Information based on query as of Wednesday, July 24, 2024.
Permit Information
Permit NumberBLD19-01314
StatusFinaled
Name RED OAK DEVELOPMENT LLC
Site Address 2082 N WOODCREEK ST
Project NameThe Avenue Sub.
Customer Number 
ePlanReviewYes
Description
**PRESCRIPTIVE ENERGY METHOD** Permit for the construction of a new 2128 sq. ft., two story (first story 931 sq. ft., second story 1197 sq. ft.) single family dwelling with 3 bedrooms, 3 bathrooms, approximately 64 sq. ft. of covered patio/porch and a 538 sq. ft. attached garage per the approved plans and any notations. R-1C zoning and setbacks per planning. JJN
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final10/30/201910/31/201910/31/2019PPASS
DetailsBrandon Shaw
Corrections SAT...
DOC - Permit Finaled10/31/201910/31/201910/31/2019PPASS
DetailsBrandon Shaw
BLD-Blower Door Test Results10/31/201910/31/201910/31/2019PDONE
DetailsBrandon Shaw
ACH50- 4.58
BLD-Final10/28/201910/29/201910/29/2019ANR
DetailsTell Riley
Call ahead for access //
Willie Phone #: ###-####//need to add window opeing device upstairs-fix the two installed as well//finish hand rail//add pipe bollard//
BLD-Energy code compliance9/4/20199/4/20199/4/2019PPASS
DetailsTell Riley
will Phone #: ###-####//ok//
BLD-Framing/Rough-in9/3/20199/4/20199/4/2019APASS
DetailsTell Riley
Willy Phone #: ###-####//corrections made//
BLD-Framing/Rough-in8/30/20199/3/20199/3/2019APASS
DetailsTell Riley
Willy Phone #: ###-####//ok to insulate only//correction for minor framing corrections posted//
Routing - MECHANICAL8/23/2019 8/23/2019 PASS
DetailsTroy James
New manual j report.
BLD-Wall Bracing8/14/20198/15/20198/15/2019APASS
DetailsTell Riley
shear // will Phone #: ###-####
BLD-Foundation6/18/20196/18/20196/18/2019PPASS
DetailsTell Riley
Phone #: 2086971241 >> Inspection requested via mobile web by Heron//install STHD 14's per plans.// will move to correct location as discussed onsite.//
BLD-Foundation6/17/20196/17/20196/17/2019PPART
DetailsTell Riley
Phone #: 2086971241 >> Inspection requested via mobile web by Heron//rebar installed per plans//work in progress//
BLD-Footing6/14/20196/14/20196/14/2019PPASS
DetailsTell Riley
Phone #: 2086971241 >> Inspection requested via mobile web by Heron//setbacks ok per site plan//rebar installed per plans. //
Issue PAID IN FULL permit  5/17/2019 DONE
Inspection Record Card- Bld  5/17/2019 DONE
OVERRIDE  5/16/2019  
Plan assigned to (J_N)5/2/20195/2/20195/16/2019 DONE
DetailsJenny Nelson
05/15 sfd L1 ePlan. 1st complete 5/14, need bracing calcs
Telephone call  5/16/2019 DONE
spoke with contractor informing him there are fees still due for issuance.
Routing - PLAN CHECK5/16/2019 5/16/2019 PASS
DetailsJenny Nelson
PLANS/APPL TAKEN TO FRONT DESK  5/16/2019 DONE
DetailsJenny Nelson
Permit Ready to Issue  5/16/2019 DONE
1st review completed  5/14/2019 FAIL
DetailsJenny Nelson
Routing - PLAN CHECK5/2/2019 5/14/2019 FAIL
DetailsJenny Nelson
need wall bracing calcs
Routing - PLANNING5/2/2019 5/8/2019 PASS
DetailsBrent Moore
Route to Impact Fee Review5/2/20195/5/20195/3/2019 PASS
DetailsEric Bilimoria
Initial residential review of new SFD permits requested for now.
Routing - Addressing5/2/2019 5/2/2019 PASS
DetailsDoug Chausow
Routing - PUBLIC WORKS5/2/2019 5/2/2019 PASS
DetailsAngela Hardy
Routing - MECHANICAL5/2/2019 5/2/2019 PASS
DetailsChad Schwendiman
Intake Approval  5/2/2019 PASS
Recd Pcfee & Taken To Pln CK  5/2/2019 DONE
Intake Approval  5/1/2019 FAIL
1. Plans must be uploaded in "landscape" format in the horizontal
2. indicate where crawl access is located
Application received  4/22/2019 DONE
Application submitted via PDS Online on Apr 22 2019 3:31PM