Permanent Occupancy | | | 8/22/2019 | | DONE |
|
|
|
|
BLD-Final | 8/21/2019 | 8/21/2019 | 8/21/2019 | P | PASS |
Brandon Shaw
|
|
|
Natalie Phone #: ###-####
|
DOC - Permit Finaled | 8/21/2019 | 8/21/2019 | 8/21/2019 | P | PASS |
Brandon Shaw
|
|
|
|
FIRE-Final Inspection | 8/19/2019 | 8/20/2019 | 8/20/2019 | A | PASS |
Jim Page
|
|
|
Previously noted item has been corrected, no fire sprinklers, no fire alarms, fire extinguisher is placed with a current inspection tag. Final life fire safety inspection for area of work complete.
natalie Phone #: ###-####
|
BLD-Final | 8/1/2019 | 8/2/2019 | 8/2/2019 | A | FAIL |
Tell Riley
|
|
|
Natalie Phone #: ###-####//office door is locked//need fire/life safety inspection pass prior to final//
|
FIRE-Final Inspection | 8/1/2019 | 8/1/2019 | 8/1/2019 | P | FAIL |
Troy Cobbley
|
|
|
Repair or remove the non-functional exit sign at the main exit.
Natalie Phone #: ###-####
|
Print Occupancy Form | | | 8/1/2019 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 8/1/2019 | | DONE |
|
|
|
|
Telephone call | | | 8/1/2019 | | DONE |
|
|
|
called to let know permit is ready left message on her cell phone
|
Issue PAID IN FULL permit | | | 8/1/2019 | | DONE |
|
|
|
|
Plan assigned to (JHB) | 7/30/2019 | | 7/31/2019 | | PASS |
Joe Bruce
|
|
|
08/02 (528) Allstate Insurance, Paper
|
Routing - PLAN CHECK | 7/30/2019 | | 7/31/2019 | | PASS |
Joe Bruce
|
|
|
|
1st review completed | | | 7/31/2019 | | DONE |
Joe Bruce
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/31/2019 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 7/31/2019 | | DONE |
Joe Bruce
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 7/30/2019 | | DONE |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 7/30/2019 | | DONE |
|
|
|
|
Intake Approval | | | 7/30/2019 | | PASS |
|
|
|
|
First Notice | | 9/1/2019 | | | |
|
|
|
|
First Notice | 8/21/2019 | 8/21/2019 | | | |
Brandon Shaw
|
|
|
|
Application received | | 4/23/2019 | | | |
|
|
|
|