Letter of compliance/Occupancy | | | 10/28/2019 | | DONE |
|
|
|
|
BLD-Final | 10/24/2019 | 10/24/2019 | 10/24/2019 | A | PASS |
Jim Storey
|
|
|
garage door code is 2468 Phone #: ###-#### Inspection requested via web by Joel Hirtle no blower door test.
|
DOC - Permit Finaled | 10/24/2019 | 10/24/2019 | 10/24/2019 | P | PASS |
Jim Storey
|
|
|
|
BLD-Energy code compliance | 9/12/2019 | 9/12/2019 | 9/12/2019 | P | PASS |
Jim Storey
|
|
|
Phone #: ###-#### Inspection requested via web by Joel Hirtle
|
BLD-Framing/Rough-in | 9/12/2019 | 9/12/2019 | 9/12/2019 | P | PASS |
Jim Storey
|
|
|
Phone #: ###-#### Inspection requested via web by Joel Hirtle
|
BLD-Framing/Rough-in | 9/12/2019 | 9/12/2019 | 9/12/2019 | A | CANC |
Jim Storey
|
|
|
check c/n items Inspection cancelled from web by: Joel Hirtle
|
BLD-Framing/Rough-in | 9/11/2019 | 9/11/2019 | 9/12/2019 | P | PART |
Dave Hannah
|
|
|
I have documentation of nails required for the hanger, i will leave on site.
HGUS 7.25/12 face, (56 nails, 0.162x 3-1/2 ) joist (20 nails, 0.162 x 3-1/2 )
Phone #: ###-#### Inspection requested via web by Joel Hirtle ok to insulate but I need jim to check off his c/n itmes rescheduled for tomorrow am after talking with contractor
|
BLD-Framing/Rough-in | 9/9/2019 | 9/10/2019 | 9/10/2019 | A | NR |
Jim Storey
|
|
|
Phone #: ###-#### Inspection requested via web by Joel Hirtle
|
BLD-Framing/Rough-in | 9/8/2019 | 9/9/2019 | 9/9/2019 | A | FAIL |
Jim Storey
|
|
|
Phone #: ###-#### Inspection requested via web by Joel Hirtle c/n posted
|
Fees Due Hold | 8/30/2019 | | 8/30/2019 | | DONE |
|
|
|
|
BLD-Wall Bracing | 8/27/2019 | 8/28/2019 | 8/28/2019 | A | PASS |
Jim Storey
|
|
|
Phone #: ###-#### Inspection requested via web by Joel Hirtle
|
Routing - MECHANICAL | 8/28/2019 | | 8/28/2019 | | PASS |
Chad Schwendiman
|
|
|
|
Plan Modification Accepted | | | 8/27/2019 | | DONE |
|
|
|
manual J
|
BLD-Foundation | 8/8/2019 | 8/9/2019 | 8/9/2019 | P | PASS |
Jim Storey
|
|
|
Phone #: 2089495359 >> Inspection requested via mobile web by Ricardo
|
BLD-Footing | 8/7/2019 | 8/8/2019 | 8/8/2019 | P | PASS |
Jim Storey
|
|
|
Ricrado Phone #: ###-####
|
Inspection Record Card- Bld | | | 6/6/2019 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 6/6/2019 | | DONE |
|
|
|
|
OVERRIDE | | | 5/21/2019 | | |
|
|
|
|
Plan assigned to (RDP) | 5/9/2019 | 5/9/2019 | 5/21/2019 | | DONE |
Rob Patrick
|
|
|
05/21 sfd L1 ePlan...05/17 1st done Failed
|
Routing - PLAN CHECK | 5/21/2019 | | 5/21/2019 | | PASS |
Rob Patrick
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/21/2019 | | DONE |
Rob Patrick
|
|
|
|
Permit Ready to Issue | | | 5/21/2019 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 5/9/2019 | | 5/17/2019 | | FAIL |
Rob Patrick
|
|
|
|
1st review completed | | | 5/17/2019 | | FAIL |
Rob Patrick
|
|
|
Corrections Req'd
|
Route to Impact Fee Review | 5/8/2019 | 5/11/2019 | 5/9/2019 | | PASS |
Shannon Cade
|
|
|
Initial residential review of new SFD permits requested for now.
|
Plan assigned to (BJM) | 5/8/2019 | 5/8/2019 | 5/9/2019 | | DEFR |
Brian McGowan
|
|
|
|
Routing - MECHANICAL | 5/8/2019 | | 5/8/2019 | | PASS |
Chad Schwendiman
|
|
|
|
Routing - PLANNING | 5/8/2019 | | 5/8/2019 | | PASS |
Ethan Mansfield
|
|
|
|
Routing - Addressing | 5/8/2019 | | 5/8/2019 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 5/8/2019 | | 5/8/2019 | | PASS |
Morgan Webb
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 5/8/2019 | | DONE |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 5/8/2019 | | DONE |
|
|
|
|
Intake Approval | | | 5/8/2019 | | PASS |
|
|
|
|
Application received | | | 5/7/2019 | | DONE |
|
|
|
Application submitted via PDS Online on May 7 2019 4:25PM
|