BLD-Aging Inspection | 1/28/2020 | 1/28/2020 | 1/29/2020 | | DONE |
Tell Riley
|
|
|
C of C was issued
|
DOC - Permit Finaled | 1/29/2020 | 1/29/2020 | 1/29/2020 | P | PASS |
Tell Riley
|
|
|
Telephone call 9/17/2019 DONE emailed C of C to Jon Gleason
|
Letter of compliance/Occupancy | | | 9/17/2019 | | DONE |
|
|
|
|
Telephone call | | | 9/17/2019 | | DONE |
|
|
|
emailed C of C to Jon Gleason
|
BLD-Final | 9/13/2019 | 9/16/2019 | 9/16/2019 | A | PASS |
Tell Riley
|
|
|
John Phone #: ###-####//ok per plans//
|
FIRE-Final Inspection | 9/13/2019 | 9/13/2019 | 9/13/2019 | P | PASS |
Jim Page
|
|
|
No fire sprinkler modifications, no fire alarm modifications, fire extinguishers are in common areas and not in vanilla space, next tenant will be required to have additional fire extinguishers due to current extinguisher spacing. Final life fire safety inspection for vanilla space is complete, signatures provided on sign off card for associated trades, no occupancy allowed under this permit.
John Phone #: ###-####
|
BLD-Final | 6/26/2019 | 6/28/2019 | 6/28/2019 | P | CANC |
Tell Riley
|
|
|
John Phone #: ###-####//wrong permit number//will call in correct #//
|
FIRE-Final Inspection | 6/26/2019 | 6/28/2019 | 6/28/2019 | A | CANC |
Jim Page
|
|
|
Wrong permit requested for inspection, this request is cancelled.
John Phone #: ###-####
|
Issue PAID IN FULL permit | | | 5/14/2019 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 5/14/2019 | | DONE |
|
|
|
|
Plan assigned to (JG) | 4/24/2019 | 4/24/2019 | 5/13/2019 | | PASS |
Javier Guzman
|
|
|
2nd rev, 05/02 L2 Vanilla (ePlan under BLD19-01272)
|
Routing - PLAN CHECK | 5/9/2019 | | 5/13/2019 | | PASS |
Javier Guzman
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/13/2019 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 5/13/2019 | | DONE |
|
|
|
MET
NEED
REVISED VALUE
MET
GC FORM
|
Route to Impact Fee Review | 5/2/2019 | 5/5/2019 | 5/3/2019 | | PASS |
Eric Bilimoria
|
|
|
Review requested for Commercial Permit
|
Routing - PLAN CHECK | 4/24/2019 | | 5/2/2019 | | FAIL |
Javier Guzman
|
|
|
|
1st review completed | | | 5/2/2019 | | FAIL |
Javier Guzman
|
|
|
|
Routing - Addressing | 4/24/2019 | | 4/25/2019 | | PASS |
Doug Chausow
|
|
|
|
Application received | | 4/24/2019 | 4/24/2019 | | DONE |
Javier Guzman
|
|
|
|
Intake Approval | | | 4/24/2019 | | PASS |
Javier Guzman
|
|
|
|
Routing - PUBLIC WORKS | 4/24/2019 | | 4/24/2019 | | PASS |
Angela Hardy
|
|
|
|