OVERRIDE | | | 7/16/2020 | | |
|
|
|
|
Plan assigned to (JAR) | 5/13/2020 | 5/13/2020 | 7/16/2020 | | DONE |
Julie Romig
|
|
|
1st Rev Comp - Plan Mod 1 - The Cartee
|
Permit Ready to Issue | | | 7/16/2020 | | DONE |
|
|
|
PLAN MOD- do not issue
|
Routing - PLAN CHECK | 7/10/2020 | | 7/16/2020 | | PASS |
Julie Romig
|
|
|
Plan Mod 1 - 2nd Review
|
Routing Off Site - STRUCTURAL | 7/10/2020 | | 7/10/2020 | | PASS |
Julie Romig
|
|
|
Jacobs - Plan Mod 1 - 2nd Review
|
Routing - FIRE | 5/28/2020 | 5/28/2020 | 6/23/2020 | | PASS |
Erika Akin
|
|
|
Attached revised comments to case and redlined floor plan level four pet area
|
Routing - MECHANICAL | 5/28/2020 | | 6/23/2020 | | PASS |
Troy James
|
|
|
Passed per ePlanReview
|
Routing PW Drainage | 6/12/2020 | | 6/18/2020 | | PASS |
Brian Murphy
|
|
|
sand shown c-33
|
Routing - PLAN CHECK | 5/28/2020 | | 6/17/2020 | | FAIL |
Julie Romig
|
|
|
Plan Mod 1 - Corrections required, refer to changemarks.
|
Routing PW Environmental | 6/12/2020 | | 6/15/2020 | | PASS |
Zach Conde
|
|
|
PER ZACH: Passed on ePlan with this comment: "Approved with grease abatement as shown." Please pass on Tidemark.
|
Routing PW Flood Plain | 6/2/2020 | | 6/12/2020 | | CANC |
Jason C. Taylor
|
|
|
Project is outside Special Flood Hazard Area, no floodplain review required. If you have any questions, please call Jason Taylor at ###-####.
|
Routing - Design Review | 5/28/2020 | | 6/12/2020 | | PASS |
Josh Wilson
|
|
|
|
Routing - PUBLIC WORKS | 5/28/2020 | | 6/2/2020 | | PASS |
Morgan Webb
|
|
|
|
Routing Off Site - STRUCTURAL | 5/28/2020 | | 5/29/2020 | | FAIL |
Julie Romig
|
|
|
Plan Mod 1 - Jacobs
|
Routing - PLUMBING | 5/28/2020 | | 5/29/2020 | | PASS |
Daryl Spivey
|
|
|
Per plan and ISPC.
|
Plan Modification Accepted | | | 5/13/2020 | | DONE |
|
|
|
Per Angie B. Project Manager, creating Plan Mod Workflow
The overall changes include a fourth-floor pet relief area at the alley-side roof deck, the removal of the geothermal snowmelt system, a revised furniture (both freestanding and built-in)
layout for the ground floor residential lobby and coworking lobby, and a revised layout to the Community Room and 4th street-side roof deck furniture layout (both freestanding and built-in).
In addition to the brief description above, a more detailed narrative with page-by-page descriptions will be uploaded in conjunction with the drawings
|
BLD-Footing | 1/2/2020 | 1/2/2020 | 1/2/2020 | P | PEND |
Dave Hannah
|
|
|
|
Issue PAID IN FULL permit | | | 10/8/2019 | | DONE |
|
|
|
|
Print Occupancy Form | | | 10/8/2019 | | DONE |
|
|
|
|
Plan assigned to (JAR) | 5/6/2019 | 5/7/2019 | 9/27/2019 | | DONE |
Julie Romig
|
|
|
09/26 - 4th Rev - 1st Rev Comp - The Cartee IA Podium
|
OVERRIDE | | | 9/25/2019 | | |
|
|
|
|
Routing - Design Review | 9/19/2019 | | 9/25/2019 | | PASS |
Josh Wilson
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/25/2019 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 9/25/2019 | | DONE |
|
|
|
BLD19-01469 AND 03318 - 03319
|
Routing - PLAN CHECK | 9/19/2019 | | 9/24/2019 | | PASS |
Julie Romig
|
|
|
4th Review
|
Routing Off Site - STRUCTURAL | 9/19/2019 | | 9/24/2019 | | PASS |
Julie Romig
|
|
|
Jacobs - 4th Review
|
Routing - PLUMBING | 9/19/2019 | | 9/19/2019 | | PASS |
Daryl Spivey
|
|
|
Per plan and ISPC.
|
Routing - MECHANICAL | 9/19/2019 | | 9/19/2019 | | PASS |
Troy James
|
|
|
|
Routing Off Site - STRUCTURAL | 8/21/2019 | | 9/16/2019 | | FAIL |
Julie Romig
|
|
|
Jacobs
|
Routing - PLAN CHECK | 8/21/2019 | | 9/6/2019 | | FAIL |
Julie Romig
|
|
|
|
Routing PW Drainage | 8/21/2019 | | 9/6/2019 | | PASS |
Brian Murphy
|
|
|
|
Routing - FIRE | 8/21/2019 | 8/21/2019 | 8/28/2019 | | PASS |
Erika Akin
|
|
|
Attached revised comments to case
|
Routing PW Street Lights | 8/28/2019 | | 8/28/2019 | | PASS |
Tom Marshall
|
|
|
|
Routing - Design Review | 8/21/2019 | | 8/26/2019 | | FAIL |
Josh Wilson
|
|
|
Still need recorded ACHD air rights agreement
|
Routing PW Street Lights | 8/21/2019 | | 8/23/2019 | | FAIL |
Tom Marshall
|
|
|
|
Routing - FIRE | 7/18/2019 | 7/18/2019 | 8/6/2019 | | FAIL |
Erika Akin
|
|
|
Attached comments to case and emailed architect
|
Routing - PLAN CHECK | 7/18/2019 | | 8/6/2019 | | FAIL |
Julie Romig
|
|
|
|
Routing Off Site - STRUCTURAL | 7/18/2019 | | 8/2/2019 | | FAIL |
Julie Romig
|
|
|
Jacobs - 2nd Rev
|
Routing - MECHANICAL | 7/22/2019 | | 7/22/2019 | | PASS |
Troy James
|
|
|
|
Routing - Design Review | 7/18/2019 | | 7/19/2019 | | FAIL |
Josh Wilson
|
|
|
Changemarks A1.00 and A1.03
|
Routing PW Street Lights | 7/18/2019 | | 7/18/2019 | | FAIL |
Tom Marshall
|
|
|
|
Routing PW Sewer Design | 7/18/2019 | | 7/18/2019 | | PASS |
DeAnn Brown
|
|
|
|
Route to Impact Fee Review | 6/13/2019 | 6/16/2019 | 6/14/2019 | | PASS |
Eric Bilimoria
|
|
|
Review requested for Commercial Permit
|
Routing - FIRE | 5/6/2019 | 5/7/2019 | 6/13/2019 | | FAIL |
Erika Akin
|
|
|
Attached comments to case and emailed architect
|
1st review completed | | | 6/13/2019 | | FAIL |
Julie Romig
|
|
|
|
Routing - PLAN CHECK | 5/6/2019 | | 6/12/2019 | | FAIL |
Julie Romig
|
|
|
|
Routing PW Environmental | 5/7/2019 | | 5/23/2019 | | PASS |
Terry Alber
|
|
|
Food service restricted to East Corner retail space to correspond with location of grease abatement. Interior garage drains routed to sewer is approved design.
|
Routing Off Site - STRUCTURAL | 5/7/2019 | | 5/21/2019 | | FAIL |
Julie Romig
|
|
|
Jacobs Engineering
|
Routing - MECHANICAL | 5/6/2019 | | 5/15/2019 | | FAIL |
Troy James
|
|
|
|
Routing - PLUMBING | 5/6/2019 | | 5/15/2019 | | PASS |
Daryl Spivey
|
|
|
See redline remarks. Install per plan and ISPC
|
Routing - Design Review | 5/6/2019 | | 5/15/2019 | | FAIL |
Josh Wilson
|
|
|
1. Submit documentation from Idaho Power that building separation from overhead power lines is acceptable.
2. Provide air rights agreement with ACHD for portion of building in right of way
3. Provide evidence of ITD approval for design of alley exit and show alley as one-way southbound
|
Routing PW Drainage | 5/7/2019 | | 5/14/2019 | | FAIL |
Brian Murphy
|
|
|
need c-33 sand, apedex J, 10 FROM STRUCTURE OR LETTER
|
Routing PW Solid Waste | 5/7/2019 | | 5/14/2019 | | PASS |
Evan Carpenter
|
|
|
Containers to be placed in alley by buidling staff for collection.
|
Routing PW Sewer Design | 5/7/2019 | | 5/10/2019 | | FAIL |
DeAnn Brown
|
|
|
See changemarks on sheet C1.02.
|
Routing PW Street Lights | 5/7/2019 | | 5/9/2019 | | FAIL |
Tom Marshall
|
|
|
|
Routing PW Geothermal | 5/7/2019 | | 5/9/2019 | | PASS |
Javier Guzman
|
|
|
Contact Public Works to coordinate geothermal service connection. (Jon Gunnerson @ ###-####)
|
Routing - Addressing | 5/6/2019 | | 5/8/2019 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 5/6/2019 | | 5/7/2019 | | PASS |
Angela Hardy
|
|
|
|
Routing - Erosion and Sediment | 5/6/2019 | | 5/7/2019 | | PASS |
Michael Zawacki
|
|
|
Site prep inspection required. If dewatering needed for garage or foundation seperate approved dewatering plan required.
|
Intake Approval | | | 5/7/2019 | | PASS |
Joe Bruce
|
|
|
Prescreen approved and fees paid 05/06/19
|
Routing - PLANNING | 5/6/2019 | | 5/7/2019 | | PASS |
Cody Riddle
|
|
|
Final design and construction per DRH.
|
Application received | | | 4/30/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Apr 30 2019 12:02PM
|
Routing PW Drainage | 7/18/2019 | | | | FAIL |
Brian Murphy
|
|
|
need steve hubble om cost agreement
|
Routing - PLUMBING | 7/18/2019 | | | | |
|
|
|
|