BLD-Final | 7/24/2020 | 7/24/2020 | 7/24/2020 | P | FAIL |
Brandon Shaw
|
|
|
Due to Covid-19, virtual inspection was requested, no one available...
|
FIRE-Final Inspection | 7/23/2020 | 7/24/2020 | 7/24/2020 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed. Inspection via video.
*Screened* Joe Phone #: ###-####
|
FIRE-Final Inspection | 7/20/2020 | 7/20/2020 | 7/21/2020 | P | CANC |
Troy Cobbley
|
|
|
Could no perform on site inspectio due to covid protocols so requested a video of the smoke alarms functioning by 4:00pm. Did not receive anything by 7:00am the following morning so inspection is canceled. WIll need to be rescheduled. photo ok // Joe Phone #: ###-#### or ###-#### Jack (manager)
|
Plan Reviewer's activity | | | 4/1/2020 | | DONE |
Brian McGowan
|
|
|
Updated scope of work and Tidemark Inspections. Joe still needs to get a Mechanical Inspection.
|
Print Occupancy Form | | | 4/1/2020 | | DONE |
|
|
|
|
Plan Reviewer's activity | | | 3/13/2020 | | DONE |
Brian McGowan
|
|
|
Joe Levco came in asking me to adjust the scope of work to say that there is no fire sprinkler system, only a pull fire alarm in the hallway.
I told him I would do some research and get back to him.
|
BLD-Final | 2/27/2020 | 2/28/2020 | 2/28/2020 | A | NR |
Tell Riley
|
|
|
jack Phone #: ###-####//need to update project description--no sprinklers--no alarms in unit//no smoke detectors in unit//need approved plans onsite//need fire life safety inspection and plumbing, mechanical inspections//
|
Fees Due Hold | 5/16/2019 | | 5/16/2019 | | DONE |
Tiffany Carson-Herker
|
|
|
|
Issue PAID IN FULL permit | | | 5/15/2019 | | DONE |
|
|
|
|
Print Occupancy Form | | | 5/15/2019 | | DONE |
|
|
|
|
Plan assigned to (BJM) | 5/9/2019 | 5/9/2019 | 5/14/2019 | | DONE |
Brian McGowan
|
|
|
05/14 L1 Baker Residence ePlan
|
Routing - PLAN CHECK | 5/9/2019 | | 5/14/2019 | | PASS |
Brian McGowan
|
|
|
|
1st review completed | | | 5/14/2019 | | DONE |
Brian McGowan
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/14/2019 | | DONE |
Brian McGowan
|
|
|
|
Permit Ready to Issue | | | 5/14/2019 | | DONE |
|
|
|
MET
Need GC-met
rev cert of val emailed Glenn
|
Intake Approval | | | 5/8/2019 | | PASS |
Javier Guzman
|
|
|
|
Application received | | | 5/4/2019 | | DONE |
|
|
|
Application submitted via PDS Online on May 4 2019 5:31PM
|
BLD-Final | 8/11/2020 | 8/14/2020 | | P | |
Tell Riley
|
|
|
Please call ahead 45 minutes if possible Joe - */Video Inspection Requested*/ Phone #: ###-####
|