Permit Information
Permit NumberBLD19-01479
StatusIssued
Name OKLAND CONSTRUCTION CO INC
Site Address 749 E PARK BLVD
Project NamePark Place Apartments - Bldg 2
Customer NumberEPLAN BLD19-01478
ePlanReviewNo
Description
(2 PERMITS IN EPLAN UNDER BLD19-01478) (PARK PLACE APARTMENTS - APARTMENT BUILDING - NEW BUILDING) (PROJECT MANAGEMENT - ANGIE BROSIOUS) (DRH19-00093) (CFH19-00029) (8-12-20 FORMERLY, AN IMAGINARY PROPERTY LINE WAS CONSIDERED BETWEEN THE GARAGE BUILDING AND THE APARTMENT BUILDING. THE BEARING WALLS OF THE APARTMENT BUILDING NEXT TO THE IMAGINARY PROPERTY LINE WERE REQUIRED TO BE CONSTRUCTED OF FIRE-RETARDANT-TREATED WOOD AND TO HAVE A 2-HR FIRE-RESISTANCE-RATING WITH FIRE EXPOSURE FROM EACH SIDE. THE APARTMENT WALLS NEXT TO THE IMAGINARY PROPERTY LINE WERE NOT CONSTRUCTED THAT WAY. THIS PLAN MODIFICATION TO CHANGE THE MASONRY WALLS BETWEEN THE GARAGE AND THE APARTMENT BUILDING TO A 3-HR FIRE-RESISTANCE-RATED FIRE WALL. ACCORDING TO THE PROJECT STRUCTURAL ENGINEER, THE POST-TENSIONED CONCRETE SLABS THAT WILL SUPPORT THE 3-HR FIRE WALLS HAVE A 3-HR FIRE-RESISTANCE-RATING. THE FIRE WALL IS REQUIRED TO EXTEND AT LEAST 30 INCHES ABOVE THE HIGHEST PARKING GARAGE FLOOR WITH THE WALL OF THE APARTMENT BUILDING RATED FOR AT LEAST 1-HR FROM BOTH SIDES ABOVE THAT AS AN INTERIOR BEARING WALL EXPOSED TO THE WEATHER. ETC. The fire sprinkler system is used for building area increase, for story increase, for occupancy, for code alternate, and for fire flow and is required to comply with NFPA 13 as a wet system. To construct a residential apartment building having a total floor area of about 262,198 square feet (52,555 square feet 1st story, 52,482 square feet 2nd story, 52,387 square feet 3rd story, 52,387 square feet 4th story, and 52,387 square feet 5th story) and having a total of 237 residential dwelling units. This building wraps entirely around a parking garage constructed under permit BLD19-01478. All dwelling units are required to comply as Type B dwelling units with at least 5 units also required to comply as Type A dwelling units. Work is to include concrete footings, concrete foundations, concrete slabs on grade, interior concrete ramps on grade, exterior concrete ramp on grade, 1-hr interior wood stud bearing walls, 2-hr exterior walls with fire-retardant-treated wood studs and sheathing, 2-hr stairway enclosures, 3-hr fire walls, 2-hr exit passageways, 1-hr corridors, 1-hr floor-ceiling assemblies and 1-hr roof-ceiling assemblies with wood trusses and wood sheathing, an open stairway with steel cable guards, fiber cement siding, brick veneer, stucco, exterior windows, metal awnings, and a membrane roof covering. Minimum R-25 insulation will be installed on top of the roof decks. Blown-in insulation will be installed to entirely fill the concealed combustible spaces within roofs and floors to avoid fire sprinklers being required within those spaces. Work related to the wood decks and boardwalks over retention ponds at grade include concrete footings, concrete retaining and support walls, steel piles, steel beams, wood joists, wood decking, and steel cable guards. Special Inspection is required for soils, concrete, fire stopping, fire resistance, EIFS, seismic resistance, wind resistance, wood diaphragms, metal plate connected wood trusses, and steel construction (including bolting and welding). Footings located near stormwater swales are required to be located far enough away from the stormwater swales and to be located deep enough so that the ability of the footings to support the design loads within the design settlement limits is not affected by water in the stormwater swales. A separate permit is required for the swimming pool. The work is required to comply with the approved drawings, with the structural design, with the plan review report, and with all applicable codes and ordinances. The fire sprinkler system is required to comply with NFPA 13 and the fire alarm system is required to comply with NFPA 72 as regulated by the Fire Department. Separate fire sprinkler permits and fire alarm permits shall be obtained prior to beginning any modification or installation work on such systems. **CJW**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Concrete8/12/20208/12/20208/12/2020PDEFR
DetailsJim Storey
MIDDLE SECTION OF SOUTH SIDE APARTMENTS SOG AND THICKENED SLAB POUR. Phone #: ###-#### Inspection requested via web by Garrett Camp// to dave
FIRE-Conference8/6/20208/6/20208/6/2020ADONE
DetailsJim Page
Temporary standpipe has been installed, FDC hook-up is on the north side of the building, signage to be placed on the fence as discussed.
BLD-Framing/Rough-in7/27/20207/28/20208/4/2020APART
DetailsDave Hannah
SHEAR WALL NAILING AND SHEATHING Phone #: ###-#### Inspection requested via web by Garrett Camp
BLD-Foundation7/30/20207/31/20208/4/2020APEND
DetailsDave Hannah
STEM WALL POUR @ jmh LAST OF MIDDLE SECTION APARTMENTS. Phone #: ###-#### Inspection requested via web by Garrett Camp ok after spec inspection sign off
BLD-Framing/Rough-in8/3/20208/3/20208/4/2020PPART
DetailsDave Hannah
Insulation corridors level 3 and 4 in area A. Area separation wall area B-C Perimeter framing with hopes of starting some top down insulation and drywall on exterior 2 hour wall Phone #: ###-#### Inspection requested via web by Jim Williams ok to rock lids in corridors
BLD-Foundation7/27/20207/28/20207/28/2020APART
DetailsDave Hannah
STEM WALLS @ MIDDLE SECTION JOG OUT OF APARTMENTS. Phone #: ###-#### Inspection requested via web by Garrett Camp
BLD-Framing/Rough-in7/23/20207/23/20207/23/2020PPART
DetailsDave Hannah
Ceiling concealed space insulation. Phone #: ###-#### Inspection requested via web by Jim Williams level 1 and 2 section a ok
BLD-Footing7/21/20207/22/20207/22/2020APART
DetailsMike Jordan
MIDDLE SOUTH SIDE OF APARTMENTS - CONTINUOUS FTGS @ 10AM. Phone #: ###-#### Inspection requested via web by Garrett Camp. ok pending special inspection.
BLD-Foundation7/15/20207/16/20207/17/2020APART
DetailsDave Hannah
STEM WALLS @ CLUBHOUSE. CONCRETE @ 11 AM Phone #: ###-#### Inspection requested via web by Garrett Camp ok after spec inspection oks
BLD-Framing/Rough-in7/13/20207/14/20207/14/2020PPART
DetailsDave Hannah
Corridor joist for pre-sheet rock installation. levels 1-3 Area A Phone #: ###-#### Inspection requested via web by Jim Williams
BLD-Footing7/9/20207/10/20207/10/2020ADEFR
DetailsMike Jordan
POURING CONTINUOUS FOOTINGS @ CLUBHOUSE. Phone #: ###-#### Inspection requested via web by Garrett Camp. Ok pending special inspection.
BLD-Footing7/7/20207/8/20207/8/2020APASS
DetailsJim Storey
SPOT FOOTINGS UNDER CLUBHOUSE - POUR IS @ 11:30AM Phone #: ###-#### Inspection requested via web by Garrett Camp pending si report
BLD-Framing/Rough-in7/1/20207/2/20207/2/2020APEND
DetailsDave Hannah
Need to meet and go over shear wall/fire wall construction of specific area in apartments and how to get inspected. Please call Garrett (###-####). Phone #: ###-#### Inspection requested via web by Garrett Camp
BLD-Conference6/22/20206/24/20206/25/2020PDONE
DetailsDave Hannah
Meeting to discuss fire stopping. Larry Van-sickle with Idaho Barriers would like to be present. Hopefully right after lunch at 1 pm ish will work for you.

Thanks Phone #: ###-#### Inspection requested via web by Jim Williams
BLD-Concrete6/1/20206/1/20206/2/2020PPART
DetailsDave Hannah
SOG APARTMENTS - EAST SIDE OF GARAGE FROM NORTH CORNER TO SOUTH CORNER. Phone #: ###-#### Inspection requested via web by Garrett Camp
BLD-Conference5/12/20205/13/20205/13/2020ADONE
DetailsDave Hannah
Framing review and phasing discussion. Phone #: ###-#### Inspection requested via web by Jim Williams
BLD-Foundation5/5/20205/6/20205/6/2020PPEND
DetailsDave Hannah
EAST SIDE STEM WALLS FROM NORTH FACE OF GARAGE TO SOUTH FACE OF GARAGE (BETWEEN GRIDS C AND G). ALSO, SOG POUR AREA EAST OF LEASING OFFICE (BETWEEN GRIDS 3.7 AND 2.5. Phone #: ###-#### Inspection requested via web by Garrett Camp ok after spec inspection sign offs
BLD-Concrete4/29/20204/29/20204/30/2020PPASS
DetailsDave Hannah
SLAB ON GRADE @ LEASING OFFICE OF APARTMENTS - NORTH SIDE. 30+ YARDS. Phone #: ###-#### Inspection requested via web by Garrett Camp
BLD-Foundation4/17/20204/21/20204/21/2020APASS
DetailsDave Hannah
Area B stem walls. MTI is scheduled. 2 pm concrete. Phone #: ###-#### Inspection requested via web by Jim Williams
BLD-Footing4/13/20204/14/20204/14/2020APEND
DetailsDave Hannah
NORTH SITE FOOTINGS UNDER LEASING OFFICES AND NW APARTMENTS. Phone #: ###-#### Inspection requested via web by Garrett Camp ok after spec inspection sign off
BLD-Footing3/31/20203/31/20204/6/2020PDONE
DetailsDave Hannah
NW EXTERIOR CONTINUOUS FOOTINGS AND SPOT FOOTINGS FOR APARTMENTS BETWEEN GRIDS 6.5 AND 5; B TO D. Phone #: ###-#### Inspection requested via web by Garrett Camp
BLD-Concrete3/26/20203/26/20203/31/2020PPART
DetailsDave Hannah
Slab on Grade @ NW quadrant of apartments. Includes interior continuous footings (thickened slab). Phone #: ###-#### Inspection requested via web by Garrett Camp
BLD-Footing3/19/20203/19/20203/19/2020PPEND
DetailsDave Hannah
Footing reinforcement for thicken slab. slab on grade pour. MTI is scheduled for a 4 am tomorrow pour. Phone #: ###-#### Inspection requested via web by Jim Williams ok after spec inspection sign offs
BLD-Concrete3/19/20203/19/20203/19/2020PPEND
DetailsDave Hannah
INTERIOR CONTINUOUS FOOTINGS AND SOG FOR APARTMENTS - SW QUADRANT. Phone #: ###-#### Inspection requested via web by Garrett Camp ok after spec inspection sign offs
BLD-Concrete3/6/20203/6/20203/6/2020PPART
DetailsTell Riley
STEM WALLS @ SW CORNER OF APARTMENTS (NEXT TO SW CORNER OF PARKING GARAGE) Phone #: ###-#### Inspection requested via web by Garrett Camp//ok pendspecials//
BLD-Foundation2/28/20203/2/20203/2/2020APEND
DetailsDave Hannah
Area B perimeter foundations Phone #: ###-#### Inspection requested via web by Jim Williams ok after spec inpection sign off
BLD-Concrete3/2/20203/2/20203/2/2020PCANC
DetailsDave Hannah
STEM WALLS @ NW QUADRANT OF APARTMENTS Phone #: ###-#### >> Inspection requested via web by Garrett Camp Inspection cancelled from web by: Garrett Camp
BLD-Footing11/18/201911/18/201911/18/2019PPASS
DetailsDave Hannah
Phone #: ###-#### Inspection requested via web by Jim Williams
BLD-Footing11/12/201911/12/201911/14/2019PPART
DetailsDave Hannah
Phone #: ###-#### Inspection requested via web by Jim Williams ok inspected using spe. insp.
Print Occupancy Form  11/5/2019 DONE
Issue PAID IN FULL permit  11/5/2019 DONE
BLD-Conference11/1/201911/1/201911/4/2019PPASS
DetailsDave Hannah
Possible ground work being done without permit issued, call about drilling and hole filling up with oil only grading site
Telephone call  11/4/2019 DONE
sent an email to kim informing this permit is expired and that she may send in a request for an extension
Plan assigned to (CJW)6/3/20197/12/201910/31/2019 PASS
DetailsCarl Westfall
(1st done) 07/05/19 (New Building - 25 days) (eplan - 330 sheets) Park Place Apartment Building (issue after footing permit)
Plan Reviewer's activity  10/31/2019 PASS
This permit was held up until after the footing and foundation permit was approved (BLD19-03918).
PLANS/APPL TAKEN TO FRONT DESK  10/31/2019 DONE
Permit Ready to Issue  10/31/2019 DONE
MET WESTON@GARDNERCOMPANY.NET
**DO NOT ISSUE WITHOUT BLD19-01478**
NEED
RP
MET
GC Form (walk in blh 11-5-19)
Revised Value
ACHD
Routing - PLANNING10/11/2019 10/15/2019 PASS
DetailsDavid Moser
Routing PW Street Lights10/11/2019 10/14/2019 PASS
DetailsTom Marshall
Routing - PLAN CHECK10/11/2019 10/14/2019 PASS
DetailsCarl Westfall
Plan resubmittals received  10/11/2019 DONE
Plan resubmittals requested  10/8/2019 DONE
Routing - FIRE9/24/20199/24/201910/7/2019 PASS
DetailsErika Akin
Attached comments to case BLD19-01478
Routing Off Site - STRUCTURAL9/24/2019 10/4/2019 PASS
DetailsCarl Westfall
Jared Bauder (Jacobs - CH2MHill)
Routing - PLAN CHECK9/19/2019 10/2/2019 PASS
DetailsCarl Westfall
Pending structural
Routing - Design Review9/24/2019 10/2/2019 PASS
DetailsJosh Wilson
Routing - PLUMBING9/24/2019 9/30/2019 PASS
DetailsDan Ediger
Routing - MECHANICAL9/24/2019 9/26/2019 PASS
DetailsTroy James
Routing PW Street Lights9/24/2019 9/25/2019 FAIL
DetailsTom Marshall
Routing - PLANNING9/24/2019 9/24/2019 FAIL
DetailsDavid Moser
Routing - PLAN CHECK9/19/2019 9/24/2019 FAIL
DetailsCarl Westfall
Delay in routing due to improperly uploaded drawings
Plan resubmittals received  9/19/2019 DONE
Routing - FIRE8/17/20198/17/20199/10/2019 FAIL
DetailsErika Akin
Attached comments to case and emailed architect
Plan resubmittals requested  9/10/2019 DONE
Routing Off Site - STRUCTURAL8/17/2019 9/5/2019 FAIL
DetailsCarl Westfall
Jared Bauder (Jacobs - CH2MHill)
Routing - PLAN CHECK8/14/2019 8/28/2019 FAIL
DetailsCarl Westfall
Routing - Design Review8/17/2019 8/23/2019 FAIL
DetailsJosh Wilson
DR Modification not approved yet (DRH19-00362)
Routing - Addressing8/17/2019 8/21/2019 PASS
DetailsDoug Chausow
Routing PW Drainage8/17/2019 8/21/2019 PASS
DetailsBrian Murphy
Routing - PLUMBING8/17/2019 8/20/2019 FAIL
DetailsDan Ediger
Routing PW Street Lights8/17/2019 8/20/2019 FAIL
DetailsTom Marshall
Routing - PLANNING8/17/2019 8/20/2019 FAIL
DetailsDavid Moser
Routing - MECHANICAL8/17/2019 8/19/2019 PASS
DetailsTroy James
Plan resubmittals received  8/14/2019 DONE
Route to Impact Fee Review7/27/20197/30/20197/30/2019 PASS
DetailsEric Bilimoria
Review requested for Commercial Permit
Routing - PLAN CHECK6/3/2019 7/27/2019 FAIL
DetailsCarl Westfall
Revised drawings required
1st review completed  7/27/2019 DONE
Plan resubmittals requested  7/27/2019 DONE
Routing - FIRE6/3/20196/3/20197/11/2019 FAIL
DetailsErika Akin
Attached comments to case BLD19-01478
Routing Off Site - STRUCTURAL6/3/2019 6/14/2019 FAIL
DetailsCarl Westfall
Jared Bauder (Jacobs - CH2MHill)
Routing PW Drainage6/4/2019 6/11/2019 FAIL
DetailsBrian Murphy
Routing PW Flood Plain6/4/2019 6/10/2019 PASS
DetailsJason C. Taylor
Project is outside Special Flood Hazard Area, no floodplain review required. If you have any questions, please call Jason Taylor at ###-####.
Routing - MECHANICAL6/3/2019 6/6/2019 FAIL
DetailsTroy James
Routing - PLUMBING6/3/2019 6/5/2019 FAIL
DetailsDan Ediger
Sizing and Calcs per ISPC
Routing - PLANNING6/3/2019 6/5/2019 FAIL
DetailsDavid Moser
Routing - Addressing6/3/2019 6/5/2019 FAIL
DetailsDoug Chausow
Provide separate floor plans for floors 4 and 5 (currently combined onto one sheet) with unit numbers.
Routing PW Solid Waste6/4/2019 6/5/2019 PASS
DetailsPeter J. McCullough
Routing PW Street Lights6/4/2019 6/5/2019 FAIL
DetailsTom Marshall
Routing - Erosion and Sediment6/3/2019 6/5/2019 PASS
DetailsMichael Zawacki
Please refer to ESC19-00542 issued with grading permit as main site permit.
Routing PW Sewer Design6/4/2019 6/4/2019 PASS
DetailsDeAnn Brown
Routing - PUBLIC WORKS6/3/2019 6/4/2019 PASS
DetailsAngela Hardy
Routing - Design Review6/3/2019 6/3/2019 FAIL
DetailsJosh Wilson
Intake Approval  6/3/2019 PASS
DetailsCarl Westfall
Prescreen approved/fees paid 6-3-19
Application received  4/30/2019 DONE
Application submitted via PDS Online on Apr 30 2019 4:24PM
BLD-Concrete8/12/20208/13/2020 A 
DetailsDave Hannah
AND THICKENED SLAB POUR. Phone #: ###-#### Inspection requested via web by Garrett Camp added after cut off time.
BLD-Framing/Rough-in8/11/20208/11/2020 A 
DetailsDave Hannah
Shear wall nailing for top down drywall in corridors to ceiling level. This excludes wall next to garage CMU walls intil plan modification is approved.
Thanks Phone #: ###-#### >> Inspection requested via web by Jim Williams