Second Notice | | 12/6/2019 | 12/30/2019 | | DONE |
|
|
|
mailed 1-1-20
|
First Notice | | 11/25/2019 | 11/26/2019 | | DONE |
|
|
|
mailed 12-2-19
|
BLD-Final | 11/15/2019 | 11/15/2019 | 11/15/2019 | P | PASS |
Dave Hannah
|
|
|
jacob Phone #: ###-####
|
FIRE-Final Inspection | 11/15/2019 | 11/15/2019 | 11/15/2019 | P | PASS |
Jim Page
|
|
|
Previously noted items have been corrected, fire sprinkler inspection is complete, fire alarm inspection is complete, fire extinguishers are placed with current inspection tags. Final life fire safety inspection for area of work complete, signatures provided on permit sign off card for associated trades.
|
Permanent Occupancy | | | 11/15/2019 | | DONE |
|
|
|
|
BLD-Final | 11/8/2019 | 11/12/2019 | 11/12/2019 | P | NR |
Brandon Shaw
|
|
|
Failed Fire/Life... No other issues...
|
FIRE-Final Inspection | 11/8/2019 | 11/12/2019 | 11/12/2019 | A | FAIL |
Jim Page
|
|
|
Provided fire alarm modifications as discussed, a seperate per it is required for fire aalrm modifications.
TJ Phone #: ###-####
|
Print Occupancy Form | | | 10/29/2019 | | DONE |
|
|
|
|
BLD-Ceiling Grid Inspection | 10/24/2019 | 10/25/2019 | 10/25/2019 | A | PASS |
Jim Storey
|
|
|
Call for access- Jake Phone #: ###-####
|
Plan assigned to (JAR) | 6/11/2019 | 6/11/2019 | 7/31/2019 | | DONE |
Julie Romig
|
|
|
07/26 - 2nd Rev - 1st Rev Comp - L3 Lost Shack Sushi Bar
|
Routing - PLAN CHECK | 7/22/2019 | | 7/31/2019 | | PASS |
Julie Romig
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/31/2019 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 7/31/2019 | | DONE |
|
|
|
met
Need GC
Need rev cert of val 7-31-19 pdf
|
Print Occupancy Form | | | 7/31/2019 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 7/31/2019 | | DONE |
|
|
|
|
Routing - MECHANICAL | 7/22/2019 | | 7/22/2019 | | PASS |
Troy James
|
|
|
|
Routing - PLUMBING | 7/22/2019 | | 7/22/2019 | | PASS |
Daryl Spivey
|
|
|
Per plan and ISPC.
|
Routing - PUBLIC WORKS | 7/22/2019 | | 7/22/2019 | | PASS |
Morgan Webb
|
|
|
SWR READY TO BE PAID. SENT TO ENVIRONMENTAL
|
Routing PW Environmental | 7/22/2019 | | 7/22/2019 | | PASS |
Rick Christenson
|
|
|
Connecting to Existing GW line
|
Route to Impact Fee Review | 7/3/2019 | 7/6/2019 | 7/5/2019 | | PASS |
Eric Bilimoria
|
|
|
Review requested for Commercial Permit
|
Routing - FIRE | 6/11/2019 | 6/11/2019 | 7/3/2019 | | PASS |
Mark Scharfen
|
|
|
Completed fire review 07.03.2019. Uploaded rev_fire 07.03.2019.pdf.
|
1st review completed | | | 7/3/2019 | | FAIL |
Julie Romig
|
|
|
|
Routing - PLAN CHECK | 6/11/2019 | | 7/3/2019 | | FAIL |
Julie Romig
|
|
|
|
Routing - MECHANICAL | 6/11/2019 | | 6/14/2019 | | PASS |
Troy James
|
|
|
|
Routing - Design Review | 6/11/2019 | | 6/12/2019 | | PASS |
Katelyn Menuge
|
|
|
DRH19-00234
|
Routing - PLANNING | 6/11/2019 | | 6/12/2019 | | PASS |
Nicolette Womack
|
|
|
|
Routing - PUBLIC WORKS | 6/11/2019 | | 6/12/2019 | | PASS |
Angela Hardy
|
|
|
|
Routing PW Environmental | 6/12/2019 | | 6/12/2019 | | PASS |
Terry Alber
|
|
|
Passed per ePlanReview
|
Routing - Addressing | 6/11/2019 | | 6/11/2019 | | PASS |
Doug Chausow
|
|
|
|
Routing - PLUMBING | 6/11/2019 | | 6/11/2019 | | FAIL |
Daryl Spivey
|
|
|
Need a waste and vent plan submitted to review.
|
Intake Approval | | | 6/10/2019 | | PASS |
|
|
|
|
Plan Reviewer's activity | | | 6/8/2019 | | PASS |
|
|
|
Plan intake review approved
|
Intake Approval | | | 6/3/2019 | | FAIL |
|
|
|
(6-3-19) The required Planning Document was not uploaded. Upload that document. CJW
|
Intake Approval | | | 5/31/2019 | | FAIL |
|
|
|
(5-31-19) Refer to the circled item in the plan intake checklist. Resolve the item as directed. CJW
|
Application received | | | 5/9/2019 | | DONE |
|
|
|
Application submitted via PDS Online on May 9 2019 8:26AM
|