BLD-Final | 10/30/2019 | 10/31/2019 | 10/31/2019 | P | PASS |
Brandon Shaw
|
|
|
Corrections SAT...
|
DOC - Permit Finaled | 10/31/2019 | 10/31/2019 | 10/31/2019 | P | PASS |
Brandon Shaw
|
|
|
|
BLD-Blower Door Test Results | 10/31/2019 | 10/31/2019 | 10/31/2019 | P | DONE |
Brandon Shaw
|
|
|
ACH50- 4.58
|
BLD-Final | 10/28/2019 | 10/29/2019 | 10/29/2019 | A | NR |
Tell Riley
|
|
|
Call ahead for access // Willie Phone #: ###-####//need to add window opeing device upstairs-fix the two installed as well//finish hand rail//add pipe bollard//
|
BLD-Energy code compliance | 9/4/2019 | 9/4/2019 | 9/4/2019 | P | PASS |
Tell Riley
|
|
|
will Phone #: ###-####//ok//
|
BLD-Framing/Rough-in | 9/3/2019 | 9/4/2019 | 9/4/2019 | A | PASS |
Tell Riley
|
|
|
Willy Phone #: ###-####//corrections made//
|
BLD-Framing/Rough-in | 8/30/2019 | 9/3/2019 | 9/3/2019 | A | PASS |
Tell Riley
|
|
|
Willy Phone #: ###-####//ok to insulate only//correction for minor framing corrections posted//
|
Routing - MECHANICAL | 8/23/2019 | | 8/23/2019 | | PASS |
Troy James
|
|
|
New manual j report.
|
BLD-Wall Bracing | 8/14/2019 | 8/15/2019 | 8/15/2019 | A | PASS |
Tell Riley
|
|
|
shear // will Phone #: ###-####
|
BLD-Foundation | 6/18/2019 | 6/18/2019 | 6/18/2019 | P | PASS |
Tell Riley
|
|
|
Phone #: 2086971241 >> Inspection requested via mobile web by Heron//install STHD 14's per plans.// will move to correct location as discussed onsite.//
|
BLD-Foundation | 6/17/2019 | 6/17/2019 | 6/17/2019 | P | PART |
Tell Riley
|
|
|
Phone #: 2086971241 >> Inspection requested via mobile web by Heron//rebar installed per plans//work in progress//
|
BLD-Footing | 6/14/2019 | 6/14/2019 | 6/14/2019 | P | PASS |
Tell Riley
|
|
|
Phone #: 2086971241 >> Inspection requested via mobile web by Heron//setbacks ok per site plan//rebar installed per plans. //
|
Issue PAID IN FULL permit | | | 5/17/2019 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 5/17/2019 | | DONE |
|
|
|
|
OVERRIDE | | | 5/16/2019 | | |
|
|
|
|
Plan assigned to (J_N) | 5/2/2019 | 5/2/2019 | 5/16/2019 | | DONE |
Jenny Nelson
|
|
|
05/15 sfd L1 ePlan. 1st complete 5/14, need bracing calcs
|
Telephone call | | | 5/16/2019 | | DONE |
|
|
|
spoke with contractor informing him there are fees still due for issuance.
|
Routing - PLAN CHECK | 5/16/2019 | | 5/16/2019 | | PASS |
Jenny Nelson
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/16/2019 | | DONE |
Jenny Nelson
|
|
|
|
Permit Ready to Issue | | | 5/16/2019 | | DONE |
|
|
|
|
1st review completed | | | 5/14/2019 | | FAIL |
Jenny Nelson
|
|
|
|
Routing - PLAN CHECK | 5/2/2019 | | 5/14/2019 | | FAIL |
Jenny Nelson
|
|
|
need wall bracing calcs
|
Routing - PLANNING | 5/2/2019 | | 5/8/2019 | | PASS |
Brent Moore
|
|
|
|
Route to Impact Fee Review | 5/2/2019 | 5/5/2019 | 5/3/2019 | | PASS |
Eric Bilimoria
|
|
|
Initial residential review of new SFD permits requested for now.
|
Routing - Addressing | 5/2/2019 | | 5/2/2019 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 5/2/2019 | | 5/2/2019 | | PASS |
Angela Hardy
|
|
|
|
Routing - MECHANICAL | 5/2/2019 | | 5/2/2019 | | PASS |
Chad Schwendiman
|
|
|
|
Intake Approval | | | 5/2/2019 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 5/2/2019 | | DONE |
|
|
|
|
Intake Approval | | | 5/1/2019 | | FAIL |
|
|
|
1. Plans must be uploaded in "landscape" format in the horizontal
2. indicate where crawl access is located
|
Application received | | | 4/22/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Apr 22 2019 3:31PM
|