BLD-Final | 5/21/2019 | 5/23/2019 | 5/23/2019 | P | DONE |
Mike Jordan
|
|
|
Call foreman, Brad Hallman, with any questions. Phone #: ###-#### Inspection requested via web by Rob Maes
|
DOC - Permit Finaled | 5/23/2019 | 5/23/2019 | 5/23/2019 | P | PASS |
Mike Jordan
|
|
|
|
BLD-Framing/Rough-in | 5/21/2019 | 5/22/2019 | 5/22/2019 | A | DONE |
Mike Jordan
|
|
|
Call foreman, Brad Hallman, one hour prior to arrival to coordinate access. Phone #: ###-#### Inspection requested via web by Rob Maes. It appears the 2x6 lumber was sistered to 2x8 existing top chords. per the structural engineers leter. No additional work was required to upgrade the roof.
|
Plan assigned to (JAB) Josh | 5/6/2019 | 5/6/2019 | 5/10/2019 | | PASS |
Josh Bogle
|
|
|
5/10 PV, ePlan
|
Routing - PLAN CHECK | 5/6/2019 | | 5/10/2019 | | PASS |
Josh Bogle
|
|
|
|
1st review completed | | | 5/10/2019 | | DONE |
Josh Bogle
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/10/2019 | | DONE |
Josh Bogle
|
|
|
ESC no - Energy no
|
Permit Ready to Issue | | | 5/10/2019 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 5/10/2019 | | DONE |
|
|
|
emailed idahopermits@auricsolar.com to sign permit
|
Application received | | | 5/6/2019 | | DONE |
|
|
|
Application submitted via PDS Online on May 6 2019 11:21AM
|
Plans ACCEPTED BY PLAN TECH | | | 5/6/2019 | | DONE |
|
|
|
|
Intake Approval | | | 5/6/2019 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 5/6/2019 | | DONE |
|
|
|
|
Routing - PLANNING | 5/6/2019 | | 5/6/2019 | | PASS |
Sue Cummings
|
|
|
|