BLD-Final | 6/25/2019 | 6/26/2019 | 6/26/2019 | P | DONE |
Tony Young
|
|
|
Please call 30 minutes prior to arrival so someone can meet on site Phone #: ###-#### Inspection requested via web by Ron Smith
|
DOC - Permit Finaled | 6/26/2019 | 6/26/2019 | 6/26/2019 | P | PASS |
Tony Young
|
|
|
done
|
Issue PAID IN FULL permit | | | 6/21/2019 | | DONE |
|
|
|
|
Plan assigned to (JAB) Josh | 5/3/2019 | 5/3/2019 | 5/16/2019 | | PASS |
Josh Bogle
|
|
|
5/9 PV, ePlan - 1st done
|
Routing - PLAN CHECK | 5/16/2019 | | 5/16/2019 | | PASS |
Josh Bogle
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/16/2019 | | DONE |
Josh Bogle
|
|
|
ESC no - Energy no
|
Permit Ready to Issue | | | 5/16/2019 | | DONE |
|
|
|
met
|
Plan Reviewer's activity | | | 5/13/2019 | | DONE |
Josh Bogle
|
|
|
didn't accept resubmittal - no roof structure info provided
|
Routing - PLANNING | 5/10/2019 | | 5/10/2019 | | PASS |
Sue Cummings
|
|
|
|
Routing - PLAN CHECK | 5/10/2019 | | 5/10/2019 | | FAIL |
Josh Bogle
|
|
|
no roof structure info provided
|
Routing - PLANNING | 5/9/2019 | | 5/9/2019 | | PASS |
Katelyn Menuge
|
|
|
No Design Review Substandard Lot Review Required
|
1st review completed | | | 5/7/2019 | | FAIL |
Josh Bogle
|
|
|
|
Routing - PLAN CHECK | 5/3/2019 | | 5/7/2019 | | FAIL |
Josh Bogle
|
|
|
no review paneding Planning approval
|
Routing - PLANNING | 5/3/2019 | | 5/3/2019 | | FAIL |
Sue Cummings
|
|
|
Needs sub-standard lot approval
|
Intake Approval | | | 5/3/2019 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 5/3/2019 | | DONE |
|
|
|
|
Application received | | | 5/2/2019 | | DONE |
|
|
|
Application submitted via PDS Online on May 2 2019 4:59PM
|