Second Notice | | 2/16/2020 | 2/19/2020 | | DONE |
|
|
|
This permit finaled on the web by Josh Bennett
|
First Notice | 1/16/2020 | 1/16/2020 | 2/6/2020 | | DONE |
Jim Storey
|
|
|
mailed 2-7-20
|
BLD-Final | 1/14/2020 | 1/16/2020 | 1/16/2020 | A | PASS |
Jim Storey
|
|
|
Please check in at front counter for access to the building. This is a secure building. Please contact Josh Bennett with any questions at ###-####. Phone #: ###-#### Inspection requested via web by Josh Bennett
|
DOC - Permit Finaled | 1/16/2020 | 1/16/2020 | 1/16/2020 | P | PASS |
Jim Storey
|
|
|
|
FIRE-Final Inspection | 1/9/2020 | 1/9/2020 | 1/9/2020 | A | PASS |
Jim Page
|
|
|
No fire sprinkler modifications, fire alarm inspection is complete, life fire safety inspection for scope of work is complete, signatures provided on permit sign off card.
|
BLD-Final | 12/18/2019 | 12/20/2019 | 12/20/2019 | A | NR |
Brandon Shaw
|
|
|
Need Fire final...
|
BLD-Framing/Rough-in | 10/22/2019 | 10/24/2019 | 10/24/2019 | P | PASS |
Jim Storey
|
|
|
rough in -Brian Phone #: ###-####
|
Issue PAID IN FULL permit | | | 8/8/2019 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 8/8/2019 | | DONE |
|
|
|
|
Plan assigned to (M_H) | 5/14/2019 | | 5/31/2019 | | DONE |
Michael Hanson
|
|
|
05/31 #518 L2 ePlan - CBP HVAC Upgrades
|
Routing - PLAN CHECK | 5/14/2019 | | 5/31/2019 | | PASS |
Michael Hanson
|
|
|
|
1st review completed | | | 5/31/2019 | | DONE |
Michael Hanson
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/31/2019 | | DONE |
Michael Hanson
|
|
|
|
Permit Ready to Issue | | | 5/31/2019 | | DONE |
|
|
|
MET JBENNETT@ACCOSERVICE.COM
NEED
GC FORM
REVISED VALUE
|
Routing - FIRE | 5/14/2019 | 5/14/2019 | 5/22/2019 | | PASS |
Mark Scharfen
|
|
|
Fire review complete. Made notations on plans, no report needed. Passed review.
|
Routing - MECHANICAL | 5/14/2019 | | 5/20/2019 | | PASS |
Troy James
|
|
|
|
Intake Approval | | | 5/10/2019 | | FAIL |
Julie Romig
|
|
|
Need Code Analysis on cover sheet.
|
Intake Approval | | | 5/10/2019 | | FAIL |
Julie Romig
|
|
|
Need signature on revised G0.0.
|
Plan Reviewer's activity | | | 5/10/2019 | | |
|
|
|
Drawings include multiple phases which will all be completed under this permit per the Eric Terada's prescreeen comments in ePlanReview on 05/10/19.
|
Application received | | | 5/9/2019 | | DONE |
|
|
|
Application submitted via PDS Online on May 9 2019 6:04AM
|