Information based on query as of Wednesday, July 24, 2024.
Permit Information
Permit NumberBLD19-01665
StatusFinaled
Name TK CONSTRUCTION & CONTRACTING LLC
Site Address 119 S BROADWAY AVE
Project NameStretchlab
Customer Number 
ePlanReviewYes
Description
(STRETCHLAB) Permit to modify an existing 1,040 sq. ft. tenant space in a 4,893 sq. ft. building. Tenant Occupancy is based on Exercise Rooms with a Net of 760 sq. ft. as per plans (760/50=15.2), however, since only (1) Restroom is present, the Occupant load shall be 15. Approval is contingent upon adhering to the approved plans on file. Work to include: New paint and finishes. Electrical work and interior finishes to be in compliance with Ch. 8 of the 2015 IBC. This building is fully Fire Sprinklered with an approved Fire Alarm system. Any alterations or modifications to the buildings Fire Sprinkler or Fire Alarm system WILL REQUIRE A SEPARATE PERMIT and shall be installed per NFPA 13 & NFPA 72 as regulated by the Boise Fire Department.Minor work. (Previous Permit was BLD15-04008, Shell and Core Permit was BLD15-01965) ***BJM***
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Third Notice 8/10/20198/27/2019 DONE
This permit finaled on the web by Todd Kurns
Second Notice 7/20/20198/5/2019 DONE
mailed 8-5-19
First Notice 6/27/20197/10/2019 DONE
mailed 7-11
BLD-Final6/17/20196/17/20196/17/2019APASS
DetailsDave Hannah
Dave,
Call me when on way. Thx. Todd Phone #: ###-#### Inspection requested via web by Todd Kurns
Permanent Occupancy  6/17/2019 DONE
FIRE-Final Inspection6/13/20196/13/20196/13/2019PPASS
DetailsJim Page
No fire sprinkler modifications, no fire alarm modifications, fire extinguisher will be placed in discussed location and will be inspected/tagged accordingly. Final life fire safety inspection for area of work complete.

Jim,

Call me when on way.

Thx
Todd Phone #: ###-#### Inspection requested via web by Todd Kurns
Issue PAID IN FULL permit  5/22/2019 DONE
Print Occupancy Form  5/22/2019 DONE
Print Occupancy Form  5/22/2019 DONE
Plan assigned to (BJM)5/14/20195/14/20195/16/2019 DONE
DetailsBrian McGowan
05/20- #518 L1 ePlan, StretchLab TI
Routing - PLAN CHECK5/14/2019 5/16/2019 PASS
DetailsBrian McGowan
1st review completed  5/16/2019 DONE
DetailsBrian McGowan
PLANS/APPL TAKEN TO FRONT DESK  5/16/2019 DONE
DetailsBrian McGowan
Permit Ready to Issue  5/16/2019 DONE
Need GC
Need rev cert of val
Routing - PUBLIC WORKS5/14/2019 5/14/2019 PASS
DetailsAngela Hardy
Routing - Addressing5/14/2019 5/14/2019 PASS
DetailsDoug Chausow
Intake Approval  5/14/2019 PASS
DetailsMichael Hanson
Prescreen approved by M_H.
Intake Approval  5/13/2019 FAIL
DetailsMichael Hanson
Please provide fire extinguisher location.
Application received  5/10/2019 DONE
Application submitted via PDS Online on May 10 2019 9:27AM