BLD-Final | 12/20/2019 | 12/20/2019 | 12/20/2019 | P | PASS |
Mike Jordan
|
|
|
Kenny Phone #: ###-####
|
DOC - Permit Finaled | 12/20/2019 | 12/20/2019 | 12/20/2019 | P | PASS |
Mike Jordan
|
|
|
|
BLD-Blower Door Test Results | 12/20/2019 | 12/20/2019 | 12/20/2019 | P | DONE |
Mike Jordan
|
|
|
3.2
|
BLD-Energy code compliance | 10/2/2019 | 10/3/2019 | 10/3/2019 | A | PASS |
Mike Jordan
|
|
|
Kenny Phone #: ###-####. All issues have been resolved.
|
BLD-Framing/Rough-in | 10/2/2019 | 10/2/2019 | 10/2/2019 | P | NR |
Mike Jordan
|
|
|
Kenny Phone #: ###-####
|
BLD-Framing/Rough-in | 10/2/2019 | 10/2/2019 | 10/2/2019 | P | NR |
Mike Jordan
|
|
|
Kenny Phone #: ###-####
|
BLD-Energy code compliance | 10/1/2019 | 10/1/2019 | 10/1/2019 | P | CANC |
Mike Jordan
|
|
|
Cancelled by contractor via text message.
|
BLD-Energy code compliance | 9/30/2019 | 10/1/2019 | 10/1/2019 | A | CANC |
Mike Jordan
|
|
|
KENNY Phone #: ###-####. Moved to pm inspection.
|
BLD-Framing/Rough-in | 9/27/2019 | 9/30/2019 | 9/30/2019 | A | PART |
Mike Jordan
|
|
|
Kenny Phone #: ###-####. Provide approved fix for cut top chords of floor joist at plumbing penetrations. Complete fire cauliking. complete laydown parapet in noted areas. Install mised lateral bracing.
|
BLD-Wall Bracing | 9/6/2019 | 9/6/2019 | 9/6/2019 | P | PASS |
Mike Jordan
|
|
|
KENNY Phone #: ###-####
|
BLD-Other | 8/23/2019 | 8/23/2019 | 8/23/2019 | P | PASS |
Mike Jordan
|
|
|
Kenny- insalation for fire wall Phone #: ###-####
|
BLD-Energy code compliance | 8/9/2019 | 8/9/2019 | 8/9/2019 | P | PASS |
Mike Jordan
|
|
|
LARRY Phone #: ###-####. . Insulation for 1hr. walls first floor.
|
BLD-Concrete | 7/24/2019 | 7/26/2019 | 7/26/2019 | P | PART |
Tell Riley
|
|
|
rebar-Shane Phone #: ###-####//rebar inspected on AM inspection//maintain clearances//
|
BLD-Foundation | 7/25/2019 | 7/26/2019 | 7/26/2019 | A | PART |
Tell Riley
|
|
|
Kenny Phone #: ###-####//extend vapor barrier to edge of foundation//maintain rebar clearance//
|
BLD-Footing | 6/25/2019 | 6/25/2019 | 6/25/2019 | P | CANC |
Mike Jordan
|
|
|
Kenny- Phone #: ###-####
|
BLD-Energy code compliance | 6/25/2019 | 6/25/2019 | 6/25/2019 | P | PASS |
Mike Jordan
|
|
|
Kenny- Phone #: ###-####. Rigid insulation on stemwall under slab on grade.
|
BLD-Foundation | 6/19/2019 | 6/20/2019 | 6/20/2019 | P | PART |
Mike Jordan
|
|
|
Dane- inspection wall Phone #: ###-####
|
BLD-Footing | 6/18/2019 | 6/19/2019 | 6/19/2019 | P | PART |
Mike Jordan
|
|
|
Dane Phone #: ###-####
|
Issue PAID IN FULL permit | | | 5/29/2019 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 5/29/2019 | | DONE |
|
|
|
|
OVERRIDE | | | 5/24/2019 | | |
|
|
|
|
Plan assigned to (J_N) | 5/15/2019 | 5/15/2019 | 5/24/2019 | | DONE |
Jenny Nelson
|
|
|
06/03 townhouses L2 ePlan
|
Routing - PLAN CHECK | 5/15/2019 | | 5/24/2019 | | PASS |
Jenny Nelson
|
|
|
|
1st review completed | | | 5/24/2019 | | DONE |
Jenny Nelson
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/24/2019 | | DONE |
Jenny Nelson
|
|
|
|
Permit Ready to Issue | | | 5/24/2019 | | DONE |
|
|
|
met
DO NOT ISSUE WITHOUT BLD19-01355, BLD19-01358 TO BLD19-01363
|
Route to Impact Fee Review | 5/15/2019 | 5/18/2019 | 5/16/2019 | | PASS |
Shannon Cade
|
|
|
Initial residential review of new SFD permits requested for now.
|
Routing - PUBLIC WORKS | 5/15/2019 | | 5/16/2019 | | PASS |
Angela Hardy
|
|
|
|
Routing - MECHANICAL | 5/15/2019 | | 5/16/2019 | | PASS |
Chad Schwendiman
|
|
|
|
Routing - PLANNING | 5/15/2019 | | 5/16/2019 | | PASS |
Andrea Tuning
|
|
|
|
Routing - Addressing | 5/15/2019 | | 5/15/2019 | | PASS |
Doug Chausow
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 5/15/2019 | | DONE |
|
|
|
|
Intake Approval | | | 5/15/2019 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 5/15/2019 | | DONE |
|
|
|
|
Meeting | | | 4/29/2019 | | DONE |
|
|
|
Spoke with Larry with Sterling Homes, he informed me that Cosatal Construction and Lumber is the parent company and is the RCE number they will be using.
|
Intake Approval | | | 4/24/2019 | | FAIL |
|
|
|
missing manual J
|
Application received | | 4/24/2019 | | | |
|
|
|
|