BLD-Final | 3/5/2020 | 3/6/2020 | 3/6/2020 | A | PASS |
Tony Young
|
|
|
Call ahead // Kelly Phone #: ###-####.. ok after sealing firewall
|
DOC - Permit Finaled | 3/6/2020 | 3/6/2020 | 3/6/2020 | P | PASS |
Tony Young
|
|
|
|
BLD-Blower Door Test Results | 3/6/2020 | 3/6/2020 | 3/6/2020 | P | DONE |
Tony Young
|
|
|
Call ahead // Kelly Phone #: ###-####// 4.1
|
BLD-Energy code compliance | 8/16/2019 | 8/16/2019 | 8/16/2019 | P | PASS |
Tony Young
|
|
|
|
BLD-Framing/Rough-in | 8/6/2019 | 8/6/2019 | 8/6/2019 | P | PART |
Tony Young
|
|
|
Kelly Phone #: ###-####,, ok to insulate,, see corrections on needing truss engineering, fire blocking, and stair treads/ rises
|
Routing - MECHANICAL | 7/30/2019 | | 7/30/2019 | | PASS |
Troy James
|
|
|
Resubmitted manual j report
|
BLD-Wall Bracing | 7/3/2019 | 7/3/2019 | 7/3/2019 | P | PASS |
Tony Young
|
|
|
Kelly Phone #: ###-####
|
BLD-Foundation | 6/3/2019 | 6/4/2019 | 6/4/2019 | P | PART |
Tony Young
|
|
|
Willie- please go as early as possible Phone #: ###-####
|
BLD-Foundation | 6/3/2019 | 6/4/2019 | 6/4/2019 | A | PART |
Tony Young
|
|
|
Willy Phone #: ###-####
|
BLD-Footing | 6/3/2019 | 6/3/2019 | 6/3/2019 | P | PASS |
Tony Young
|
|
|
Willie- please go as early as possible Phone #: ###-####,,
|
OVERRIDE | | | 5/21/2019 | | |
|
|
|
|
Plan assigned to (RDP) | 5/3/2019 | 5/3/2019 | 5/21/2019 | | DONE |
Rob Patrick
|
|
|
05/16 sfd L1 ePlan...05/15 1st done Failed...05/17 Failed
|
Routing - PLAN CHECK | 5/21/2019 | | 5/21/2019 | | PASS |
Rob Patrick
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/21/2019 | | DONE |
Rob Patrick
|
|
|
|
Permit Ready to Issue | | | 5/21/2019 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 5/21/2019 | | DONE |
|
|
|
emailed dynamickju@yahoo.com to sign permits and send back
|
Inspection Record Card- Bld | | | 5/21/2019 | | DONE |
|
|
|
|
Routing PW Sewer Design | 5/17/2019 | | 5/20/2019 | | PASS |
DeAnn Brown
|
|
|
|
Routing - PLAN CHECK | 5/17/2019 | | 5/17/2019 | | FAIL |
Rob Patrick
|
|
|
Failed Pending Sewer Review
|
1st review completed | | | 5/15/2019 | | FAIL |
Rob Patrick
|
|
|
|
Routing - PLAN CHECK | 5/3/2019 | | 5/15/2019 | | FAIL |
Rob Patrick
|
|
|
Corrections Req'd
|
Routing - MECHANICAL | 5/3/2019 | | 5/15/2019 | | PASS |
Troy James
|
|
|
|
Routing PW Sewer Design | 5/3/2019 | | 5/10/2019 | | FAIL |
DeAnn Brown
|
|
|
New sewer service for 3209 Plant Drive must be complete.
|
Route to Impact Fee Review | 5/3/2019 | 5/6/2019 | 5/6/2019 | | PASS |
Karina Myles
|
|
|
Can not find the parcel in the GIS system, the building permit may have been assigned a temporary parcel number
|
Routing - Addressing | 5/3/2019 | | 5/6/2019 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 5/3/2019 | | 5/6/2019 | | PASS |
Angela Hardy
|
|
|
|
Application received | | | 5/3/2019 | | DONE |
|
|
|
Application submitted via PDS Online on May 3 2019 9:21AM
|
Intake Approval | | | 5/3/2019 | | FAIL |
|
|
|
need building cross section, res check has 2009 code year (needs changed), need to know the building code so asked Kelly to have his designer put it on the cross section so they only have to do one new sheet
|
Plans ACCEPTED BY PLAN TECH | | | 5/3/2019 | | DONE |
|
|
|
|
Intake Approval | | | 5/3/2019 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 5/3/2019 | | DONE |
|
|
|
|
Routing - PLANNING | 5/3/2019 | | 5/3/2019 | | PASS |
Sue Cummings
|
|
|
|