Description
MODIFICATION - CHANGED PANEL MANUFACTURER 7-2-19 **jab**Permit for 385sq' of roof-mounted, grid-tied Photo-voltaic panels with micro-inverters; 22 panels in 1 array tying into a SquareD panel. No work needed to the existing roof structure per engineer’s roof evaluation. All racking, modules, and other listed equipment must be installed by a certified installer. All work per plans, engineering, manufacturer’s specs, & local code. Separate electrical permit required. **JAB**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final7/3/20197/5/20197/5/2019PPASS
DetailsTell Riley
Plans have been left on site in the meter box Phone #: ###-#### Inspection requested via web by Brecklee Brown//final complete per olans//
DOC - Permit Finaled7/5/20197/5/20197/5/2019PPASS
DetailsTell Riley
Fees Due Hold7/3/2019 7/3/2019 DONE
Details
Plan assigned to (JAB) Josh6/27/20196/27/20197/2/2019 PASS
DetailsJosh Bogle
07/03 plan mod-changing solar brand, ePlan - 1st done (fee sheet added to Agency Comments)
Routing - PLAN CHECK7/2/2019 7/2/2019 PASS
DetailsJosh Bogle
new panels UL certified
Permit Ready to Issue  7/2/2019 DONE
CHANGE STATUS TO (ISS)  7/2/2019 DONE
Routing - PLAN CHECK6/27/2019 6/27/2019 FAIL
DetailsJosh Bogle
plan mod - no spec sheet for new panels
Plan Modification Accepted  6/27/2019 DONE
Plan mod requested by Mauricia, changing solar brand
Issue PAID IN FULL permit  5/3/2019 DONE
Permit Ready to Issue  4/29/2019 DONE
Plan assigned to (JAB) Josh4/25/20194/25/20194/26/2019 PASS
DetailsJosh Bogle
Routing - PLAN CHECK4/25/2019 4/26/2019 PASS
DetailsJosh Bogle
Routing - PLANNING4/25/2019 4/26/2019 PASS
DetailsColleen T Carroll
1st review completed  4/26/2019 DONE
DetailsJosh Bogle
PLANS/APPL TAKEN TO FRONT DESK  4/26/2019 DONE
DetailsJosh Bogle
ESC no - Energy no
Application received  4/25/2019 DONE
Application submitted via PDS Online on Apr 25 2019 11:46AM
Intake Approval  4/25/2019 PASS
Recd Pcfee & Taken To Pln CK  4/25/2019 DONE
no fees paid at intake