Permit Information
Permit NumberBLD19-01310
StatusIssued
Name HELLMANN CONSTRUCTION CO INC
Site Address 234 S 10TH ST
Project Name10th & Front Garage Repairs
Customer Number 
ePlanReviewYes
Description
(10TH AND FRONT PARKING GARAGE) Permit is for repairs to an existing 5 level masonry parking garage. Work to include: removal and installation of new steel guards / vehicle barriers, installation of a new waterproof membrane, remove/replace damaged concrete deck & structural components, fix bar in accordance with engineering finds on site after demo, and pour new concrete. Special inspections are required for this project - see form #310 attached. This building is not fire sprinklered. Approval contingent upon adhering to the approved plans on file and attached structural calculations. **MDH**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final1/2/20201/3/20201/3/2020APASS
DetailsDave Hannah
Eric (said you just needed paperwork to sign off) Phone #: ###-####
MISC ACTIONS  12/18/2019 DONE
Structural Repair Final Report provided by Building Inspector Dave Hannah, attached in documents
BLD-Final12/6/201912/9/201912/9/2019APEND
DetailsDave Hannah
Aliya Phone #: ###-#### need final reports
BLD-Conference9/19/20199/23/20199/23/2019ADONE
DetailsDave Hannah
Eric Phone #: ###-####
Issue PAID IN FULL permit  8/27/2019 DONE
Inspection Record Card- Bld  8/27/2019 DONE
PLANS/APPL TAKEN TO FRONT DESK  6/21/2019 DONE
DetailsMichael Hanson
Permit Ready to Issue  6/21/2019 DONE
met (came in by fax)
Need
GC Form
Revised Value
Plan assigned to (M_H)5/16/2019 6/21/2019 DONE
DetailsMichael Hanson
1st review completed - 06/12 #520 L3 ePlan - 10th & Front Parking Garage
Routing Off Site - STRUCTURAL6/14/2019 6/21/2019 PASS
DetailsMichael Hanson
Chris M. @ Stapley engineering
Routing - Design Review6/14/2019 6/14/2019 PASS
DetailsKayCee Babb
Per CZC18-00212, to comply with all conditions of approval on guards and downspout finish.
Route to Impact Fee Review6/11/20196/14/20196/11/2019 PASS
DetailsShannon Cade
Review requested for Commercial Permit
Routing - PLAN CHECK5/16/2019 6/11/2019 PASS
DetailsMichael Hanson
1st review completed  6/11/2019 FAIL
DetailsMichael Hanson
Failed design review and structural
Routing Off Site - STRUCTURAL5/16/2019 6/10/2019 FAIL
DetailsMichael Hanson
Failed per Chris M. @ Stapley engineering. See documents and agency documents in ePlan.
Routing - Design Review5/16/2019 5/16/2019 FAIL
DetailsKayCee Babb
Elevation required to verify compliance with all documents on file and conditions of approval of CZC18-00212.
Intake Approval  5/16/2019 PASS
DetailsMichael Hanson
Prescreen approved by M_H.
Application received  4/22/2019 DONE
Application submitted via PDS Online on Apr 22 2019 2:22PM