BLD-Aging Inspection | 4/3/2020 | 4/3/2020 | 4/7/2020 | | PEND |
Tell Riley
|
|
|
|
Plan assigned to (BJM) | 5/10/2019 | 5/10/2019 | 5/20/2019 | | DONE |
Brian McGowan
|
|
|
1st Review Complete - CSN19-00119
|
Routing - PLAN CHECK | 5/20/2019 | | 5/20/2019 | | PASS |
Brian McGowan
|
|
|
|
1st review completed | | | 5/20/2019 | | DONE |
Brian McGowan
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/20/2019 | | DONE |
Brian McGowan
|
|
|
|
Permit Ready to Issue | | | 5/20/2019 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 5/20/2019 | | DONE |
|
|
|
|
Intake Approval | | | 5/15/2019 | | FAIL |
Brian McGowan
|
|
|
Attachment details are for a concrete of cinder block wall and is not legible. Special inspections mayu be required.
|
Application received | | | 5/9/2019 | | DONE |
|
|
|
Application submitted via PDS Online on May 9 2019 10:39AM
|