BLD-Final | 3/13/2020 | 3/13/2020 | 3/13/2020 | A | PASS |
Jim Storey
|
|
|
Please call 30 minutes prior to ensure access. Thanks! Phone #: ###-#### Inspection requested via web by Eric Murphy
|
DOC - Permit Finaled | 3/13/2020 | 3/13/2020 | 3/13/2020 | P | PASS |
Jim Storey
|
|
|
|
BLD-Energy code compliance | 1/17/2020 | 1/17/2020 | 1/17/2020 | A | PASS |
Jim Storey
|
|
|
Phone #: ###-#### Inspection requested via web by Eric Murphy
|
BLD-Framing/Rough-in | 1/10/2020 | 1/10/2020 | 1/10/2020 | P | PASS |
Jim Storey
|
|
|
Please call Eric 30 minutes prior to inspection if possible. ###-#### Phone #: ###-#### Inspection requested via web by Eric Murphy
|
BLD-Framing/Rough-in | 1/3/2020 | 1/6/2020 | 1/6/2020 | A | NR |
Jim Storey
|
|
|
Please call Eric 30 minutes prior to inspection for access. Thanks! Phone #: ###-#### Inspection requested via web by Eric Murphy
|
BLD-Framing/Rough-in | 1/3/2020 | 1/3/2020 | 1/6/2020 | P | CANC |
Jim Storey
|
|
|
Please call Eric 30 minutes prior to inspection for access. Thanks! Phone #: ###-#### Inspection requested via web by Eric Murphy
|
BLD-Wall Bracing | 11/25/2019 | 11/25/2019 | 11/25/2019 | P | PASS |
Dave Hannah
|
|
|
Please call Eric 15 min before inspection so I can meet you there. If your schedule allows, framers requesting 1:00 time frame. Thanks! Phone #: ###-#### Inspection requested via web by Eric Murphy
|
BLD-Wall Bracing | 11/25/2019 | 11/25/2019 | 11/25/2019 | P | CANC |
Dave Hannah
|
|
|
Eric Phone #: ###-#### Inspection cancelled from web by: Eric Murphy
|
CHANGE STATUS TO (ISS) | | | 11/25/2019 | | DONE |
|
|
|
|
OVERRIDE | | | 11/7/2019 | | |
|
|
|
|
Permit Ready to Issue | | | 11/7/2019 | | DONE |
|
|
|
PLAN MOD
|
Plan assigned to (JAB) Josh | 10/28/2019 | 10/28/2019 | 11/6/2019 | | PASS |
Josh Bogle
|
|
|
11/06 modification, ePlan
|
Routing - PLAN CHECK | 10/31/2019 | | 11/6/2019 | | PASS |
Josh Bogle
|
|
|
1hr mod fee plus added value
|
Routing - PLANNING | 11/4/2019 | | 11/4/2019 | | PASS |
Sue Cummings
|
|
|
|
Routing - MECHANICAL | 10/31/2019 | | 11/1/2019 | | PASS |
Troy James
|
|
|
|
Plan Modification Accepted | | | 10/28/2019 | | DONE |
|
|
|
Richard from Chrysalis Architecture requesting plan modification work flow to submit changing floor system to crawl space with tji's and floor decking. Also, provide a mechanical unit and manual J.
Sheets: full resubmittal - changing square footage of garage addition.
|
BLD-Footing | 10/21/2019 | 10/21/2019 | 10/21/2019 | P | PASS |
Jim Storey
|
|
|
Chris Phone #: ###-####
|
Issue PAID IN FULL permit | | | 9/20/2019 | | DONE |
|
|
|
|
Telephone call | | | 5/30/2019 | | DONE |
|
|
|
sent email to richard and jessica on what is still needed for issuance
|
Telephone call | | | 5/30/2019 | | DONE |
|
|
|
email Jessica and Richard informing them that there is remaining fees due & that we need RP and GC
|
Plan assigned to (JAB) Josh | 5/20/2019 | 5/20/2019 | 5/29/2019 | | PASS |
Josh Bogle
|
|
|
5/24 addition, ePlan - 1st done
|
Routing - PLAN CHECK | 5/29/2019 | | 5/29/2019 | | PASS |
Josh Bogle
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/29/2019 | | DONE |
Josh Bogle
|
|
|
ESC yes - Energy yes
|
Permit Ready to Issue | | | 5/29/2019 | | DONE |
|
|
|
NEED
GC FORM
RP-met
|
Routing - PLAN CHECK | 5/20/2019 | | 5/23/2019 | | FAIL |
Josh Bogle
|
|
|
lacked pergola engineering
|
1st review completed | | | 5/23/2019 | | FAIL |
Josh Bogle
|
|
|
|
Intake Approval | | | 5/20/2019 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 5/20/2019 | | DONE |
|
|
|
no fees paid at intake
|
Routing - MECHANICAL | 5/20/2019 | | 5/20/2019 | | PASS |
Troy James
|
|
|
Wall heaters, no manual j report
|
Routing - PLANNING | 5/20/2019 | | 5/20/2019 | | PASS |
Sue Cummings
|
|
|
|
Application received | | | 5/6/2019 | | DONE |
|
|
|
Application submitted via PDS Online on May 6 2019 10:12PM
|