BLD-Framing/Rough-in | 5/27/2020 | 5/27/2020 | 5/27/2020 | P | PASS |
Mike Jordan
|
|
|
Tara Phone #: ###-####. Interior wood framed walls for restrooms only ok.
|
BLD-Framing/Rough-in | 5/15/2020 | 5/18/2020 | 5/18/2020 | A | NR |
Brandon Shaw
|
|
|
Ele permits to be asigned to proper addresses...
|
BLD-Framing/Rough-in | 5/15/2020 | 5/15/2020 | 5/15/2020 | P | NR |
Tell Riley
|
|
|
kara Phone #: ###-####/add backing for grab bars//need ELE permits fixed//need mechanical permits//seal penetrations at top plates//bathroom dimension does not meet size on plans, have architect verify size will still meet min requirements or alter size to meet plans//
|
Issue PAID IN FULL permit | | | 8/1/2019 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 8/1/2019 | | DONE |
|
|
|
|
(F) Reprint permit | | | 8/1/2019 | | DONE |
|
|
|
|
Routing - PUBLIC WORKS | 7/18/2019 | | 7/31/2019 | | PASS |
Morgan Webb
|
|
|
|
Routing - PUBLIC WORKS | 6/14/2019 | | 7/31/2019 | | PASS |
Morgan Webb
|
|
|
|
Plan assigned to (BJM) | 5/3/2019 | 5/3/2019 | 7/30/2019 | | DONE |
Brian McGowan
|
|
|
6th Review Complete-05/24 - 4 Office Suite #120 L-3
|
Routing - Design Review | 6/13/2019 | | 7/30/2019 | | PASS |
KayCee Babb
|
|
|
Per DRH19-00186 modification, to comply with all conditions of approval including any RTU shall be fully screened by either the existing parapet or additional screening as approved through Design Review.
|
Routing - PLAN CHECK | 7/23/2019 | | 7/30/2019 | | PASS |
Brian McGowan
|
|
|
|
Routing - PUBLIC WORKS | 7/23/2019 | | 7/30/2019 | | PASS |
Morgan Webb
|
|
|
Please remember that this is one of (4) Pemits attached to this ePlan. Tidemark sign offs are needed on all.
BLD19- 00915, 01334, 01335, 01336
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/30/2019 | | DONE |
Brian McGowan
|
|
|
|
Permit Ready to Issue | | | 7/30/2019 | | DONE |
|
|
|
BLD19-00915, 01334 - 01336
NEED
GC FORM
REVISED VALUE
|
Routing - FIRE | 7/17/2019 | 7/17/2019 | 7/23/2019 | | PASS |
Mark Scharfen
|
|
|
Completed fire review. Uploaded rev_fire 07.23.2019.pdf
|
Routing - PLAN CHECK | 7/18/2019 | | 7/19/2019 | | FAIL |
Brian McGowan
|
|
|
|
Routing - PLAN CHECK | 7/10/2019 | | 7/10/2019 | | FAIL |
Brian McGowan
|
|
|
|
Routing - PLAN CHECK | 6/13/2019 | | 7/1/2019 | | FAIL |
Brian McGowan
|
|
|
|
Route to Impact Fee Review | 5/29/2019 | 6/1/2019 | 5/30/2019 | | PASS |
Shannon Cade
|
|
|
Review requested for Commercial Permit
|
Routing - PUBLIC WORKS | 5/3/2019 | | 5/30/2019 | | PASS |
Angela Hardy
|
|
|
|
Routing - PLANNING | 5/3/2019 | | 5/30/2019 | | PASS |
Nicolette Womack
|
|
|
|
Routing - FIRE | 5/3/2019 | 5/3/2019 | 5/29/2019 | | PASS |
Mark Scharfen
|
|
|
05.29.2019-Completed fire review. Uploaded rev_fire 05.29.2019.pdf.
|
1st review completed | | | 5/29/2019 | | FAIL |
Brian McGowan
|
|
|
|
Routing - PLAN CHECK | 5/3/2019 | | 5/29/2019 | | FAIL |
Brian McGowan
|
|
|
Modifying floor plan
|
Routing - PLUMBING | 5/3/2019 | | 5/9/2019 | | PASS |
Dan Ediger
|
|
|
per plans and ISPC
|
Routing - MECHANICAL | 5/3/2019 | | 5/7/2019 | | PASS |
Troy James
|
|
|
Need to address mechanical ventilation at occupancy.
|
Routing - Addressing | 5/3/2019 | | 5/6/2019 | | PASS |
Doug Chausow
|
|
|
Suite 120
|
Routing - Design Review | 5/3/2019 | | 5/6/2019 | | FAIL |
KayCee Babb
|
|
|
Per DRH18-00376. Plans do not match approved elevations and a Class II tree is required in the northern terminal planter.
|
Intake Approval | | | 5/1/2019 | | PASS |
|
|
|
|
Application received | | | 4/23/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Apr 23 2019 11:48AM
|