OVERRIDE | | | 8/12/2020 | | |
|
|
|
|
Plan assigned to (CDM) | 7/31/2020 | 7/31/2020 | 8/12/2020 | | PASS |
Carl D Madsen
|
|
|
|
Routing - PLAN CHECK | 8/4/2020 | | 8/12/2020 | | PASS |
Carl D Madsen
|
|
|
|
Permit Ready to Issue | | | 8/12/2020 | | DONE |
|
|
|
plan mod approved
|
Routing - MECHANICAL | 8/4/2020 | | 8/4/2020 | | PASS |
Troy James
|
|
|
|
Plan Modification Accepted | | | 7/31/2020 | | DONE |
|
|
|
Added HVAC fire damper
|
BLD-Conference | 7/29/2020 | 7/30/2020 | 7/30/2020 | A | PASS |
Jim Storey
|
|
|
Please call prior to coming onsite Phone #: ###-#### Inspection requested via web by Cody Sandercock aproved fire stopping assembly for line sets.
|
BLD-Ceiling Grid Inspection | 7/15/2020 | 7/16/2020 | 7/16/2020 | A | NR |
Jim Storey
|
|
|
Phone #: 6786443014 >> Inspection requested via mobile web by Cody Sandercock
|
BLD-Wall cover | 7/9/2020 | 7/9/2020 | 7/9/2020 | P | PASS |
Jim Storey
|
|
|
Phone #: 6786443014 >> Inspection requested via mobile web by Cody Sandercock screw sch ok for rated walls// fire stopping not done at this time.
|
BLD-Wall cover | 6/5/2020 | 6/8/2020 | 6/8/2020 | A | PASS |
Jim Storey
|
|
|
Phone #: 6786443014 >> Inspection requested via mobile web by Cody Sandercock top of wall ok/ ok to start wallcover.
|
BLD-Framing/Rough-in | 5/27/2020 | 5/28/2020 | 5/28/2020 | A | PASS |
Jim Storey
|
|
|
As early as possible Phone #: 6786443014 >> Inspection requested via mobile web by Cody Sandercock/ framing of walls ok to top fof sliptrack
|
BLD-Other | 5/18/2020 | 5/19/2020 | 5/19/2020 | A | FAIL |
Jim Storey
|
|
|
Phone #: 6786443014 >> Inspection requested via mobile web by Cody Sandercock c/n provide ul head of wall detail or have plan reviewer c madsen aprove as built.
|
BLD-Conference | 4/23/2020 | 4/24/2020 | 4/24/2020 | P | PEND |
Jim Storey
|
|
|
Phone #: 6786443014 >> Inspection requested via mobile web by Cody Sandercock submittal for corridor design.
|
BLD-Conference | 4/15/2020 | 4/16/2020 | 4/16/2020 | A | PASS |
Jim Storey
|
|
|
Phone #: 6786443014 >> Inspection requested via mobile web by Cody Sandercock
|
BLD-Framing/Rough-in | 4/15/2020 | 4/16/2020 | 4/16/2020 | A | PASS |
Jim Storey
|
|
|
Phone #: 6786443014 >> Inspection requested via mobile web by Cody Sandercock hanger fur out and insulation ok.
|
BLD-Conference | 4/10/2020 | 4/13/2020 | 4/13/2020 | A | PASS |
Jim Storey
|
|
|
Phone #: 6786443014 >> Inspection requested via mobile web by Cody Sandercock roof insulation ok/ conf ok
|
FIRE-Conference | 4/9/2020 | 4/10/2020 | 4/10/2020 | A | CANC |
Troy Cobbley
|
|
|
Needed building inspector conference on the rated wall.
Phone #: 6786443014 >> Inspection requested via mobile web by Cody Sandercock
|
BLD-Framing/Rough-in | 4/8/2020 | 4/8/2020 | 4/8/2020 | P | PASS |
Dave Hannah
|
|
|
hanger ok
|
BLD-Conference | 4/7/2020 | 4/8/2020 | 4/8/2020 | P | PASS |
Dave Hannah
|
|
|
Phone #: 6786443014 >> Inspection requested via mobile web by Cody Sandercock
|
BLD-Conference | 4/3/2020 | 4/6/2020 | 4/6/2020 | A | DONE |
Dave Hannah
|
|
|
Phone #: 6786443014 >> Inspection requested via mobile web by Cody Sandercock
|
BLD-Conference | 4/2/2020 | 4/3/2020 | 4/3/2020 | A | DEFR |
Tony Young
|
|
|
Phone #: 6786443014 >> Inspection requested via mobile web by Cody Sandercock // called to defr for Monday
|
BLD-Conference | 4/1/2020 | 4/2/2020 | 4/2/2020 | A | CANC |
Jim Storey
|
|
|
Phone #: 6786443014 >> Inspection requested via mobile web by Cody Sandercock Inspection cancelled via mobile web on Thursday, April 02, 2020.
|
OVERRIDE | | | 3/23/2020 | | |
|
|
|
|
Meeting | | | 3/23/2020 | | DONE |
|
|
|
Per Angela Project Manager, We do not charge admin fees on deferred submittals. Taking off admin fee and changing status back to issued. ITD project.
|
CHANGE STATUS TO (ISS) | | | 3/23/2020 | | DONE |
|
|
|
Per Angie Project Manager: Deferred Submittal changing status to issued. No fees are due
|
Permit Ready to Issue | | | 3/23/2020 | | DONE |
|
|
|
**PLAN MOD - DO NOT REISSUE**
|
Plan assigned to (CDM) | 1/13/2020 | 1/13/2020 | 3/20/2020 | | PASS |
Carl D Madsen
|
|
|
|
Routing Off Site - STRUCTURAL | 3/13/2020 | | 3/20/2020 | | PASS |
Carl D Madsen
|
|
|
|
BLD-Concrete | 3/6/2020 | 3/11/2020 | 3/11/2020 | P | PASS |
Jim Storey
|
|
|
Cody Phone #: ###-#### slab west rebar vappor barrior and primetor insulation ok// wall and roof insulation 30/35 ok per envolope.
|
Routing Off Site - STRUCTURAL | 2/19/2020 | | 3/11/2020 | | FAIL |
Carl D Madsen
|
|
|
|
Routing - PLUMBING | 2/27/2020 | | 2/27/2020 | | PASS |
Dan Ediger
|
|
|
|
Routing - PLAN CHECK | 2/19/2020 | | 2/27/2020 | | PASS |
Carl D Madsen
|
|
|
|
BLD-Footing | 2/3/2020 | 2/4/2020 | 2/4/2020 | A | PEND |
Dave Hannah
|
|
|
Cody Phone #: ###-####14 needs to clean mud off rebar needs to get frost out of ground, spec. inspector needs to ok final aproval
|
CHANGE STATUS TO (ISS) | | | 1/13/2020 | | DONE |
|
|
|
|
(F) Reprint permit | | | 1/13/2020 | | DONE |
|
|
|
|
Plan Modification Accepted | | | 1/13/2020 | | DONE |
|
|
|
Deferred submittal (per angie). Submit pre-engineered metal building plans for the Idaho Transportation Aeronautics office Building. (see letter in documents)
|
OVERRIDE | | | 1/10/2020 | | |
|
|
|
|
Permit Ready to Issue | | | 1/10/2020 | | DONE |
|
|
|
**DO NOT REISSUE - PLAN MOD**
|
Routing Off Site - STRUCTURAL | 1/7/2020 | | 1/10/2020 | | PASS |
Carl D Madsen
|
|
|
1/2 of engineering fees billed as this was a plan mod/deferred submittal.
|
BLD-Concrete | 1/7/2020 | 1/8/2020 | 1/8/2020 | A | PASS |
Jim Storey
|
|
|
AL - vapor barrier Phone #: ###-####
|
Routing - PLAN CHECK | 12/12/2019 | | 12/31/2019 | | PASS |
Carl D Madsen
|
|
|
deferred submittal
|
Routing Off Site - STRUCTURAL | 12/16/2019 | | 12/31/2019 | | FAIL |
Carl D Madsen
|
|
|
CH2M Routed back to applicant for correction 12/31/2019 CDM
|
BLD-Footing | 12/23/2019 | 12/24/2019 | 12/24/2019 | A | PASS |
Brandon Shaw
|
|
|
concrete at 8:30 am // Al Phone #: ###-####
|
BLD-Footing | 12/16/2019 | 12/17/2019 | 12/17/2019 | P | FAIL |
Jim Storey
|
|
|
Al Phone #: ###-#### ground frozen/ bare exposer to close to grade// si to address if placed.
|
Plan Modification Accepted | | | 12/12/2019 | | |
Carl D Madsen
|
|
|
Deferred submittal for pre-engineered metal building, phase 1, hangar
|
BLD-Footing | 12/10/2019 | 12/11/2019 | 12/11/2019 | P | PASS |
Jim Storey
|
|
|
Al Phone #: ###-#### 6ft east/west
|
BLD-Footing | 12/4/2019 | 12/5/2019 | 12/5/2019 | A | PASS |
Jim Storey
|
|
|
Al Phone #: ###-#### rebar ok si onsite cmu wall ft
|
Issue PAID IN FULL permit | | | 10/1/2019 | | DONE |
|
|
|
|
Print Occupancy Form | | | 10/1/2019 | | DONE |
|
|
|
|
OVERRIDE | | | 9/23/2019 | | |
|
|
|
|
Permit Ready to Issue | | | 9/23/2019 | | DONE |
|
|
|
MET
Need
Revised Cert of Value (IN THERE 9/20/19)
|
Plan assigned to (CDM) | 5/22/2019 | 5/24/2019 | 9/20/2019 | | PASS |
Carl D Madsen
|
|
|
ITD Aeronautics Hangar/Office
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/20/2019 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 9/16/2019 | | 9/16/2019 | | PASS |
Carl D Madsen
|
|
|
|
Routing - PLAN CHECK | 9/9/2019 | | 9/16/2019 | | PASS |
Carl D Madsen
|
|
|
|
Routing - MECHANICAL | 9/9/2019 | | 9/11/2019 | | PASS |
Troy James
|
|
|
Approved pending building review approval for fire damper requirements at corridor.
|
Routing - PLANNING | 9/9/2019 | | 9/10/2019 | | PASS |
Karla Nelson
|
|
|
Planter islands have been waived for this case.
|
Routing PW Street Lights | 9/10/2019 | | 9/10/2019 | | PASS |
Tom Marshall
|
|
|
|
Routing PW Street Lights | 9/9/2019 | | 9/9/2019 | | FAIL |
Tom Marshall
|
|
|
|
Plan resubmittals received | | | 9/9/2019 | | DONE |
Joe Bruce
|
|
|
|
Plan resubmittals received | | | 9/6/2019 | | FAIL |
Joe Bruce
|
|
|
Please provide the following before your resubmittal is accepted.
1) Sheets M01, M21, and M61 have a stamp by the registered design professional that is black and not legible when printed in grayscale/monochrome. Please revise the engineers stamp to be legible. Engineers stamp on original submittal was legible.
2) Sheet A0.1 is blank and appears to be missing information. Resubmit this sheet with appropriate information.
|
Routing - FIRE | 8/23/2019 | 8/23/2019 | 8/26/2019 | | PASS |
Mark Scharfen
|
|
|
08/29-ITD Hanger Resubmittal review completed 08.26.2019. Uploaded rev_fire 08.26.2019.pdf.
|
Routing - PLAN CHECK | 8/23/2019 | | 8/24/2019 | | FAIL |
Carl D Madsen
|
|
|
This resubmittal was only for Fire review. Additional resubmittals for mechanical, green building and street lights are pending.
|
Routing - PLAN CHECK | 7/30/2019 | | 8/17/2019 | | FAIL |
Carl D Madsen
|
|
|
|
Routing Off Site - STRUCTURAL | 7/30/2019 | | 8/17/2019 | | PASS |
Carl D Madsen
|
|
|
|
Routing PW Drainage | 7/31/2019 | | 8/8/2019 | | PASS |
Brian Murphy
|
|
|
|
Routing - FIRE | 7/30/2019 | 7/30/2019 | 8/6/2019 | | FAIL |
Mark Scharfen
|
|
|
08.06.2019-Completed 2nd review. Uploaded rev_fire 08.06.2019.pdf and emailed architect.
|
Routing PW Street Lights | 7/31/2019 | | 7/31/2019 | | FAIL |
Tom Marshall
|
|
|
|
Routing PW Sewer Design | 7/31/2019 | | 7/31/2019 | | PASS |
DeAnn Brown
|
|
|
|
Route to Impact Fee Review | 7/2/2019 | 7/5/2019 | 7/2/2019 | | PASS |
Shannon Cade
|
|
|
Review requested for Commercial Permit
|
Routing - FIRE | 5/22/2019 | 5/22/2019 | 7/2/2019 | | FAIL |
Mark Scharfen
|
|
|
07.02.2019-Completed fire review. Uploaded rev_fire 07.02.2019.pdf and emailed applicant.
|
1st review completed | | | 7/2/2019 | | DONE |
|
|
|
|
Routing Off Site - STRUCTURAL | 5/24/2019 | | 6/28/2019 | | FAIL |
Carl D Madsen
|
|
|
CH2M Hill
|
Routing - PLAN CHECK | 5/22/2019 | | 6/28/2019 | | FAIL |
Carl D Madsen
|
|
|
|
Routing - MECHANICAL | 5/22/2019 | | 6/12/2019 | | PASS |
Troy James
|
|
|
|
Routing - PLUMBING | 5/22/2019 | | 6/12/2019 | | FAIL |
Dan Ediger
|
|
|
See detail for Sand and oil separator does not meet code.
The duplex ejection system requires 3" minimum pumps and discharge line.
|
Routing PW Sewer Design | 5/28/2019 | | 6/12/2019 | | PASS |
DeAnn Brown
|
|
|
2" pressure service is a private sewer facility and must meet the plumbing code requirements.
|
Routing PW Environmental | 5/28/2019 | | 6/12/2019 | | PASS |
Terry Alber
|
|
|
Approved with no fire suppression foam system. Should fire suppression foam system be installed, automatic valve downstream of oil/sediment interceptor required.
|
Routing - PLANNING | 5/22/2019 | | 6/4/2019 | | PASS |
Karla Nelson
|
|
|
Passed with the condition that the landscape plan be modified to include internal planter islands for every grouping of parking that exceeds 10 spaces. Terminal planters shall be provided a the ends of rows. Landscape planters shall be a minimum of 8' and shall be landscaped with at least 1 tree and shall be covered with shrubs or other vegetative groundcover.
Note on plan call for a maximum height of 76'. The M-1 district only allows for heights of 55' any structure or equipment in excess of 55' will require a conditional use permit.
|
Routing - PLUMBING | 9/23/2019 | | 6/3/2019 | | PASS |
Daryl Spivey
|
|
|
Per plan and ISPC.
|
Routing - Addressing | 5/22/2019 | | 5/31/2019 | | PASS |
Doug Chausow
|
|
|
Corrected address to 1390 W Gowen Rd
|
Routing - PUBLIC WORKS | 5/22/2019 | | 5/31/2019 | | PASS |
Angela Hardy
|
|
|
|
Routing - Erosion and Sediment | 5/22/2019 | | 5/30/2019 | | PASS |
Andy J. Long
|
|
|
SWPPP/ESC plan approved. Contractor and ESC Responsible Person TBD. Site preparation inspection is required.
|
Routing PW Solid Waste | 5/28/2019 | | 5/29/2019 | | PASS |
Peter J. McCullough
|
|
|
|
Routing PW Street Lights | 5/28/2019 | | 5/29/2019 | | FAIL |
Tom Marshall
|
|
|
Need street light plan for Gowen Rd.
|
Intake Approval | | | 5/22/2019 | | PASS |
Joe Bruce
|
|
|
Intake approval/fees paid 5/22/19
|
Intake Approval | | | 5/14/2019 | | FAIL |
Joe Bruce
|
|
|
Provide the following items to complete the prescreen process:
1) Plan sheets do not have the required space reserved for City approval stamps as specified in the Electronic Plans Submittal Standards. Revise sheets with a blank 4” x 2” space located 3” off the right sheet edge to allow for the title block. Verify ALL plan sheets have the required space for city approval stamp.
2) Site Specific Fire Flow at the fire hydrant letter is required from Suez Water. Please email: katie.birkenstein@suez.com for your request to receive the required letter for plan review. Upload this document into the documents folder.
3) Form #310 – “Statement of Special Inspections” is required to be completed by the structural engineer for the metal deck and welding. Provide this information on the form.
4) The prefabricated metal building do not appear to be submitted. Please submit the metal building drawings as required. A letter signed by Jason Blais (Building Official) might be accepted if a deferred submittal is desired.
5) The permanent operation & maintenance agreement form is required to be mailed or dropped off to Brian Murphy. Please contact Brian Murphy at ###-#### regarding this requirement.
6) Provide an Erosion & Sediment Control Narrative for this project. No document could be locate in the documents folder.
7) The heating and cooling load calculations could not be found attached to the plans. Please provide the heating and cooling load calcs on the plans or submitted as separate documents.
|
Application received | | | 5/10/2019 | | DONE |
|
|
|
Application submitted via PDS Online on May 10 2019 12:17PM
|
Routing PW Drainage | 5/28/2019 | | | | FAIL |
Brian Murphy
|
|
|
need airort o and m
|