to make visible the hold downs Added Simpson S27 straps on the portal header. A roof plan and engineering is in the fireplace. Phone #: ###-#### Inspection requested via web by Oleksiy Yanchuk//correction notice posted/need two hold downs per portal frame- only 1 per side on side portal frames//straps are not the same as specified on plans, and all 4 wall need them per the engineering// trusses ok//fix framing per plans or have enginneer approve//
|
BLD-Framing/Rough-in | 3/6/2020 | 3/9/2020 | 3/9/2020 | A | FAIL |
Tell Riley
|
|
|
Shear wall and Framing inspection Approved plans are on site in the fire place. Phone #: ###-#### Inspection requested via web by Oleksiy Yanchuk//CN posted//need hot dip galvanized nails in pt//need access to columns to verify attachments per plans//straps need added opposite side of sheating on all portal frame per details on plans//need truss plans//
|
BLD-Foundation | 11/18/2019 | 11/18/2019 | 11/18/2019 | A | PASS |
Tell Riley
|
|
|
Phone #: 2089656103 >> Inspection requested via mobile web by Alvaro//WIP...pending specials if required on this portion//
|
BLD-Foundation | 11/15/2019 | 11/15/2019 | 11/15/2019 | P | CANC |
Tell Riley
|
|
|
Phone #: 2089656103 >> Inspection requested via mobile web by Alvaro//cancel per Alvaro//
|
BLD-Footing | 11/14/2019 | 11/14/2019 | 11/14/2019 | P | PART |
Tell Riley
|
|
|
As early as possible Phone #: 2089656103 >> Inspection requested via mobile web by Alvaro//cabana and planter footings--ok per plans//pending specials if required//setbacks surveyed in and per plans//
|
BLD-Foundation | 10/24/2019 | 10/24/2019 | 10/25/2019 | P | DEFR |
Tell Riley
|
|
|
Phone #: 2089656103 >> Inspection requested via mobile web by Alvaro//defer to special inspection//spoke with contact and rebar, formwork and concrete testing will be performed//
|
BLD-Footing | 10/17/2019 | 10/17/2019 | 10/17/2019 | P | PASS |
Tell Riley
|
|
|
Phone #: 2089656103 >> Inspection requested via mobile web by Alvaro//footings per plans//setbacks were set by surveyor//ok pending specials //
|
PubWorks Subgrade Approval | 10/17/2019 | 10/17/2019 | 10/17/2019 | | DONE |
Melissa Jannusch
|
|
|
*fire pit retaining walls* A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Melissa Jannusch ###-####.
|
BLD-Footing | 10/16/2019 | 10/16/2019 | 10/16/2019 | P | FAIL |
Tell Riley
|
|
|
*please as late as possible after 3:30pm** Phone #: 2089656103 >> Inspection requested via mobile web by Alvaro///need geotech report approved by public works prior to pouring footings//special inspections for rebar and concrete placement are required per plans//
|
Issue PAID IN FULL permit | | | 7/16/2019 | | DONE |
|
|
|
|
OVERRIDE | | | 6/6/2019 | | |
|
|
|
|
Plan assigned to (RDP) | 4/22/2019 | 4/22/2019 | 6/6/2019 | | DONE |
Rob Patrick
|
|
|
Took in at front desk. 05/07 Hillside Failed.
|
Telephone call | | | 6/6/2019 | | DONE |
|
|
|
Left a message for Clayton informing permit is ready, fee amount due and RP needed (his expired)
|
Inspection Record Card- Bld | | | 6/6/2019 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 6/6/2019 | | DONE |
Rob Patrick
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/6/2019 | | DONE |
Rob Patrick
|
|
|
|
Permit Ready to Issue | | | 6/6/2019 | | DONE |
|
|
|
met: NEED RP
|
Routing - PLAN CHECK | 5/28/2019 | | 6/6/2019 | | PASS |
Rob Patrick
|
|
|
|
Routing - PLANNING | 6/4/2019 | | 6/5/2019 | | PASS |
Celine Acord
|
|
|
|
Routing - PUBLIC WORKS GRADING | 5/28/2019 | | 6/4/2019 | | PASS |
Angela Hardy
|
|
|
|
Routing PW Grading-Hillside | 6/3/2019 | | 6/3/2019 | | PASS |
Melissa Jannusch
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Please e-mail the stamped inspection approval letter to mjannusch@cityofboise.org and allow 24 hours for subgrade approval processing. Call Melissa Jannusch at ###-#### with questions.
Prior to obtaining a final for the permit, the roof storm drainage system must be inspected by Public Works. Call Melissa Jannusch at ###-####.
The final inspection of the site grading and drainage work shall be done by the design engineer. Written approval shall be submitted to Boise Public Works prior to the issuance of the building final.
|
Plan Reviewer's activity | | | 5/28/2019 | | |
Rob Patrick
|
|
|
Delivered 3 corrected sets to Hillside/Public Works for review.
|
Plan resubmittals received | | | 5/24/2019 | | DONE |
|
|
|
3 copies of resubmitted plans received (CVR, A-1.1. A-2.1) and taken to Rob
|
Plan Reviewer's activity | | | 5/17/2019 | | |
|
|
|
Emailed Clayton to include Architectral dwgs with 05/15 re-submittal before routing could start.
|
Plan resubmittals received | | | 5/16/2019 | | DONE |
|
|
|
resubmittals recieved 3 sets of sheets l1.1,l1.5,l2.1, l2.5, s-0.1, s-0.2, s-0.3, s-0.4, s-1.0, s-1.1, s-2.0, s-2.1, s-3.0 & 3 letters from, materials testing-took to Rob
|
Plan Reviewer's activity | | | 5/14/2019 | | |
|
|
|
Delivered 3 L2.1 sheets to Andy for "APPROVAL" stamps.
|
Routing - PLAN CHECK | 4/22/2019 | | 5/7/2019 | | FAIL |
Rob Patrick
|
|
|
Hillside corrections req'd.
|
1st review completed | | | 5/7/2019 | | DONE |
Rob Patrick
|
|
|
|
Routing - Erosion and Sediment | 4/22/2019 | | 5/6/2019 | | PASS |
Andy J. Long
|
|
|
ESC plan approved. Certified stormwater team designated. Site preparation inspection is REQUIRED.
|
Routing - PLANNING | 4/22/2019 | | 5/2/2019 | | FAIL |
Karla Nelson
|
|
|
Wall heights cannot exceed 6' in the side or rear setback. Side setback is 10', rear is 30'.
|
Routing PW Grading-Hillside | 4/22/2019 | | 4/30/2019 | | FAIL |
Melissa Jannusch
|
|
|
See e-mail
|
Routing - PUBLIC WORKS | 4/30/2019 | | 4/30/2019 | | FAIL |
Angela Hardy
|
|
|
Hillside Fail
|
Plan resubmittals received | | | 4/24/2019 | | DONE |
|
|
|
Resubmittals recieved 2 sets of sheet L1.1, L2.1, 2 material testing & inspections and 1 eng calcs-took to Rob P
|
Routing - Addressing | 4/23/2019 | | 4/23/2019 | | PASS |
Doug Chausow
|
|
|
|
Routing Walk-In (Zoning) | 4/22/2019 | 4/22/2019 | 4/22/2019 | A | PASS |
Ethan Mansfield
|
|
|
|
Routing Walk-In (BLD) | 4/22/2019 | 4/22/2019 | 4/22/2019 | A | CANC |
Rob Patrick
|
|
|
|
Application received | | 4/22/2019 | | | |
|
|
|
|