Information based on query as of Tuesday, July 23, 2024.
Permit Information
Permit NumberBLD19-01569
StatusFinaled
Name B H INC
Site Address 1161 W RIVER ST
Project NameBOI BSU
Customer NumberCAA19-00070
ePlanReviewYes
Description
(VERIZON WIRELESS) Permit for the modifications to the existing roof top antenna mount assemblies with work to include; Removing six (6) existing antennas and twelve (12) RRH units. Installing six (6) new panel antennas, six (6) new RRH units and one (1) new BBU unit. No changes to the height of the assemblies and minor equipment modification to interior of existing equipment structure. Structural engineering and plans provided. ***BJM***
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final10/1/201910/2/201910/2/2019APASS
DetailsDave Hannah
Phone #: ###-#### Inspection requested via web by Josh Woodbeck
DOC - Permit Finaled10/2/201910/2/201910/2/2019PPASS
DetailsDave Hannah
Issue PAID IN FULL permit  5/21/2019 DONE
Inspection Record Card- Bld  5/21/2019 DONE
Route to Impact Fee Review5/20/20195/23/20195/20/2019 PASS
DetailsKarina Myles
Review requested for Commercial Permit
Plan assigned to (BJM)5/7/20195/7/20195/20/2019 DONE
DetailsBrian McGowan
05/16 L2 Verizon antennas ePlan (do not issue until 5-16)
1st review completed  5/20/2019 DONE
DetailsBrian McGowan
Routing - PLANNING5/20/2019 5/20/2019 PASS
DetailsSue Cummings
Routing - PLAN CHECK5/20/2019 5/20/2019 PASS
DetailsBrian McGowan
PLANS/APPL TAKEN TO FRONT DESK  5/20/2019 DONE
DetailsBrian McGowan
Permit Ready to Issue  5/20/2019 DONE
ALL MET-
NEED
GC FORM
REVISED CERT OF VALUE
Routing - FIRE5/15/20195/15/20195/17/2019 PASS
DetailsMark Scharfen
05/21 They noted a BBU to be installed with (24) Enersys batteries. Batteries are existing. BBU is interface for new antennas. No review required.
Routing - PLAN CHECK5/7/2019 5/16/2019 PASS
DetailsBrian McGowan
Routing - PLANNING5/7/2019 5/8/2019 FAIL
DetailsSue Cummings
Do not issue until May 16, as per the approval letter in the BLD file
Intake Approval  5/7/2019 PASS
DetailsJavier Guzman
Application received  5/6/2019 DONE
Application submitted via PDS Online on May 6 2019 2:11PM
First Notice10/2/201910/2/2019   
DetailsDave Hannah