BLD-Concrete | 8/12/2020 | 8/12/2020 | 8/12/2020 | P | DEFR |
Jim Storey
|
|
|
MIDDLE SECTION OF SOUTH SIDE APARTMENTS SOG AND THICKENED SLAB POUR. Phone #: ###-#### Inspection requested via web by Garrett Camp// to dave
|
FIRE-Conference | 8/6/2020 | 8/6/2020 | 8/6/2020 | A | DONE |
Jim Page
|
|
|
Temporary standpipe has been installed, FDC hook-up is on the north side of the building, signage to be placed on the fence as discussed.
|
BLD-Framing/Rough-in | 7/27/2020 | 7/28/2020 | 8/4/2020 | A | PART |
Dave Hannah
|
|
|
SHEAR WALL NAILING AND SHEATHING Phone #: ###-#### Inspection requested via web by Garrett Camp
|
BLD-Foundation | 7/30/2020 | 7/31/2020 | 8/4/2020 | A | PEND |
Dave Hannah
|
|
|
STEM WALL POUR @ jmh LAST OF MIDDLE SECTION APARTMENTS. Phone #: ###-#### Inspection requested via web by Garrett Camp ok after spec inspection sign off
|
BLD-Framing/Rough-in | 8/3/2020 | 8/3/2020 | 8/4/2020 | P | PART |
Dave Hannah
|
|
|
Insulation corridors level 3 and 4 in area A. Area separation wall area B-C Perimeter framing with hopes of starting some top down insulation and drywall on exterior 2 hour wall Phone #: ###-#### Inspection requested via web by Jim Williams ok to rock lids in corridors
|
BLD-Foundation | 7/27/2020 | 7/28/2020 | 7/28/2020 | A | PART |
Dave Hannah
|
|
|
STEM WALLS @ MIDDLE SECTION JOG OUT OF APARTMENTS. Phone #: ###-#### Inspection requested via web by Garrett Camp
|
BLD-Framing/Rough-in | 7/23/2020 | 7/23/2020 | 7/23/2020 | P | PART |
Dave Hannah
|
|
|
Ceiling concealed space insulation. Phone #: ###-#### Inspection requested via web by Jim Williams level 1 and 2 section a ok
|
BLD-Footing | 7/21/2020 | 7/22/2020 | 7/22/2020 | A | PART |
Mike Jordan
|
|
|
MIDDLE SOUTH SIDE OF APARTMENTS - CONTINUOUS FTGS @ 10AM. Phone #: ###-#### Inspection requested via web by Garrett Camp. ok pending special inspection.
|
BLD-Foundation | 7/15/2020 | 7/16/2020 | 7/17/2020 | A | PART |
Dave Hannah
|
|
|
STEM WALLS @ CLUBHOUSE. CONCRETE @ 11 AM Phone #: ###-#### Inspection requested via web by Garrett Camp ok after spec inspection oks
|
BLD-Framing/Rough-in | 7/13/2020 | 7/14/2020 | 7/14/2020 | P | PART |
Dave Hannah
|
|
|
Corridor joist for pre-sheet rock installation. levels 1-3 Area A Phone #: ###-#### Inspection requested via web by Jim Williams
|
BLD-Footing | 7/9/2020 | 7/10/2020 | 7/10/2020 | A | DEFR |
Mike Jordan
|
|
|
POURING CONTINUOUS FOOTINGS @ CLUBHOUSE. Phone #: ###-#### Inspection requested via web by Garrett Camp. Ok pending special inspection.
|
BLD-Footing | 7/7/2020 | 7/8/2020 | 7/8/2020 | A | PASS |
Jim Storey
|
|
|
SPOT FOOTINGS UNDER CLUBHOUSE - POUR IS @ 11:30AM Phone #: ###-#### Inspection requested via web by Garrett Camp pending si report
|
BLD-Framing/Rough-in | 7/1/2020 | 7/2/2020 | 7/2/2020 | A | PEND |
Dave Hannah
|
|
|
Need to meet and go over shear wall/fire wall construction of specific area in apartments and how to get inspected. Please call Garrett (###-####). Phone #: ###-#### Inspection requested via web by Garrett Camp
|
BLD-Conference | 6/22/2020 | 6/24/2020 | 6/25/2020 | P | DONE |
Dave Hannah
|
|
|
Meeting to discuss fire stopping. Larry Van-sickle with Idaho Barriers would like to be present. Hopefully right after lunch at 1 pm ish will work for you.
Thanks Phone #: ###-#### Inspection requested via web by Jim Williams
|
BLD-Concrete | 6/1/2020 | 6/1/2020 | 6/2/2020 | P | PART |
Dave Hannah
|
|
|
SOG APARTMENTS - EAST SIDE OF GARAGE FROM NORTH CORNER TO SOUTH CORNER. Phone #: ###-#### Inspection requested via web by Garrett Camp
|
BLD-Conference | 5/12/2020 | 5/13/2020 | 5/13/2020 | A | DONE |
Dave Hannah
|
|
|
Framing review and phasing discussion. Phone #: ###-#### Inspection requested via web by Jim Williams
|
BLD-Foundation | 5/5/2020 | 5/6/2020 | 5/6/2020 | P | PEND |
Dave Hannah
|
|
|
EAST SIDE STEM WALLS FROM NORTH FACE OF GARAGE TO SOUTH FACE OF GARAGE (BETWEEN GRIDS C AND G). ALSO, SOG POUR AREA EAST OF LEASING OFFICE (BETWEEN GRIDS 3.7 AND 2.5. Phone #: ###-#### Inspection requested via web by Garrett Camp ok after spec inspection sign offs
|
BLD-Concrete | 4/29/2020 | 4/29/2020 | 4/30/2020 | P | PASS |
Dave Hannah
|
|
|
SLAB ON GRADE @ LEASING OFFICE OF APARTMENTS - NORTH SIDE. 30+ YARDS. Phone #: ###-#### Inspection requested via web by Garrett Camp
|
BLD-Foundation | 4/17/2020 | 4/21/2020 | 4/21/2020 | A | PASS |
Dave Hannah
|
|
|
Area B stem walls. MTI is scheduled. 2 pm concrete. Phone #: ###-#### Inspection requested via web by Jim Williams
|
BLD-Footing | 4/13/2020 | 4/14/2020 | 4/14/2020 | A | PEND |
Dave Hannah
|
|
|
NORTH SITE FOOTINGS UNDER LEASING OFFICES AND NW APARTMENTS. Phone #: ###-#### Inspection requested via web by Garrett Camp ok after spec inspection sign off
|
BLD-Footing | 3/31/2020 | 3/31/2020 | 4/6/2020 | P | DONE |
Dave Hannah
|
|
|
NW EXTERIOR CONTINUOUS FOOTINGS AND SPOT FOOTINGS FOR APARTMENTS BETWEEN GRIDS 6.5 AND 5; B TO D. Phone #: ###-#### Inspection requested via web by Garrett Camp
|
BLD-Concrete | 3/26/2020 | 3/26/2020 | 3/31/2020 | P | PART |
Dave Hannah
|
|
|
Slab on Grade @ NW quadrant of apartments. Includes interior continuous footings (thickened slab). Phone #: ###-#### Inspection requested via web by Garrett Camp
|
BLD-Footing | 3/19/2020 | 3/19/2020 | 3/19/2020 | P | PEND |
Dave Hannah
|
|
|
Footing reinforcement for thicken slab. slab on grade pour. MTI is scheduled for a 4 am tomorrow pour. Phone #: ###-#### Inspection requested via web by Jim Williams ok after spec inspection sign offs
|
BLD-Concrete | 3/19/2020 | 3/19/2020 | 3/19/2020 | P | PEND |
Dave Hannah
|
|
|
INTERIOR CONTINUOUS FOOTINGS AND SOG FOR APARTMENTS - SW QUADRANT. Phone #: ###-#### Inspection requested via web by Garrett Camp ok after spec inspection sign offs
|
BLD-Concrete | 3/6/2020 | 3/6/2020 | 3/6/2020 | P | PART |
Tell Riley
|
|
|
STEM WALLS @ SW CORNER OF APARTMENTS (NEXT TO SW CORNER OF PARKING GARAGE) Phone #: ###-#### Inspection requested via web by Garrett Camp//ok pendspecials//
|
BLD-Foundation | 2/28/2020 | 3/2/2020 | 3/2/2020 | A | PEND |
Dave Hannah
|
|
|
Area B perimeter foundations Phone #: ###-#### Inspection requested via web by Jim Williams ok after spec inpection sign off
|
BLD-Concrete | 3/2/2020 | 3/2/2020 | 3/2/2020 | P | CANC |
Dave Hannah
|
|
|
STEM WALLS @ NW QUADRANT OF APARTMENTS Phone #: ###-#### >> Inspection requested via web by Garrett Camp Inspection cancelled from web by: Garrett Camp
|
BLD-Footing | 11/18/2019 | 11/18/2019 | 11/18/2019 | P | PASS |
Dave Hannah
|
|
|
Phone #: ###-#### Inspection requested via web by Jim Williams
|
BLD-Footing | 11/12/2019 | 11/12/2019 | 11/14/2019 | P | PART |
Dave Hannah
|
|
|
Phone #: ###-#### Inspection requested via web by Jim Williams ok inspected using spe. insp.
|
Print Occupancy Form | | | 11/5/2019 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 11/5/2019 | | DONE |
|
|
|
|
BLD-Conference | 11/1/2019 | 11/1/2019 | 11/4/2019 | P | PASS |
Dave Hannah
|
|
|
Possible ground work being done without permit issued, call about drilling and hole filling up with oil only grading site
|
Telephone call | | | 11/4/2019 | | DONE |
|
|
|
sent an email to kim informing this permit is expired and that she may send in a request for an extension
|
Plan assigned to (CJW) | 6/3/2019 | 7/12/2019 | 10/31/2019 | | PASS |
Carl Westfall
|
|
|
(1st done) 07/05/19 (New Building - 25 days) (eplan - 330 sheets) Park Place Apartment Building (issue after footing permit)
|
Plan Reviewer's activity | | | 10/31/2019 | | PASS |
|
|
|
This permit was held up until after the footing and foundation permit was approved (BLD19-03918).
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/31/2019 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 10/31/2019 | | DONE |
|
|
|
MET WESTON@GARDNERCOMPANY.NET
**DO NOT ISSUE WITHOUT BLD19-01478**
NEED
RP
MET
GC Form (walk in blh 11-5-19)
Revised Value
ACHD
|
Routing - PLANNING | 10/11/2019 | | 10/15/2019 | | PASS |
David Moser
|
|
|
|
Routing PW Street Lights | 10/11/2019 | | 10/14/2019 | | PASS |
Tom Marshall
|
|
|
|
Routing - PLAN CHECK | 10/11/2019 | | 10/14/2019 | | PASS |
Carl Westfall
|
|
|
|
Plan resubmittals received | | | 10/11/2019 | | DONE |
|
|
|
|
Plan resubmittals requested | | | 10/8/2019 | | DONE |
|
|
|
|
Routing - FIRE | 9/24/2019 | 9/24/2019 | 10/7/2019 | | PASS |
Erika Akin
|
|
|
Attached comments to case BLD19-01478
|
Routing Off Site - STRUCTURAL | 9/24/2019 | | 10/4/2019 | | PASS |
Carl Westfall
|
|
|
Jared Bauder (Jacobs - CH2MHill)
|
Routing - PLAN CHECK | 9/19/2019 | | 10/2/2019 | | PASS |
Carl Westfall
|
|
|
Pending structural
|
Routing - Design Review | 9/24/2019 | | 10/2/2019 | | PASS |
Josh Wilson
|
|
|
|
Routing - PLUMBING | 9/24/2019 | | 9/30/2019 | | PASS |
Dan Ediger
|
|
|
|
Routing - MECHANICAL | 9/24/2019 | | 9/26/2019 | | PASS |
Troy James
|
|
|
|
Routing PW Street Lights | 9/24/2019 | | 9/25/2019 | | FAIL |
Tom Marshall
|
|
|
|
Routing - PLANNING | 9/24/2019 | | 9/24/2019 | | FAIL |
David Moser
|
|
|
|
Routing - PLAN CHECK | 9/19/2019 | | 9/24/2019 | | FAIL |
Carl Westfall
|
|
|
Delay in routing due to improperly uploaded drawings
|
Plan resubmittals received | | | 9/19/2019 | | DONE |
|
|
|
|
Routing - FIRE | 8/17/2019 | 8/17/2019 | 9/10/2019 | | FAIL |
Erika Akin
|
|
|
Attached comments to case and emailed architect
|
Plan resubmittals requested | | | 9/10/2019 | | DONE |
|
|
|
|
Routing Off Site - STRUCTURAL | 8/17/2019 | | 9/5/2019 | | FAIL |
Carl Westfall
|
|
|
Jared Bauder (Jacobs - CH2MHill)
|
Routing - PLAN CHECK | 8/14/2019 | | 8/28/2019 | | FAIL |
Carl Westfall
|
|
|
|
Routing - Design Review | 8/17/2019 | | 8/23/2019 | | FAIL |
Josh Wilson
|
|
|
DR Modification not approved yet (DRH19-00362)
|
Routing - Addressing | 8/17/2019 | | 8/21/2019 | | PASS |
Doug Chausow
|
|
|
|
Routing PW Drainage | 8/17/2019 | | 8/21/2019 | | PASS |
Brian Murphy
|
|
|
|
Routing - PLUMBING | 8/17/2019 | | 8/20/2019 | | FAIL |
Dan Ediger
|
|
|
|
Routing PW Street Lights | 8/17/2019 | | 8/20/2019 | | FAIL |
Tom Marshall
|
|
|
|
Routing - PLANNING | 8/17/2019 | | 8/20/2019 | | FAIL |
David Moser
|
|
|
|
Routing - MECHANICAL | 8/17/2019 | | 8/19/2019 | | PASS |
Troy James
|
|
|
|
Plan resubmittals received | | | 8/14/2019 | | DONE |
|
|
|
|
Route to Impact Fee Review | 7/27/2019 | 7/30/2019 | 7/30/2019 | | PASS |
Eric Bilimoria
|
|
|
Review requested for Commercial Permit
|
Routing - PLAN CHECK | 6/3/2019 | | 7/27/2019 | | FAIL |
Carl Westfall
|
|
|
Revised drawings required
|
1st review completed | | | 7/27/2019 | | DONE |
|
|
|
|
Plan resubmittals requested | | | 7/27/2019 | | DONE |
|
|
|
|
Routing - FIRE | 6/3/2019 | 6/3/2019 | 7/11/2019 | | FAIL |
Erika Akin
|
|
|
Attached comments to case BLD19-01478
|
Routing Off Site - STRUCTURAL | 6/3/2019 | | 6/14/2019 | | FAIL |
Carl Westfall
|
|
|
Jared Bauder (Jacobs - CH2MHill)
|
Routing PW Drainage | 6/4/2019 | | 6/11/2019 | | FAIL |
Brian Murphy
|
|
|
|
Routing PW Flood Plain | 6/4/2019 | | 6/10/2019 | | PASS |
Jason C. Taylor
|
|
|
Project is outside Special Flood Hazard Area, no floodplain review required. If you have any questions, please call Jason Taylor at ###-####.
|
Routing - MECHANICAL | 6/3/2019 | | 6/6/2019 | | FAIL |
Troy James
|
|
|
|
Routing - PLUMBING | 6/3/2019 | | 6/5/2019 | | FAIL |
Dan Ediger
|
|
|
Sizing and Calcs per ISPC
|
Routing - PLANNING | 6/3/2019 | | 6/5/2019 | | FAIL |
David Moser
|
|
|
|
Routing - Addressing | 6/3/2019 | | 6/5/2019 | | FAIL |
Doug Chausow
|
|
|
Provide separate floor plans for floors 4 and 5 (currently combined onto one sheet) with unit numbers.
|
Routing PW Solid Waste | 6/4/2019 | | 6/5/2019 | | PASS |
Peter J. McCullough
|
|
|
|
Routing PW Street Lights | 6/4/2019 | | 6/5/2019 | | FAIL |
Tom Marshall
|
|
|
|
Routing - Erosion and Sediment | 6/3/2019 | | 6/5/2019 | | PASS |
Michael Zawacki
|
|
|
Please refer to ESC19-00542 issued with grading permit as main site permit.
|
Routing PW Sewer Design | 6/4/2019 | | 6/4/2019 | | PASS |
DeAnn Brown
|
|
|
|
Routing - PUBLIC WORKS | 6/3/2019 | | 6/4/2019 | | PASS |
Angela Hardy
|
|
|
|
Routing - Design Review | 6/3/2019 | | 6/3/2019 | | FAIL |
Josh Wilson
|
|
|
|
Intake Approval | | | 6/3/2019 | | PASS |
Carl Westfall
|
|
|
Prescreen approved/fees paid 6-3-19
|
Application received | | | 4/30/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Apr 30 2019 4:24PM
|
BLD-Concrete | 8/12/2020 | 8/13/2020 | | A | |
Dave Hannah
|
|
|
AND THICKENED SLAB POUR. Phone #: ###-#### Inspection requested via web by Garrett Camp added after cut off time.
|
BLD-Framing/Rough-in | 8/11/2020 | 8/11/2020 | | A | |
Dave Hannah
|
|
|
Shear wall nailing for top down drywall in corridors to ceiling level. This excludes wall next to garage CMU walls intil plan modification is approved. Thanks Phone #: ###-#### >> Inspection requested via web by Jim Williams
|